Summary

A1 — I/O List, Audit View
ProjectKingsford Hotel Bacolod — BMS
Canonical sourceA1-io-list.yaml
How to record correctionsEdit the canonical YAML directly — add a verification: block to the affected row(s)
Totals
Total I/O points619
Unique equipment instances23
Systems represented11
Verification status
StatusCount% of total
verified00%
needs_correction00%
uncertain00%
unverified619100%
⚠ Known weak points
Equipment quantities are derived from the customer's points list. Cross-verify against mechanical floor plans (Q-008) and architectural plans (Q-005). Where the points list shows aggregate counts without per-tag enumeration, the gap is captured as Q-021.
How corrections flow
Edit A1-io-list.yaml — add a verification: block to any row where you confirm or correct the equipment, location, or panel assignment.
Re-run the deliverables generator to refresh downstream artifacts.

By System

SystemEquipment instancesI/O points
Plumbing — Sanitary Hot Water748
Chilled Water Plant4121
General Ventilation4156
Air Handling — Basement / Podium BOH1140
Air Handling — Pre-cooled116
Boiler / Laundry122
Casino MVAC — Dedicated Outdoor Air130
Casino MVAC — Smoke Sanitizer14
Air Handling — Pre-cooled (Roofdeck)114
Air Handling — Roofdeck AHU132
Heat Rejection — Cooling Tower136
TOTAL23619

By Location

LocationEquipment instances
2F9
RD7
LG5
GF1
3F1

By Panel

PanelEquipment instances
BMS-PNL-CHWPLANT-2F4
BMS-PNL-PLUMBING-LG4
BMS-PNL-PLUMBING-RD3
BMS-PNL-CASINO-2F2
BMS-PNL-AHU-RD2
BMS-PNL-BOHAHU-2F1
BMS-PNL-AHU-2F1
BMS-PNL-VENT-GF1
BMS-PNL-VENT-2F1
BMS-PNL-VENT-3F1
BMS-PNL-VENT-RD1
BMS-PNL-BOILER-LG1
BMS-PNL-CT-RD1

Verification schema

How to record verification / corrections in A1-io-list.yaml
Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block:
- id: chws.ch-1.entering-chw-temp
verification: # ADDED by team
status: needs_correction # unverified | verified | needs_correction | uncertain
verified_by: J. Cruz
verified_date: 2026-05-10
drawing_ref: "EE-09 grid B-2"
notes: ""
After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project>
Corrections propagate to B4 manhours, BOQ, and final deliverables automatically.
Recommended verification methods (priority order):
1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion).
2. Properly-scaled architectural drawings.
3. Mechanical contractor's tray layout combined with BMS panel locations.
4. A-001 default with ±20% contingency in BOQ — last resort.