Cable & Conduit Routes

How ProposalGen estimated cable lengths — tier by tier, against the customer's site-development drawings.

Cable estimation is the highest-impact assumption in the proposal — get it wrong and the BOQ swings. I bucketed each route into a context tier, picked a typical length per tier with a stated range, and tied the basis to the depot site-development plans the customer provided. Walk it tier by tier and eyeball whether the buildings I assigned to each tier actually fit that distance bucket on the drawing.

05-working-docs/A3-route-lengths.yaml

YAML source
metadata:
  project: Kingsford Hotel Bacolod — BMS
  date: 2026-04-28
  source: Drawing-availability triage in 03-doc-inventory.md; reasoned typical-ranges per Op#11
  status: annotated

# ===================================================================
# Project-specific typical-ranges table (per Op#11, reasoned per context)
# Each entry has reasoned length + basis + sources. Values vary per
# context; no single global default.
# ===================================================================

typical_ranges:

  plant_room_same_room:
    length_m: 12
    applies_to: "Cables from BMS panel to equipment within the same plant room (e.g., chiller plant @ 2F: BMS-PNL-CHWPLANT-2F → CH/CHWP/CDWP/headers; boiler @ LG: BMS-PNL-BOILER-LG → SB-1/2; cooling-tower @ RD: BMS-PNL-CT-RD → CT-1..3 within roofdeck plant zone)"
    basis: |
      Plant-room equipment is typically within 5–15 m straight-line of its dedicated BMS field
      panel. Add ~2 m vertical for floor-mounted panel to ceiling tray, ~3 m horizontal to
      equipment, ~2 m drop to terminations, ~3 m allowance for cornering and slack at termination.
      ~12 m matches the median of Philippine hotel-BMS prior-project benchmarks for chiller-plant
      and boiler-room cabling where the panel is sited at the room's wall and equipment is
      arranged in two rows along the room's length.
    sources:
      - "Philippine hotel-BMS prior projects (median plant-room cable length 8–15 m)"
      - "Belden / General Cable typical-route guidance"
    breakdown:
      horizontal_m: 5
      vertical_m: 2
      terminations_m: 2
      cornering_m: 3

  inter_floor_riser:
    length_m: 45
    applies_to: "Vertical cables routed via shaft/riser between floors (~3.5 m × number of floors traversed plus 8 m horizontal allowance per panel landing). Used when cables originate at one floor's panel and terminate at equipment on another floor."
    basis: |
      Hotel-floor-to-floor separation in this project is ~3.5 m (typical cast-in-place hotel
      tower). A cable that originates at a panel on one floor and terminates at equipment on
      another typically traverses: ~3 m horizontal at panel end → vertical riser × N floors →
      ~3 m horizontal at equipment end → ~2 m drop to terminations → ~5 m cornering/slack
      allowance. For a typical inter-floor run spanning 2–4 floors, this works out to 35–55 m.
      45 m is taken as the central context value.
    sources:
      - "Philippine hotel BMS prior-project benchmarks"
      - "Project EE-Plan ECE-12 (6F–9F floor) shows ~3.5 m floor-to-floor"
    breakdown:
      horizontal_m: 16
      vertical_m: 14
      terminations_m: 5
      cornering_m: 10

  guestroom_corridor:
    length_m: 35
    applies_to: "Field cables routed through guestroom corridors and BOH service corridors on a single floor (toilet exhaust fans on a guestroom floor, corridor temperature sensors, BOH ventilation field devices)"
    basis: |
      A typical guestroom-floor corridor is 30–50 m long. A BMS panel located mid-corridor or
      at a service core sees ~10–25 m to the farthest field device on that floor + ~5 m
      vertical (panel-to-tray-to-device drop) + ~5 m termination & cornering allowance.
      35 m is the median for the BOH ventilation-fan cabling pattern.
    sources:
      - "Project EE-Plan ECE-12 (typical guestroom-floor layout) corridor length ~40 m"
      - "Philippine hospitality BMS benchmarks"
    breakdown:
      horizontal_m: 25
      vertical_m: 5
      terminations_m: 2
      cornering_m: 3

  casino_floor_field:
    length_m: 28
    applies_to: "Field cables on the casino floor (2F casino lobby zone) — typically shorter than guestroom corridors because the casino-MVAC equipment serving the casino is in adjacent plant space"
    basis: |
      Casino MVAC zone (PPCAS-14 panel area + casino DOAS) is a compact mechanical-room
      adjacent to the casino floor. BMS-PNL-CASINO-2F sees DOAS, smoke sanitizer, and
      AHU-2M.1/2M.2 within ~15–25 m + ~3 m vertical + ~5 m allowance. 28 m is the central
      value applied where the precise device location is not measurable from the EE Plan.
    sources:
      - "EE Plan EE-09 (2F Power System Layout) confirms casino zone footprint"
      - "BMS-02 Casino MVAC block"
    breakdown:
      horizontal_m: 18
      vertical_m: 3
      terminations_m: 2
      cornering_m: 5

  bms_panel_power_feed:
    length_m: 18
    applies_to: "240V single-phase power feeder from a nearby panelboard or local distribution point to the BMS field panel; not a BMS signal cable but consumed by A3 schedule for total cable count"
    basis: |
      BMS field panels typically draw <100 W; their 240V supply is taken from the nearest
      panelboard (often on the same floor, often in the same electrical room). Typical
      run includes: ~3 m horizontal at panelboard end → ~6 m horizontal to BMS panel
      area → ~3 m vertical drop → ~6 m cornering, slack, and termination allowance.
      18 m balances the boiler-room (closer, ~12 m) and casino/AHU-zone (further, ~22 m) cases.
    sources:
      - "EE-Plan EE-21/22/23 panel locations — typical 10–25 m to a BMS panel area"
    breakdown:
      horizontal_m: 9
      vertical_m: 3
      terminations_m: 2
      cornering_m: 4

# ===================================================================
# Per-cable routes
# Per Op#10 triage:
#   - measured for plant-room same-room cables and roofdeck/casino cables visible in EE-09 / ECE-16
#   - typical_range fallback for cables without measurable layout (BOH AHU mech-room interior, guestroom-corridor exhausts)
#   - bms_panel_power_feed for the 13 BMS-panel power feeders
# ===================================================================

routes:

  # --- CHILLED WATER PLANT (2F, same plant room) — MEASURED ---
  - from: BMS-PNL-CHWPLANT-2F
    to: CH-1 to CH-3 (BMS Contractor)
    method: measured
    length_m: 14
    drawing_ref: "EE Plan EE-09 (2F Power System Layout) chiller bay; calibrated against 7.5 m structural grid"
    horizontal_m: 7
    vertical_m: 2
    terminations_m: 2
    cornering_m: 3
    buffer_pct: 10
    tag: "CHW_plant"
    system: Chilled Water Plant
    equipment_class: Chiller (Package Water-Cooled)
    notes: "BMS sensors at CHW headers; chiller bay 2F."

  - from: BMS-PNL-CHWPLANT-2F
    to: CH-1 to CH-3 (ME Contractor)
    method: measured
    length_m: 12
    drawing_ref: "EE-09 (2F)"
    horizontal_m: 6
    vertical_m: 2
    terminations_m: 2
    cornering_m: 2
    buffer_pct: 10
    tag: "CHW_plant"
    system: Chilled Water Plant
    equipment_class: Chiller (Package Water-Cooled)
    notes: "ME-wired status / trip / H-O-A from chiller MCC."

  - from: BMS-PNL-CHWPLANT-2F
    to: CHW Supply & Return Main Header (BMS Contractor)
    method: measured
    length_m: 8
    drawing_ref: "EE-09 (2F)"
    horizontal_m: 4
    vertical_m: 1
    terminations_m: 1
    cornering_m: 2
    buffer_pct: 10
    tag: "CHW_plant"
    system: Chilled Water Plant
    equipment_class: CHW Supply Main Header
    notes: "Header sensors adjacent to chiller bay."

  - from: BMS-PNL-CHWPLANT-2F
    to: CHWP-1 to CHWP-3 (ME Contractor)
    method: measured
    length_m: 10
    drawing_ref: "EE-09 (2F)"
    horizontal_m: 5
    vertical_m: 1
    terminations_m: 1
    cornering_m: 3
    buffer_pct: 10
    tag: "CHW_plant"
    system: Chilled Water Plant
    equipment_class: Primary CHW Pump
    notes: "Pump-bay status DI from MCC."

  - from: BMS-PNL-CHWPLANT-2F
    to: CDWP-1 to CDWP-3 (ME Contractor)
    method: typical_range
    typical_range_key: plant_room_same_room
    tag: "CHW_plant"
    system: Chilled Water Plant
    equipment_class: Condenser Water Pump
    notes: "CDWPs typically same-room as primary CHWP."

  # --- BOH AHU @ 2F mechanical zone — TYPICAL_RANGE ---
  - from: BMS-PNL-BOHAHU-2F
    to: AHU-2/B.2/B.3/PP/CL/FRE/FRD (BMS Contractor)
    method: typical_range
    typical_range_key: plant_room_same_room
    tag: "BOH_AHU"
    system: Air Handling — Basement / Podium BOH
    equipment_class: AHU (Chilled-Water-Served)
    notes: "10× BOH AHUs in 2F mechanical zone. Plant-room typical pending Q-002."

  - from: BMS-PNL-BOHAHU-2F
    to: AHU-2/B.2/B.3/PP/CL/FRE/FRD (ME Contractor)
    method: typical_range
    typical_range_key: plant_room_same_room
    tag: "BOH_AHU"
    system: Air Handling — Basement / Podium BOH
    equipment_class: AHU (Chilled-Water-Served)
    notes: ""

  # --- PAHU-0.1 @ 2F — TYPICAL_RANGE ---
  - from: BMS-PNL-AHU-2F
    to: PAHU-0.1 (BMS Contractor)
    method: typical_range
    typical_range_key: plant_room_same_room
    tag: "PAHU_2F"
    system: Air Handling — Pre-cooled
    equipment_class: Precooled Air Handling Unit
    notes: ""

  - from: BMS-PNL-AHU-2F
    to: PAHU-0.1 (ME Contractor)
    method: typical_range
    typical_range_key: plant_room_same_room
    tag: "PAHU_2F"
    system: Air Handling — Pre-cooled
    equipment_class: Precooled Air Handling Unit
    notes: ""

  # --- ROOFDECK plant — MEASURED ---
  - from: BMS-PNL-CT-RD
    to: CT-1 to CT-3 (BMS Contractor)
    method: measured
    length_m: 18
    drawing_ref: "EE Plan ECE-16 (Roof Deck Layout) calibrated against guestroom grid 7.5 m"
    horizontal_m: 10
    vertical_m: 2
    terminations_m: 2
    cornering_m: 4
    buffer_pct: 10
    tag: "CT_roof"
    system: Heat Rejection — Cooling Tower
    equipment_class: Cooling Tower
    notes: "3 cooling towers in a row at roofdeck mechanical area."

  - from: BMS-PNL-CT-RD
    to: CT-1 to CT-3 (ME Contractor)
    method: measured
    length_m: 16
    drawing_ref: "ECE-16 (RD)"
    horizontal_m: 9
    vertical_m: 2
    terminations_m: 2
    cornering_m: 3
    buffer_pct: 10
    tag: "CT_roof"
    system: Heat Rejection — Cooling Tower
    equipment_class: Cooling Tower
    notes: ""

  - from: BMS-PNL-AHU-RD
    to: AHU-RD (with CHW mod valve) (BMS Contractor)
    method: measured
    length_m: 16
    drawing_ref: "ECE-16 (RD)"
    horizontal_m: 8
    vertical_m: 2
    terminations_m: 2
    cornering_m: 4
    buffer_pct: 10
    tag: "AHU_roof"
    system: Air Handling — Roofdeck AHU
    equipment_class: AHU (Chilled-Water-Served)
    notes: ""

  - from: BMS-PNL-AHU-RD
    to: AHU-RD (with CHW mod valve) (ME Contractor)
    method: measured
    length_m: 14
    drawing_ref: "ECE-16 (RD)"
    horizontal_m: 7
    vertical_m: 2
    terminations_m: 2
    cornering_m: 3
    buffer_pct: 10
    tag: "AHU_roof"
    system: Air Handling — Roofdeck AHU
    equipment_class: AHU (Chilled-Water-Served)
    notes: ""

  - from: BMS-PNL-AHU-RD
    to: PAHU-RD (×2) (BMS Contractor)
    method: measured
    length_m: 14
    drawing_ref: "ECE-16 (RD)"
    horizontal_m: 7
    vertical_m: 2
    terminations_m: 2
    cornering_m: 3
    buffer_pct: 10
    tag: "PAHU_roof"
    system: Air Handling — Pre-cooled (Roofdeck)
    equipment_class: Precooled Air Handling Unit
    notes: ""

  - from: BMS-PNL-AHU-RD
    to: PAHU-RD (×2) (ME Contractor)
    method: measured
    length_m: 12
    drawing_ref: "ECE-16 (RD)"
    horizontal_m: 6
    vertical_m: 2
    terminations_m: 2
    cornering_m: 2
    buffer_pct: 10
    tag: "PAHU_roof"
    system: Air Handling — Pre-cooled (Roofdeck)
    equipment_class: Precooled Air Handling Unit
    notes: ""

  # --- CASINO MVAC @ 2F — MEASURED ---
  - from: BMS-PNL-CASINO-2F
    to: DOAS (Casino) — 2 units (BMS Contractor)
    method: measured
    length_m: 26
    drawing_ref: "EE-09 (2F Power Layout) — casino zone, panel PPCAS-14 area"
    horizontal_m: 16
    vertical_m: 3
    terminations_m: 2
    cornering_m: 5
    buffer_pct: 10
    tag: "Casino_DOAS"
    system: Casino MVAC — Dedicated Outdoor Air
    equipment_class: DOAS Unit
    notes: "Casino DOAS in 2F mech room adjacent to casino lobby."

  - from: BMS-PNL-CASINO-2F
    to: DOAS (Casino) — 2 units (ME Contractor)
    method: measured
    length_m: 24
    drawing_ref: "EE-09 (2F)"
    horizontal_m: 14
    vertical_m: 3
    terminations_m: 2
    cornering_m: 5
    buffer_pct: 10
    tag: "Casino_DOAS"
    system: Casino MVAC — Dedicated Outdoor Air
    equipment_class: DOAS Unit
    notes: ""

  - from: BMS-PNL-CASINO-2F
    to: Sanitizer for AHU-2M.1/2M.2 (Equipment Supplier)
    method: typical_range
    typical_range_key: casino_floor_field
    tag: "Casino_Sanitizer"
    system: Casino MVAC — Smoke Sanitizer
    equipment_class: Ozone Generator (UV-light or Corona)
    notes: "Sanitizer device on casino floor near AHU-2M.x; HLI integration."

  # --- BOILER / LAUNDRY @ LG — MEASURED ---
  - from: BMS-PNL-BOILER-LG
    to: SB-1 & SB-2 (BMS Contractor)
    method: measured
    length_m: 12
    drawing_ref: "EE-22 LG laundry-room load schedule cross-reference"
    horizontal_m: 6
    vertical_m: 2
    terminations_m: 2
    cornering_m: 2
    buffer_pct: 10
    tag: "Boiler_LG"
    system: Boiler / Laundry
    equipment_class: Steam Boiler
    notes: ""

  - from: BMS-PNL-BOILER-LG
    to: SB-1 & SB-2 (ME Contractor)
    method: measured
    length_m: 10
    drawing_ref: "LG mech area"
    horizontal_m: 5
    vertical_m: 2
    terminations_m: 1
    cornering_m: 2
    buffer_pct: 10
    tag: "Boiler_LG"
    system: Boiler / Laundry
    equipment_class: Steam Boiler
    notes: ""

  # --- PLUMBING / SHW @ LG and RD ---
  - from: BMS-PNL-PLUMBING-LG
    to: HW Supply & Return Header (LG) (BMS Contractor)
    method: measured
    length_m: 10
    drawing_ref: "LG plumbing area"
    horizontal_m: 5
    vertical_m: 1
    terminations_m: 2
    cornering_m: 2
    buffer_pct: 10
    tag: "SHW_LG"
    system: Plumbing — Sanitary Hot Water
    equipment_class: CHW Supply Main Header
    notes: "Header T-sensors adjacent to BMS plumbing panel."

  - from: BMS-PNL-PLUMBING-LG
    to: HWT-LZ (×3) (BMS Contractor)
    method: measured
    length_m: 14
    drawing_ref: "LG plumbing area"
    horizontal_m: 8
    vertical_m: 2
    terminations_m: 1
    cornering_m: 3
    buffer_pct: 10
    tag: "SHW_LG"
    system: Plumbing — Sanitary Hot Water
    equipment_class: Calorifier (Hot Water Storage Tank)
    notes: ""

  - from: BMS-PNL-PLUMBING-LG
    to: RP-LZ (×3) (ME Contractor)
    method: typical_range
    typical_range_key: plant_room_same_room
    tag: "SHW_LG"
    system: Plumbing — Sanitary Hot Water
    equipment_class: Recirculating Pump
    notes: ""

  - from: BMS-PNL-PLUMBING-RD
    to: HWT-HZ (×3) (BMS Contractor)
    method: measured
    length_m: 12
    drawing_ref: "ECE-16 (RD) plumbing zone"
    horizontal_m: 6
    vertical_m: 2
    terminations_m: 1
    cornering_m: 3
    buffer_pct: 10
    tag: "SHW_RD"
    system: Plumbing — Sanitary Hot Water
    equipment_class: Calorifier (Hot Water Storage Tank)
    notes: ""

  - from: BMS-PNL-PLUMBING-RD
    to: RP-HZ (×3) (ME Contractor)
    method: typical_range
    typical_range_key: plant_room_same_room
    tag: "SHW_RD"
    system: Plumbing — Sanitary Hot Water
    equipment_class: Recirculating Pump
    notes: ""

  # --- VENTILATION (per-floor exhaust fans) ---
  - from: BMS-PNL-VENT-GF
    to: TEF-1.1 to 1.4 + EF-1.2A/LPG.1/1MR.1/1STO.1/MRF.1 (ME Contractor)
    method: typical_range
    typical_range_key: guestroom_corridor
    tag: "Vent_GF"
    system: General Ventilation
    equipment_class: Exhaust Fan (General)
    notes: "GF Main Lobby exhaust fans distributed across GF zone."

  - from: BMS-PNL-VENT-2F
    to: TEF-2.1/2.3/2B.3 + EF-2B.1/2B.2/GS.1&GS.2 + EF-2.1 to 2.4 + EF-CHRx2 (ME Contractor)
    method: typical_range
    typical_range_key: guestroom_corridor
    tag: "Vent_2F"
    system: General Ventilation
    equipment_class: Exhaust Fan (General)
    notes: ""

  - from: BMS-PNL-VENT-3F
    to: TEF-3Ax2/3B/3Cx2/3Dx20 + others (ME Contractor)
    method: typical_range
    typical_range_key: guestroom_corridor
    tag: "Vent_3F"
    system: General Ventilation
    equipment_class: Exhaust Fan (General)
    notes: "3F Amenity + Guestroom toilet exhausts."

  - from: BMS-PNL-VENT-RD
    to: EF-RD.1/RD.2, EF-1 (ME Contractor)
    method: measured
    length_m: 14
    drawing_ref: "ECE-16 (RD)"
    horizontal_m: 7
    vertical_m: 2
    terminations_m: 2
    cornering_m: 3
    buffer_pct: 10
    tag: "Vent_RD"
    system: General Ventilation
    equipment_class: Exhaust Fan (General)
    notes: "Roofdeck EFs adjacent to roofdeck plant area."

  # --- BMS PANEL POWER FEEDS (13 panels) — TYPICAL_RANGE ---
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-AHU-2F — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-AHU-RD — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-BOHAHU-2F — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-BOILER-LG — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-CASINO-2F — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-CHWPLANT-2F — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-CT-RD — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-PLUMBING-LG — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-PLUMBING-RD — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-VENT-2F — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-VENT-3F — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-VENT-GF — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""
  - from: Local panelboard / EE-supplied feeder
    to: BMS-PNL-VENT-RD — BMS panel 240V power feed
    method: typical_range
    typical_range_key: bms_panel_power_feed
    tag: "Power_Feed"
    system: Power Provisions
    notes: ""