Summary

A2 — Equipment Takeoff, Audit View
ProjectKingsford Hotel Bacolod — BMS
Canonical sourceA2-equipment-takeoff.yaml
How to record correctionsEdit the canonical YAML directly — add a verification: block to the affected row(s)
Totals
Total equipment instances109
Equipment classes26
Locations42
Verification status
StatusCount% of total
verified00%
needs_correction00%
uncertain00%
unverified109100%
⚠ Known weak points
Verify quantities and locations against mechanical / electrical drawings. The 'Make/Model' field is a generic class default — supplier RFQ refines.
How corrections flow
Edit A2-equipment-takeoff.yaml — add a verification: block to the affected row when location or count is confirmed/corrected.

By Class

Equipment classCount
Exhaust Fan (General)32
Exhaust Fan (Toilet)15
AHU (Chilled-Water-Served)12
Precooled Air Handling Unit8
Multifunction Power Meter (Feeder)5
Chiller (Package Water-Cooled)3
Condenser Water Pump3
Cooling Tower3
Secondary CHW Pump3
Air Ionizer (Casino)2
DOAS Unit2
Heat Pump2
Hot Water Header Set2
Calorifier (Hot Water Storage Tank)2
Primary CHW Pump2
Recirculating Pump2
Steam Boiler2
CHW Bypass Header1
CHW Return Main Header1
CHW Supply Main Header1
Cooling Tower (Common)1
Condenser Water Header1
DOAS Unit (Casino — with CO/VOC)1
FACP Gateway1
Multifunction Power Meter (Main)1
Primary CHW Pump (Standby)1
TOTAL109

By Location

LocationCount
2nd Level Chiller Room15
Roof Deck11
2nd Level BOH6
2nd Mezzanine (Casino)5
3rd Floor5
2nd Floor4
Roof Deck HWL Area4
Lower Ground HWL Room4
GF Main Lobby Toilet4
3rd Floor Toilet4
Ground Floor BOH3
Basement3
2nd Level Pre-Function2
2nd Floor BOH2
Basement Battery Room2
Basement Service2
Basement Garbage Lobby2
2nd Floor General Service2
Basement Pump Room2
Lower Ground Boiler Room2
2nd Floor Toilet2
3rd Floor Amenity Toilet2
Basement Toilet2
2nd Level Executive Lounge1
2nd Level Function Room 21
2nd Level Function Room 31
Roof Deck CT Area1
3rd Floor BOH1
Basement FOST Room1
Basement Main Fire Riser1
Basement Mech / Pump1
2nd Floor OHR1
Basement Wash Service1
Ground Floor Fire Command Center1
2nd Level AHU MCC1
Ground Floor AHU MCC1
2nd Level Chiller MCC1
Lower Ground Lighting Panel A1
Lower Ground Lighting Panel B1
Lower Ground Main Switchroom1
2nd Level Function Rooms1
2nd Floor BOH Toilet1

Detail

IDClassLocationPanelPrimary C/OStatusVerified byDateDrawing refNotes
AHU-1.1AHU (Chilled-Water-Served)Ground Floor BOHDDC-GF-BOHEquipment Supplierunverified
AHU-1.2AHU (Chilled-Water-Served)Ground Floor BOHDDC-GF-BOHEquipment Supplierunverified
AHU-1.3AHU (Chilled-Water-Served)Ground Floor BOHDDC-GF-BOHEquipment Supplierunverified
AHU-2M.1AHU (Chilled-Water-Served)2nd Mezzanine (Casino)DDC-2M-CASINOEquipment Supplierunverified
AHU-2M.2AHU (Chilled-Water-Served)2nd Mezzanine (Casino)DDC-2M-CASINOEquipment Supplierunverified
AHU-B.1AHU (Chilled-Water-Served)2nd Level BOHDDC-2F-BOHEquipment Supplierunverified
AHU-B.2AHU (Chilled-Water-Served)2nd Level BOHDDC-2F-BOHEquipment Supplierunverified
AHU-B.3AHU (Chilled-Water-Served)2nd Level BOHDDC-2F-BOHEquipment Supplierunverified
AHU-ELAHU (Chilled-Water-Served)2nd Level Executive LoungeDDC-2F-BOHEquipment Supplierunverified
AHU-FR2AHU (Chilled-Water-Served)2nd Level Function Room 2DDC-2F-BOHEquipment Supplierunverified
AHU-FR3AHU (Chilled-Water-Served)2nd Level Function Room 3DDC-2F-BOHEquipment Supplierunverified
AHU-PFAHU (Chilled-Water-Served)2nd Level Pre-FunctionDDC-2F-BOHEquipment Supplierunverified
AIR-ION-2M.1Air Ionizer (Casino)2nd Mezzanine (Casino)DDC-2M-CASINOEquipment Supplierunverified
AIR-ION-2M.2Air Ionizer (Casino)2nd Mezzanine (Casino)DDC-2M-CASINOEquipment Supplierunverified
CH-1Chiller (Package Water-Cooled)2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
CH-2Chiller (Package Water-Cooled)2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
CH-3Chiller (Package Water-Cooled)2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
CHW-DIFFCHW Bypass Header2nd Level Chiller RoomDDC-2F-CHILLERBMS Contractorunverified
CHW-RET-HDRCHW Return Main Header2nd Level Chiller RoomDDC-2F-CHILLERBMS Contractorunverified
CHW-SUP-HDRCHW Supply Main Header2nd Level Chiller RoomDDC-2F-CHILLERBMS Contractorunverified
COWP-1Condenser Water Pump2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
COWP-2Condenser Water Pump2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
COWP-3Condenser Water Pump2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
CT-1Cooling TowerRoof DeckDDC-RD-PLANTBMS Contractorunverified
CT-2Cooling TowerRoof DeckDDC-RD-PLANTBMS Contractorunverified
CT-3Cooling TowerRoof DeckDDC-RD-PLANTBMS Contractorunverified
CT-COMMONCooling Tower (Common)Roof DeckDDC-RD-PLANTBMS Contractorunverified
CW-HDRCondenser Water HeaderRoof Deck CT AreaDDC-RD-PLANTBMS Contractorunverified
DOAS-2MDOAS Unit (Casino — with CO/VOC)2nd Mezzanine (Casino)DDC-2M-CASINOEquipment Supplierunverified
DOAS-RD.1DOAS UnitRoof DeckDDC-RD-PLANTEquipment Supplierunverified
DOAS-RD.2DOAS UnitRoof DeckDDC-RD-PLANTEquipment Supplierunverified
EF-1Exhaust Fan (General)Roof DeckDDC-RD-PLANTEquipment Supplierunverified
EF-2.1Exhaust Fan (General)2nd FloorDDC-2F-BOHEquipment Supplierunverified
EF-2.2Exhaust Fan (General)2nd FloorDDC-2F-BOHEquipment Supplierunverified
EF-2.3Exhaust Fan (General)2nd FloorDDC-2F-BOHEquipment Supplierunverified
EF-2.4Exhaust Fan (General)2nd FloorDDC-2F-BOHEquipment Supplierunverified
EF-2B.1Exhaust Fan (General)2nd Floor BOHDDC-2F-BOHEquipment Supplierunverified
EF-2B.2Exhaust Fan (General)2nd Floor BOHDDC-2F-BOHEquipment Supplierunverified
EF-3.1Exhaust Fan (General)3rd FloorDDC-3FEquipment Supplierunverified
EF-3.2Exhaust Fan (General)3rd FloorDDC-3FEquipment Supplierunverified
EF-3.3Exhaust Fan (General)3rd FloorDDC-3FEquipment Supplierunverified
EF-3.4Exhaust Fan (General)3rd FloorDDC-3FEquipment Supplierunverified
EF-3B-GExhaust Fan (General)3rd Floor BOHDDC-3FEquipment Supplierunverified
EF-3C.1-GExhaust Fan (General)3rd FloorDDC-3FEquipment Supplierunverified
EF-B.1Exhaust Fan (General)BasementDDC-B1-BOHEquipment Supplierunverified
EF-B.2Exhaust Fan (General)BasementDDC-B1-BOHEquipment Supplierunverified
EF-BR.1Exhaust Fan (General)Basement Battery RoomDDC-B1-BOHEquipment Supplierunverified
EF-BR.2Exhaust Fan (General)Basement Battery RoomDDC-B1-BOHEquipment Supplierunverified
EF-BS.1Exhaust Fan (General)Basement ServiceDDC-B1-BOHEquipment Supplierunverified
EF-BS.2Exhaust Fan (General)Basement ServiceDDC-B1-BOHEquipment Supplierunverified
EF-FOST.1Exhaust Fan (General)Basement FOST RoomDDC-B1-BOHEquipment Supplierunverified
EF-GL.1Exhaust Fan (General)Basement Garbage LobbyDDC-B1-BOHEquipment Supplierunverified
EF-GL.2Exhaust Fan (General)Basement Garbage LobbyDDC-B1-BOHEquipment Supplierunverified
EF-GS.1Exhaust Fan (General)2nd Floor General ServiceDDC-2F-BOHEquipment Supplierunverified
EF-GS.2Exhaust Fan (General)2nd Floor General ServiceDDC-2F-BOHEquipment Supplierunverified
EF-MFR.1Exhaust Fan (General)Basement Main Fire RiserDDC-B1-BOHEquipment Supplierunverified
EF-MP.1Exhaust Fan (General)Basement Mech / PumpDDC-B1-BOHEquipment Supplierunverified
EF-OHRv2Exhaust Fan (General)2nd Floor OHRDDC-2F-BOHEquipment Supplierunverified
EF-PR.1Exhaust Fan (General)Basement Pump RoomDDC-B1-BOHEquipment Supplierunverified
EF-PR.3Exhaust Fan (General)Basement Pump RoomDDC-B1-BOHEquipment Supplierunverified
EF-RD.1Exhaust Fan (General)Roof DeckDDC-RD-PLANTEquipment Supplierunverified
EF-RO.2Exhaust Fan (General)Roof DeckDDC-RD-PLANTEquipment Supplierunverified
EF-WS.1Exhaust Fan (General)Basement Wash ServiceDDC-B1-BOHEquipment Supplierunverified
FACP-GWFACP GatewayGround Floor Fire Command CenterDDC-GF-BOHEE Contractorunverified
HP-HZHeat PumpRoof Deck HWL AreaDDC-RD-PLANTEquipment Supplierunverified
HP-LZHeat PumpLower Ground HWL RoomDDC-LG-PLANTEquipment Supplierunverified
HWH-HZHot Water Header SetRoof Deck HWL AreaDDC-RD-PLANTBMS Contractorunverified
HWH-LZHot Water Header SetLower Ground HWL RoomDDC-LG-PLANTBMS Contractorunverified
HWT-HZCalorifier (Hot Water Storage Tank)Roof Deck HWL AreaDDC-RD-PLANTBMS Contractorunverified
HWT-LZCalorifier (Hot Water Storage Tank)Lower Ground HWL RoomDDC-LG-PLANTBMS Contractorunverified
MPM-AHU-2FMultifunction Power Meter (Feeder)2nd Level AHU MCCDDC-2F-BOHBMS Contractorunverified
MPM-AHU-GFMultifunction Power Meter (Feeder)Ground Floor AHU MCCDDC-GF-BOHBMS Contractorunverified
MPM-CHILLERMultifunction Power Meter (Feeder)2nd Level Chiller MCCDDC-2F-CHILLERBMS Contractorunverified
MPM-LIGHT-AMultifunction Power Meter (Feeder)Lower Ground Lighting Panel ADDC-LG-PLANTBMS Contractorunverified
MPM-LIGHT-BMultifunction Power Meter (Feeder)Lower Ground Lighting Panel BDDC-LG-PLANTBMS Contractorunverified
MPM-MAINMultifunction Power Meter (Main)Lower Ground Main SwitchroomDDC-LG-PLANTBMS Contractorunverified
PAHU-0.1Precooled Air Handling UnitBasementDDC-B1-BOHEquipment Supplierunverified
PAHU-B.1Precooled Air Handling Unit2nd Level BOHDDC-2F-BOHEquipment Supplierunverified
PAHU-B.2Precooled Air Handling Unit2nd Level BOHDDC-2F-BOHEquipment Supplierunverified
PAHU-B.3Precooled Air Handling Unit2nd Level BOHDDC-2F-BOHEquipment Supplierunverified
PAHU-FRPrecooled Air Handling Unit2nd Level Function RoomsDDC-2F-BOHEquipment Supplierunverified
PAHU-PFPrecooled Air Handling Unit2nd Level Pre-FunctionDDC-2F-BOHEquipment Supplierunverified
PAHU-r.1Precooled Air Handling UnitRoof DeckDDC-RD-PLANTEquipment Supplierunverified
PAHU-r.2Precooled Air Handling UnitRoof DeckDDC-RD-PLANTEquipment Supplierunverified
PCHWP-1Primary CHW Pump2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
PCHWP-2Primary CHW Pump2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
PCHWP-3Primary CHW Pump (Standby)2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
RP-HZRecirculating PumpRoof Deck HWL AreaDDC-RD-PLANTEquipment Supplierunverified
RP-LZRecirculating PumpLower Ground HWL RoomDDC-LG-PLANTEquipment Supplierunverified
SB-1Steam BoilerLower Ground Boiler RoomDDC-LG-PLANTEquipment Supplierunverified
SB-2Steam BoilerLower Ground Boiler RoomDDC-LG-PLANTEquipment Supplierunverified
SCHWP-1Secondary CHW Pump2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
SCHWP-2Secondary CHW Pump2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
SCHWP-3Secondary CHW Pump2nd Level Chiller RoomDDC-2F-CHILLEREquipment Supplierunverified
TEF-1.1Exhaust Fan (Toilet)GF Main Lobby ToiletDDC-GF-BOHEquipment Supplierunverified
TEF-1.2Exhaust Fan (Toilet)GF Main Lobby ToiletDDC-GF-BOHEquipment Supplierunverified
TEF-1.3Exhaust Fan (Toilet)GF Main Lobby ToiletDDC-GF-BOHEquipment Supplierunverified
TEF-1.4Exhaust Fan (Toilet)GF Main Lobby ToiletDDC-GF-BOHEquipment Supplierunverified
TEF-2.1Exhaust Fan (Toilet)2nd Floor ToiletDDC-2F-BOHEquipment Supplierunverified
TEF-2.2Exhaust Fan (Toilet)2nd Floor ToiletDDC-2F-BOHEquipment Supplierunverified
TEF-2B.3Exhaust Fan (Toilet)2nd Floor BOH ToiletDDC-2F-BOHEquipment Supplierunverified
TEF-30.20Exhaust Fan (Toilet)3rd Floor ToiletDDC-3FEquipment Supplierunverified
TEF-3A.1Exhaust Fan (Toilet)3rd Floor Amenity ToiletDDC-3FEquipment Supplierunverified
TEF-3A.2Exhaust Fan (Toilet)3rd Floor Amenity ToiletDDC-3FEquipment Supplierunverified
TEF-3BExhaust Fan (Toilet)3rd Floor ToiletDDC-3FEquipment Supplierunverified
TEF-3C.1Exhaust Fan (Toilet)3rd Floor ToiletDDC-3FEquipment Supplierunverified
TEF-3C.2Exhaust Fan (Toilet)3rd Floor ToiletDDC-3FEquipment Supplierunverified
TEF-B.1Exhaust Fan (Toilet)Basement ToiletDDC-B1-BOHEquipment Supplierunverified
TEF-B.2Exhaust Fan (Toilet)Basement ToiletDDC-B1-BOHEquipment Supplierunverified

Verification schema

How to record verification / corrections in A2-equipment-takeoff.yaml
Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block:
- id: AHU-01
verification: # ADDED by team
status: needs_correction # unverified | verified | needs_correction | uncertain
corrected_location: 3rd Floor Mech Room # team's measured / confirmed value
verified_by: J. Cruz
verified_date: 2026-05-10
drawing_ref: "EE-09 grid B-2"
notes: ""
After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project>
Corrections propagate to B4 manhours, BOQ, and final deliverables automatically.
Recommended verification methods (priority order):
1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion).
2. Properly-scaled architectural drawings.
3. Mechanical contractor's tray layout combined with BMS panel locations.
4. A-001 default with ±20% contingency in BOQ — last resort.