Summary

A1 — I/O List, Audit View
ProjectKingsford Hotel Bacolod — BMS
Canonical sourceA1-io-list.yaml
How to record correctionsEdit the canonical YAML directly — add a verification: block to the affected row(s)
Totals
Total I/O points554
Unique equipment instances161
Systems represented15
Verification status
StatusCount% of total
verified00%
needs_correction00%
uncertain00%
unverified554100%
⚠ Known weak points
Equipment quantities are derived from the customer's points list. Cross-verify against mechanical floor plans (Q-008) and architectural plans (Q-005). Where the points list shows aggregate counts without per-tag enumeration, the gap is captured as Q-021.
How corrections flow
Edit A1-io-list.yaml — add a verification: block to any row where you confirm or correct the equipment, location, or panel assignment.
Re-run the deliverables generator to refresh downstream artifacts.

By System

SystemEquipment instancesI/O points
VENT-FCU90270
Power-EE1313
HVAC-Chillers816
Network88
HVAC-Pumps729
VENT-AHU672
PL-Calorifiers66
PL-RecircPumps612
HVAC-Cooling-Towers420
VENT-EAS412
VENT-DOAS363
PL-HeatPumps39
VENT-PAHU110
PL-HotWater16
PL-Boiler18
TOTAL161554

By Location

LocationEquipment instances
2F35
GF33
3F32
Plant Room27
Sub-Distribution Board10
panel8
Roofdeck7
Plant Room (Basement)3
Basement3
Main Switchgear3

By Panel

PanelEquipment instances
PNL-GF47
PNL-2F35
PNL-3F33
PNL-CHPLANT-GND31
PNL-RD8
PNL-BSMT4
PNL-BOH-2F2
PNL-HE-GF1

Verification schema

How to record verification / corrections in A1-io-list.yaml
Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block:
- id: chws.ch-1.entering-chw-temp
verification: # ADDED by team
status: needs_correction # unverified | verified | needs_correction | uncertain
verified_by: J. Cruz
verified_date: 2026-05-10
drawing_ref: "EE-09 grid B-2"
notes: ""
After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project>
Corrections propagate to B4 manhours, BOQ, and final deliverables automatically.
Recommended verification methods (priority order):
1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion).
2. Properly-scaled architectural drawings.
3. Mechanical contractor's tray layout combined with BMS panel locations.
4. A-001 default with ±20% contingency in BOQ — last resort.