Summary

A4 — Panel Schedule, Audit View
ProjectKingsford Hotel Bacolod — BMS
Canonical sourceA4-panel-schedule.yaml
How to record correctionsEdit the canonical YAML directly — add a verification: block to the affected row(s)
Totals
Total panels13
Total physical I/O570
Total HLI sub-points49
Total controllers21
Verification status
StatusCount% of total
verified00%
needs_correction00%
uncertain00%
unverified13100%
⚠ Known weak points
Verify panel locations against architectural drawings. Confirm proximity to served equipment, panel-room space allocation, and access for maintenance.
How corrections flow
Edit A4-panel-schedule.yaml — add a verification: block to the panel row when location is confirmed or revised.

Detail

PanelLocationEquipment servedPhys I/OHLINetwork dropsControllersPower (W)StatusVerified byDrawing refNotes
BMS-PNL-AHU-2F2F11240125unverified
BMS-PNL-AHU-RDRD24420250unverified
BMS-PNL-BOHAHU-2F2F1120200375unverified
BMS-PNL-BOILER-LGLG12200125unverified
BMS-PNL-CASINO-2F2F23040125unverified
BMS-PNL-CHWPLANT-2F2F4121004100unverified
BMS-PNL-CT-RDRD13510125unverified
BMS-PNL-PLUMBING-LGLG41890125unverified
BMS-PNL-PLUMBING-RDRD31290125unverified
BMS-PNL-VENT-2F2F13900125unverified
BMS-PNL-VENT-3F3F18100375unverified
BMS-PNL-VENT-GFGF12700125unverified
BMS-PNL-VENT-RDRD1900125unverified

Verification schema

How to record verification / corrections in A4-panel-schedule.yaml
Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block:
- id: PNL-AHU-3F
verification: # ADDED by team
status: needs_correction # unverified | verified | needs_correction | uncertain
corrected_location: 3F Mech Room A # team's measured / confirmed value
verified_by: J. Cruz
verified_date: 2026-05-10
drawing_ref: "EE-09 grid B-2"
notes: ""
After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project>
Corrections propagate to B4 manhours, BOQ, and final deliverables automatically.
Recommended verification methods (priority order):
1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion).
2. Properly-scaled architectural drawings.
3. Mechanical contractor's tray layout combined with BMS panel locations.
4. A-001 default with ±20% contingency in BOQ — last resort.