Summary

A4 — Panel Schedule, Audit View
ProjectKingsford Hotel Bacolod BMS
Canonical sourceA4-panel-schedule.yaml
How to record correctionsEdit the canonical YAML directly — add a verification: block to the affected row(s)
Totals
Total panels18
Total physical I/O523
Total HLI sub-points166
Total controllers30
Verification status
StatusCount% of total
verified00%
needs_correction00%
uncertain00%
unverified18100%
⚠ Known weak points
Verify panel locations against architectural drawings. Confirm proximity to served equipment, panel-room space allocation, and access for maintenance.
How corrections flow
Edit A4-panel-schedule.yaml — add a verification: block to the panel row when location is confirmed or revised.

Detail

PanelLocationEquipment servedPhys I/OHLINetwork dropsControllersPower (W)StatusVerified byDrawing refNotes
PNL-AHU-L22nd Level/Casino MVAC Plant43242260unverified
PNL-BL-LZLower Ground/Boiler Room23200125unverified
PNL-CH-PLANT-GNDGND/Chiller Plant Room327543265unverified
PNL-CHWP-GNDGND/BOH AHU Area34263265unverified
PNL-CHWP-L22F/CHW Pump Room114031255unverified
PNL-CT-RDRoofdeck/Cooling Tower Area63100125unverified
PNL-DOAS-L22nd Level/Casino MVAC Plant12141255unverified
PNL-DOAS-RDRoofdeck/Hotel DOAS Plant24282260unverified
PNL-EE-DISTDistribution (per A4)10050102100unverified
PNL-EE-MAINMain Switchgear Room30153265unverified
PNL-PAHU-RDRoofdeck/PAHU Plant22242260unverified
PNL-PL-HZRoofdeck/HW Plant106180125unverified
PNL-PL-LZLower Ground/HW Plant102400125unverified
PNL-VENT-BSMTBasement164800250unverified
PNL-VENT-GFGF Main Lobby92700125unverified
PNL-VENT-L22nd Floor133900125unverified
PNL-VENT-L33rd Amenity & Guestroom278100375unverified
PNL-VENT-RDRoofdeck3900125unverified

Verification schema

How to record verification / corrections in A4-panel-schedule.yaml
Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block:
- id: PNL-AHU-3F
verification: # ADDED by team
status: needs_correction # unverified | verified | needs_correction | uncertain
corrected_location: 3F Mech Room A # team's measured / confirmed value
verified_by: J. Cruz
verified_date: 2026-05-10
drawing_ref: "EE-09 grid B-2"
notes: ""
After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project>
Corrections propagate to B4 manhours, BOQ, and final deliverables automatically.
Recommended verification methods (priority order):
1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion).
2. Properly-scaled architectural drawings.
3. Mechanical contractor's tray layout combined with BMS panel locations.
4. A-001 default with ±20% contingency in BOQ — last resort.