A2 — Equipment Takeoff, Audit View
ProjectKingsford Hotel Bacolod — BMS
Canonical sourceA2-equipment-takeoff.yaml
How to record correctionsEdit the canonical YAML directly — add a verification: block to the affected row(s)
Totals
Total equipment instances23
Equipment classes14
Locations5
Verification status
StatusCount% of total
verified00%
needs_correction00%
uncertain00%
unverified23100%
⚠ Known weak points
Verify quantities and locations against mechanical / electrical drawings. The 'Make/Model' field is a generic class default — supplier RFQ refines.
How corrections flow
Edit A2-equipment-takeoff.yaml — add a verification: block to the affected row when location or count is confirmed/corrected.

By Class

Equipment classCount
Exhaust Fan (General)4
AHU (Chilled-Water-Served)2
CHW Supply Main Header2
Heat Pump2
Calorifier (Hot Water Storage Tank)2
Precooled Air Handling Unit2
Recirculating Pump2
Condenser Water Pump1
Chiller (Package Water-Cooled)1
Primary CHW Pump1
Cooling Tower1
DOAS Unit1
Steam Boiler1
Ozone Generator (UV-light or Corona)1
TOTAL23

By Location

LocationCount
2F9
RD7
LG5
GF1
3F1

Detail

IDClassLocationPanelPrimary C/OStatusVerified byDateDrawing refNotes
AHU-2/B.2/B.3/PP/CL/FRE/FRDAHU (Chilled-Water-Served)2FBMS-PNL-BOHAHU-2FBMS Contractorunverified
AHU-RD (with CHW mod valve)AHU (Chilled-Water-Served)RDBMS-PNL-AHU-RDBMS Contractorunverified
CDWP-1 to CDWP-3Condenser Water Pump2FBMS-PNL-CHWPLANT-2FME Contractorunverified
CH-1 to CH-3Chiller (Package Water-Cooled)2FBMS-PNL-CHWPLANT-2FME Contractorunverified
CHW Supply & Return Main HeaderCHW Supply Main Header2FBMS-PNL-CHWPLANT-2FBMS Contractorunverified
CHWP-1 to CHWP-3Primary CHW Pump2FBMS-PNL-CHWPLANT-2FME Contractorunverified
CT-1 to CT-3Cooling TowerRDBMS-PNL-CT-RDBMS Contractorunverified
DOAS (Casino) — 2 unitsDOAS Unit2FBMS-PNL-CASINO-2FBMS Contractorunverified
EF-RD.1/RD.2, EF-1Exhaust Fan (General)RDBMS-PNL-VENT-RDME Contractorunverified
HP-HZ (×3)Heat PumpRDBMS-PNL-PLUMBING-RDEquipment Supplierunverified
HP-LZ (×3)Heat PumpLGBMS-PNL-PLUMBING-LGEquipment Supplierunverified
HW Supply & Return Header (LG)CHW Supply Main HeaderLGBMS-PNL-PLUMBING-LGBMS Contractorunverified
HWT-HZ (×3)Calorifier (Hot Water Storage Tank)RDBMS-PNL-PLUMBING-RDBMS Contractorunverified
HWT-LZ (×3)Calorifier (Hot Water Storage Tank)LGBMS-PNL-PLUMBING-LGBMS Contractorunverified
PAHU-0.1Precooled Air Handling Unit2FBMS-PNL-AHU-2FBMS Contractorunverified
PAHU-RD (×2)Precooled Air Handling UnitRDBMS-PNL-AHU-RDME Contractorunverified
RP-HZ (×3)Recirculating PumpRDBMS-PNL-PLUMBING-RDME Contractorunverified
RP-LZ (×3)Recirculating PumpLGBMS-PNL-PLUMBING-LGME Contractorunverified
SB-1 & SB-2Steam BoilerLGBMS-PNL-BOILER-LGME Contractorunverified
Sanitizer for AHU-2M.1/2M.2Ozone Generator (UV-light or Corona)2FBMS-PNL-CASINO-2FEquipment Supplierunverified
TEF-1.1 to 1.4 + EF-1.2A/LPG.1/1MR.1/1STO.1/MRF.1Exhaust Fan (General)GFBMS-PNL-VENT-GFME Contractorunverified
TEF-2.1/2.3/2B.3 + EF-2B.1/2B.2/GS.1&GS.2 + EF-2.1 to 2.4 + EF-CHRx2Exhaust Fan (General)2FBMS-PNL-VENT-2FME Contractorunverified
TEF-3Ax2/3B/3Cx2/3Dx20 + othersExhaust Fan (General)3FBMS-PNL-VENT-3FME Contractorunverified

Verification schema

How to record verification / corrections in A2-equipment-takeoff.yaml
Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block:
- id: AHU-01
verification: # ADDED by team
status: needs_correction # unverified | verified | needs_correction | uncertain
corrected_location: 3rd Floor Mech Room # team's measured / confirmed value
verified_by: J. Cruz
verified_date: 2026-05-10
drawing_ref: "EE-09 grid B-2"
notes: ""
After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project>
Corrections propagate to B4 manhours, BOQ, and final deliverables automatically.
Recommended verification methods (priority order):
1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion).
2. Properly-scaled architectural drawings.
3. Mechanical contractor's tray layout combined with BMS panel locations.
4. A-001 default with ±20% contingency in BOQ — last resort.