Summary
| A4 — Panel Schedule, Audit View | |||||
| Project | Kingsford Hotel Bacolod — BMS | ||||
| Canonical source | A4-panel-schedule.yaml | ||||
| How to record corrections | Edit the canonical YAML directly — add a verification: block to the affected row(s) | ||||
| Totals | |||||
| Total panels | 8 | ||||
| Total physical I/O | 561 | ||||
| Total HLI sub-points | 141 | ||||
| Total controllers | 19 | ||||
| Verification status | |||||
| Status | Count | % of total | |||
| verified | 0 | 0% | |||
| needs_correction | 0 | 0% | |||
| uncertain | 0 | 0% | |||
| unverified | 8 | 100% | |||
| ⚠ Known weak points | |||||
| Verify panel locations against architectural drawings. Confirm proximity to served equipment, panel-room space allocation, and access for maintenance. | |||||
| How corrections flow | |||||
| Edit A4-panel-schedule.yaml — add a verification: block to the panel row when location is confirmed or revised. | |||||
Detail
| Panel | Location | Equipment served | Phys I/O | HLI | Network drops | Controllers | Power (W) | Status | Verified by | Drawing ref | Notes |
| DDC-2F-BOH | 2nd Floor / 2nd Floor BOH / 2nd Floor BOH Toilet / 2nd Floor General Service / 2nd Floor OHR / 2nd Floor Toilet / 2nd Level AHU MCC / 2nd Level BOH / 2nd Level Executive Lounge / 2nd Level Function Room 2 / 2nd Level Function Room 3 / 2nd Level Function Rooms / 2nd Level Pre-Function | 25 | 165 | 25 | 13 | 5 | 190 | unverified | |||
| DDC-2F-CHILLER | 2nd Level Chiller MCC / 2nd Level Chiller Room | 16 | 72 | 65 | 9 | 2 | 95 | unverified | |||
| DDC-2M-CASINO | 2nd Mezzanine (Casino) | 5 | 47 | 8 | 5 | 2 | 75 | unverified | |||
| DDC-3F | 3rd Floor / 3rd Floor Amenity Toilet / 3rd Floor BOH / 3rd Floor Toilet | 12 | 36 | 0 | 0 | 1 | 25 | unverified | |||
| DDC-B1-BOH | Basement / Basement Battery Room / Basement FOST Room / Basement Garbage Lobby / Basement Main Fire Riser / Basement Mech / Pump / Basement Pump Room / Basement Service / Basement Toilet / Basement Wash Service | 17 | 57 | 2 | 1 | 2 | 55 | unverified | |||
| DDC-GF-BOH | GF Main Lobby Toilet / Ground Floor AHU MCC / Ground Floor BOH / Ground Floor Fire Command Center | 9 | 48 | 10 | 5 | 2 | 75 | unverified | |||
| DDC-LG-PLANT | Lower Ground Boiler Room / Lower Ground HWL Room / Lower Ground Lighting Panel A / Lower Ground Lighting Panel B / Lower Ground Main Switchroom | 9 | 26 | 19 | 5 | 2 | 75 | unverified | |||
| DDC-RD-PLANT | Roof Deck / Roof Deck CT Area / Roof Deck HWL Area | 16 | 110 | 12 | 4 | 3 | 95 | unverified |
Verification schema
| How to record verification / corrections in A4-panel-schedule.yaml | |||||||
| Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block: | |||||||
| - id: PNL-AHU-3F | |||||||
| verification: # ADDED by team | |||||||
| status: needs_correction # unverified | verified | needs_correction | uncertain | |||||||
| corrected_location: 3F Mech Room A # team's measured / confirmed value | |||||||
| verified_by: J. Cruz | |||||||
| verified_date: 2026-05-10 | |||||||
| drawing_ref: "EE-09 grid B-2" | |||||||
| notes: "" | |||||||
| After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project> | |||||||
| Corrections propagate to B4 manhours, BOQ, and final deliverables automatically. | |||||||
| Recommended verification methods (priority order): | |||||||
| 1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion). | |||||||
| 2. Properly-scaled architectural drawings. | |||||||
| 3. Mechanical contractor's tray layout combined with BMS panel locations. | |||||||
| 4. A-001 default with ±20% contingency in BOQ — last resort. | |||||||