Summary
| A1 — I/O List, Audit View | |||||
| Project | Kingsford Hotel Bacolod — BMS | ||||
| Canonical source | A1-io-list.yaml | ||||
| How to record corrections | Edit the canonical YAML directly — add a verification: block to the affected row(s) | ||||
| Totals | |||||
| Total I/O points | 753 | ||||
| Unique equipment instances | 132 | ||||
| Systems represented | 9 | ||||
| Verification status | |||||
| Status | Count | % of total | |||
| verified | 0 | 0% | |||
| needs_correction | 0 | 0% | |||
| uncertain | 0 | 0% | |||
| unverified | 753 | 100% | |||
| ⚠ Known weak points | |||||
| Equipment quantities are derived from the customer's points list. Cross-verify against mechanical floor plans (Q-008) and architectural plans (Q-005). Where the points list shows aggregate counts without per-tag enumeration, the gap is captured as Q-021. | |||||
| How corrections flow | |||||
| Edit A1-io-list.yaml — add a verification: block to any row where you confirm or correct the equipment, location, or panel assignment. | |||||
| Re-run the deliverables generator to refresh downstream artifacts. | |||||
By System
| System | Equipment instances | I/O points |
| ventilation | 71 | 373 |
| hot_water | 19 | 45 |
| chilled_water | 12 | 135 |
| power_metering | 11 | 11 |
| btu_metering | 5 | 5 |
| condenser_water | 4 | 40 |
| casino_mvac | 4 | 38 |
| common_area | 4 | 64 |
| steam | 2 | 42 |
| TOTAL | 132 | 753 |
By Location
| Location | Equipment instances |
| 3rd Floor Amenity | 26 |
| 2nd Level Mechanical Room | 20 |
| Basement 1 | 16 |
| Roof Deck Mechanical | 14 |
| Lower Ground HW Plant | 10 |
| Ground Floor Lobby | 9 |
| Roof Deck HW Plant | 9 |
| Roof Deck | 6 |
| 2nd Floor BOH | 5 |
| Ground Floor | 4 |
| 2nd Floor Casino MVAC Room | 3 |
| 2nd Floor Casino | 3 |
| Lower Ground Laundry | 3 |
| Ground Floor BOH | 1 |
| Ground Floor Mezzanine BOH | 1 |
| Basement 1 BOH | 1 |
| Main Switchgear Room | 1 |
By Panel
| Panel | Equipment instances |
| BMS-PNL-3F | 26 |
| BMS-PNL-RD-MECH | 25 |
| BMS-PNL-LG-CHILLER | 20 |
| BMS-PNL-B1 | 17 |
| BMS-PNL-GF | 16 |
| BMS-PNL-LG-PLUMB | 13 |
| BMS-PNL-2F-CASINO | 11 |
| BMS-PNL-RD-CT | 4 |
Verification schema
| How to record verification / corrections in A1-io-list.yaml | |||||||
| Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block: | |||||||
| - id: chws.ch-1.entering-chw-temp | |||||||
| verification: # ADDED by team | |||||||
| status: needs_correction # unverified | verified | needs_correction | uncertain | |||||||
| verified_by: J. Cruz | |||||||
| verified_date: 2026-05-10 | |||||||
| drawing_ref: "EE-09 grid B-2" | |||||||
| notes: "" | |||||||
| After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project> | |||||||
| Corrections propagate to B4 manhours, BOQ, and final deliverables automatically. | |||||||
| Recommended verification methods (priority order): | |||||||
| 1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion). | |||||||
| 2. Properly-scaled architectural drawings. | |||||||
| 3. Mechanical contractor's tray layout combined with BMS panel locations. | |||||||
| 4. A-001 default with ±20% contingency in BOQ — last resort. | |||||||