Summary

A1 — I/O List, Audit View
ProjectKingsford Hotel Bacolod BMS
Canonical sourceA1-io-list.yaml
How to record correctionsEdit the canonical YAML directly — add a verification: block to the affected row(s)
Totals
Total I/O points716
Unique equipment instances135
Systems represented11
Verification status
StatusCount% of total
verified00%
needs_correction00%
uncertain00%
unverified716100%
⚠ Known weak points
Equipment quantities are derived from the customer's points list. Cross-verify against mechanical floor plans (Q-008) and architectural plans (Q-005). Where the points list shows aggregate counts without per-tag enumeration, the gap is captured as Q-021.
How corrections flow
Edit A1-io-list.yaml — add a verification: block to any row where you confirm or correct the equipment, location, or panel assignment.
Re-run the deliverables generator to refresh downstream artifacts.

By System

SystemEquipment instancesI/O points
General Ventilation68204
Chilled Water20159
Plumbing & Sanitary Hotwater2048
Power Metering1378
BOH Air Handling351
Boiler/Laundry232
DOAS - Hotel/Roofdeck252
AHU - Casino232
AHU - Casino (Ozonizer)26
PAHU - Roofdeck228
DOAS - Casino MVAC126
TOTAL135716

By Location

LocationEquipment instances
3rd Amenity & Guestroom27
Basement16
2nd Floor13
2F/CHW Pump Room11
Lower Ground/HW Plant10
Roofdeck/HW Plant10
Distribution (per A4)10
GF Main Lobby9
Roofdeck/Cooling Tower Area6
2nd Level/Casino MVAC Plant5
GND/Chiller Plant Room3
GND/BOH AHU Area3
Roofdeck3
Main Switchgear Room3
Lower Ground/Boiler Room2
Roofdeck/Hotel DOAS Plant2
Roofdeck/PAHU Plant2

By Panel

PanelEquipment instances
PNL-VENT-L327
PNL-VENT-BSMT16
PNL-VENT-L213
PNL-CHWP-L211
PNL-PL-LZ10
PNL-PL-HZ10
PNL-EE-DIST10
PNL-VENT-GF9
PNL-CT-RD6
PNL-AHU-L24
PNL-CH-PLANT-GND3
PNL-CHWP-GND3
PNL-VENT-RD3
PNL-EE-MAIN3
PNL-BL-LZ2
PNL-DOAS-RD2
PNL-PAHU-RD2
PNL-DOAS-L21

Verification schema

How to record verification / corrections in A1-io-list.yaml
Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block:
- id: chws.ch-1.entering-chw-temp
verification: # ADDED by team
status: needs_correction # unverified | verified | needs_correction | uncertain
verified_by: J. Cruz
verified_date: 2026-05-10
drawing_ref: "EE-09 grid B-2"
notes: ""
After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project>
Corrections propagate to B4 manhours, BOQ, and final deliverables automatically.
Recommended verification methods (priority order):
1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion).
2. Properly-scaled architectural drawings.
3. Mechanical contractor's tray layout combined with BMS panel locations.
4. A-001 default with ±20% contingency in BOQ — last resort.