Cable & Conduit Routes

How ProposalGen estimated cable lengths — tier by tier, against the customer's site-development drawings.

Cable estimation is the highest-impact assumption in the proposal — get it wrong and the BOQ swings. I bucketed each route into a context tier, picked a typical length per tier with a stated range, and tied the basis to the depot site-development plans the customer provided. Walk it tier by tier and eyeball whether the buildings I assigned to each tier actually fit that distance bucket on the drawing.
Substep 1 of 7

Tier · ADMIN-INTERNAL

A3 · Op#11

Cable within Admin Building (OCC ↔ FCCR ↔ CER ↔ ECB internal)

Typical30 mRange1550 m

Basis

Typical office/control-room building internal vertical + horizontal cable runs

Applies to (4)

  • Workstation power feed (UPS-to-WS-PC)
  • OCC L2 switch to CER L2 switch (REC interface per TOR §4.7)
  • Workstation control & communication cable (BOQ row 4)
  • FCCR internal cabling (BOQ row 10)

Drawing references

Provisional mapping — page references hand-authored after the agent run. Future projects will capture this automatically once the scaled-cable-routes playbook patch lands.

1 / 7

Why I made these choices

7 decisions