Summary

Bill of Quantities — Summary
ProjectKingsford Hotel Bacolod — BMS
CurrencyPHP
Generated fromA1-A7 + B1-B4 + standard-pricing-defaults.yaml
Total line items86
RFQ-required items63
RFQ-required %73.3%
Base subtotal (PHP)16,111,720.00
Overhead & margin (18%)2,900,109.60
Cost + overhead19,011,829.60
Contingency (6.0%)1,140,709.78
Cost + contingency20,152,539.38
VAT (12%)2,418,304.73
GRAND TOTAL (PHP)22,570,844.10

Section Subtotals

WBS SectionSubtotal (PHP)
1.01,688,000.00
2.011,129,220.00
3.02,282,680.00
4.0413,220.00
5.0507,400.00
6.091,200.00
7.00.00

All Line Items

WBSDescriptionQtyUnitUnit Price (PHP)Extended (PHP)SourceRate SourceRFQ Required
1.1Project management (off-site, full duration, 16 weeks)640hr1500960000D2 PM 1 FTE × 16 wkinternal
1.1Site mobilization (week 1)80hr1500120000D1 + B4 mobilizationinternal
1.2Engineering & design (system architecture, panel layouts, IO list, sequences, network)320hr1200384000D2 engineering allocationinternal
1.3Submittals & approvals administration80hr120096000within engineering budgetinternal
1.4Factory Acceptance Test (FAT) delivery1lot8000080000D1 week 5default
1.4FAT support hours (BMS engineer)40hr120048000D2 week 5internal
2.1.1BMS Server (Primary) — dual-CPU, 16+ GB RAM, redundant PSU1each350000350000A6 HE-SVR-01default
2.1.1BMS Server (Standby, redundancy)1each350000350000A6 HE-SVR-02default
2.1.2Operator Workstation2each80000160000A6 HE-WS-01, HE-WS-02default
2.1.3Graphics PC + 55-inch Display1set150000150000A6 HE-GFX-01default
2.1.4Head-End UPS (3 kVA, 30-min runtime)1each9000090000A6 HE-UPS-01default
2.1.5Software licenses (server + 3 client + energy module + graphics editor)1lot600000600000A6 HE-SW-*default
2.1.6Server-room peripherals (KVM, console monitor, color laser printer, 19-inch rack)1lot8000080000A6 HE-PRINTER, HE-RACK, HE-KVM, HE-MONdefault
2.2.1Core managed L2/L3 switch (24-port + 4 SFP)1each120000120000A5 SW-COREdefault
2.2.2Edge managed L2 switch (16-port + 2 SFP)3each35000105000A5 SW-GND/2F/RDdefault
2.2.2Edge managed L2 switch (8-port + 2 SFP)3each1800054000A5 SW-LZ/3F/BSMTdefault
2.2.3Riser fiber, OM3 multimode 6-strand armored300m28084000A5default
2.2.3Fiber transceivers (1G SX/LX, paired)14each8000112000A5default
2.2.4IDF wall-mount enclosures (9U)6each18000108000A5default
2.3.1+2.3.2+2.3.3+2.3.4BMS field cabinet (small, IP54 wall-mount)10each40000400000A4 panels (small I/O)default
2.3.1+2.3.2+2.3.3+2.3.4BMS field cabinet (medium, IP54 wall-mount)6each80000480000A4 panels (medium I/O)default
2.3.1+2.3.2+2.3.3+2.3.4BMS field cabinet (large, IP54 wall-mount)2each150000300000A4 panels (large I/O)default
2.3.5DDC controllers (incl. network gateway controllers)30each900002700000A4 total_controllersdefault
2.3.5AI input modules (16-channel)8each4000032000093 AI + 25% spare ÷ 16 (per A3-cable-spec-rules.yaml spare_strategy)default
2.3.5AO output modules (16-channel)4each4500018000044 AO + 25% spare ÷ 16 (per A3-cable-spec-rules.yaml spare_strategy)default
2.3.5DI input modules (32-channel)8each30000240000203 DI + 15% spare ÷ 32 (per A3-cable-spec-rules.yaml spare_strategy)default
2.3.5DO output modules (16-channel)14each35000490000183 DO + 15% spare ÷ 16 (per A3-cable-spec-rules.yaml spare_strategy)default
2.3.524VDC switching power supplies (5A, redundant for 6 critical panels)24each800019200018 panels + 6 redundantdefault
2.3.5Terminal blocks (push-in 2.5 mm²)900each8072000(716 I/O × 1.25)default
2.3.5Surge protection (signal-level SPD)36each50001800002 per panel × 18default
2.3.5Cable management hardware (DIN rail, ducts, ferrules) per panel18lot8000144000per A4 paneldefault
2.4.1Temperature sensor — immersion/thermowell (water-side)12each450054000A1 BMS-supplied immersion tempsdefault
2.4.1Temperature sensor — duct insertion50each3000150000A1 BMS-supplied duct tempsdefault
2.4.1Temperature sensor — outdoor (weatherproof)1each60006000A1 ct-common.outside-air-tempdefault
2.4.2Humidity sensor (duct/outdoor)24each6500156000A1 BMS-supplied RH sensorsdefault
2.4.3Pressure sensor — water-side6each800048000A1 BMS-supplied pressuredefault
2.4.3Differential pressure sensor (CHW header)1each1200012000A1 hdr-chw-bp.diff-pressdefault
2.4.3Pressure sensor — duct static4each800032000A1 EAF static pressuredefault
2.4.4Flow sensor — water (insertion)9each25000225000A1 chiller branch flowsdefault
2.4.4BTU meter (ultrasonic, Modbus)1each8000080000A1 BTU-CHWS-MAINdefault
2.4.5Modulating valve actuator (BMS-supplied for CHW bypass)1each1200012000A1 hdr-chw-bp.iso-vlv-cmddefault
2.4.8CO2 sensor (duct return)5each800040000A1 return-air-co2default
2.4.8CO sensor (duct return, casino)2each1000020000A1 return-air-codefault
2.4.8VOC sensor (ozonizer return)2each1200024000A1 ozonizer vocdefault
2.4Mounting brackets, thermowells, valve fittings1lot20002000per device count + 5% sparedefault
2.5.1Tank temperature sensor (calorifiers)6each350021000A1 calorifier tank tempsdefault
2.5.2HW header temperature sensors (supply/return/MUCW)6each450027000A1 hdr-hw-* tempsdefault
2.5.3Pump aux-contact wiring kits (heat pumps + recirc pumps)12each150018000A1 HP + RP rowsdefault
2.5.4Boiler steam pressure sensor2each1200024000A1 sb-*.steam-pressuredefault
2.5.4Boiler feedwater temperature sensor2each45009000A1 sb-*.feedwater-tempdefault
2.5.4Boiler fluegas temperature sensor (high-temp)2each800016000A1 sb-*.fluegas-tempdefault
2.5.4Boiler fluegas O2 sensor (zirconia)2each3000060000A1 sb-*.fluegas-o2default
2.5.4Boiler motorized blowdown valve (BMS-supplied actuator)2each1800036000A1 sb-*.blowdown-vlv-cmddefault
2.6.1Multifunction power meter (Main switchgear class)3each90000270000A1 MTR-MAIN-*default
2.6.1Multifunction power meter (Sub-feeder class)10each35000350000A1 MTR-FDR-*default
2.6.2Current transformers (split-core, sized per ampacity)39each400015600013 meters × 3 phasesdefault
2.6.4Modbus serial-to-IP gateway2each25000500001 per switchgear groupdefault
2.6Modbus shielded TP cable300m8024000A3 ee_metering trunksdefault
2.7.14C × 1.5 mm² shielded FRLS control/signal cable6314m95599830A3 field cables (BMS/ME/EQ-supplier)default
2.7.16C × 1.5 mm² shielded FRLS (where conductor count > 4)549m13071370A3 field cables (wider runs)default
2.7.2BACnet MS/TP shielded TP cable (low-cap)150m9013500A3 trunkdefault
2.7.3Cat6 4P × 23 AWG U/UTP FRLS cable700m9063000A3 network drops + trunkdefault
2.7.5Conduit (PVC HW 25 mm)2233m12026796030% of total cable lengthdefault
2.73C × 2.5 mm² FRLS panel power feed cable96m11010560A3 panel power feedsdefault
2.7.6Cable identification (labels, ferrules, marker tags) — full project lot1lot3000030000per cable countdefault
2.7.5Cable management (junction boxes, cable ties) per panel field18lot500090000per paneldefault
3.0Installation labor — Wireman / Electrician (cable pulling, conduit, panel install, terminations)2839.6hr350993860B4 total 4368.6 hr × 65% trade splitinternal
3.0Installation labor — BMS Technician (testing, pre-comm)1092.2hr700764540B4 total 4368.6 hr × 25%internal
3.0Installation labor — Engineer / Supervisor (oversight, fault resolution)436.9hr1200524280B4 total 4368.6 hr × 10%internal
4.1Controller programming (point database, control loops, schedules, alarms, reports, trends)193.1hr1200231720B1 programming hoursinternal
4.2Graphics development (35 pages: navigation, floor, system, popups, alarm, trend, reports)165hr1100181500B2 graphics hoursinternal
5.1Pre-commissioning (cable continuity, megger, panel power-up smoke test) — covered in B40lot00B4 coveredinternal
5.2Point-to-point (P2P) testing78.5hr70054950B3 h_p2pinternal
5.3Functional testing per equipment241.5hr700169050B3 h_functionalinternal
5.4Integrated commissioning (cross-system sequences, energy savings)32hr120038400B3 h_integratedinternal
5.5Owner T&C / SAT support (1 week)40hr120048000D2 SAT weekinternal
5.6Snagging / punch-list resolution30hr70021000typical for medium projectinternal
5.7As-built documentation package (drawings, O&M, point database, programming archive)1lot8000080000D2 docs allocationdefault
5.7As-built documentation engineer hours80hr120096000D2 docs allocationinternal
6.1Operator training — on-site, 16 hours over 2 days, up to 6 operators1lot6000060000A-013 (default)default
6.1Training delivery hours (1 trainer × 16 hr)16hr120019200trainer timeinternal
6.3Documentation handover (formal, with sign-off)8hr150012000week 16internal
7.1[OPTION] 1-year preventive maintenance contract (post-warranty)1yr00Q-016 dependent — quote separatelyrfq
7.2[OPTION] Additional administrator training (8 hr session)0lot300000Q-015 dependentdefault
7.3[OPTION] FDAS integration (BACnet/Modbus from fire panel + smoke control sequences)0lot00Q-012 dependent — TBDrfq
7.4[OPTION] PMS integration (guestroom occupancy → BMS for FCU control)0lot00Q-012 dependent — TBDrfq

1.0 PM & Engineering

WBSDescriptionQtyUnitUnit Price (PHP)Extended (PHP)SourceRFQ?
1.1Project management (off-site, full duration, 16 weeks)640hr1500960000D2 PM 1 FTE × 16 wk
1.1Site mobilization (week 1)80hr1500120000D1 + B4 mobilization
1.2Engineering & design (system architecture, panel layouts, IO list, sequences, network)320hr1200384000D2 engineering allocation
1.3Submittals & approvals administration80hr120096000within engineering budget
1.4Factory Acceptance Test (FAT) delivery1lot8000080000D1 week 5
1.4FAT support hours (BMS engineer)40hr120048000D2 week 5

2.0 Material Supply

WBSDescriptionQtyUnitUnit Price (PHP)Extended (PHP)SourceRFQ?
2.1.1BMS Server (Primary) — dual-CPU, 16+ GB RAM, redundant PSU1each350000350000A6 HE-SVR-01
2.1.1BMS Server (Standby, redundancy)1each350000350000A6 HE-SVR-02
2.1.2Operator Workstation2each80000160000A6 HE-WS-01, HE-WS-02
2.1.3Graphics PC + 55-inch Display1set150000150000A6 HE-GFX-01
2.1.4Head-End UPS (3 kVA, 30-min runtime)1each9000090000A6 HE-UPS-01
2.1.5Software licenses (server + 3 client + energy module + graphics editor)1lot600000600000A6 HE-SW-*
2.1.6Server-room peripherals (KVM, console monitor, color laser printer, 19-inch rack)1lot8000080000A6 HE-PRINTER, HE-RACK, HE-KVM, HE-MON
2.2.1Core managed L2/L3 switch (24-port + 4 SFP)1each120000120000A5 SW-CORE
2.2.2Edge managed L2 switch (16-port + 2 SFP)3each35000105000A5 SW-GND/2F/RD
2.2.2Edge managed L2 switch (8-port + 2 SFP)3each1800054000A5 SW-LZ/3F/BSMT
2.2.3Riser fiber, OM3 multimode 6-strand armored300m28084000A5
2.2.3Fiber transceivers (1G SX/LX, paired)14each8000112000A5
2.2.4IDF wall-mount enclosures (9U)6each18000108000A5
2.3.1+2.3.2+2.3.3+2.3.4BMS field cabinet (small, IP54 wall-mount)10each40000400000A4 panels (small I/O)
2.3.1+2.3.2+2.3.3+2.3.4BMS field cabinet (medium, IP54 wall-mount)6each80000480000A4 panels (medium I/O)
2.3.1+2.3.2+2.3.3+2.3.4BMS field cabinet (large, IP54 wall-mount)2each150000300000A4 panels (large I/O)
2.3.5DDC controllers (incl. network gateway controllers)30each900002700000A4 total_controllers
2.3.5AI input modules (16-channel)8each4000032000093 AI + 25% spare ÷ 16 (per A3-cable-spec-rules.yaml spare_strategy)
2.3.5AO output modules (16-channel)4each4500018000044 AO + 25% spare ÷ 16 (per A3-cable-spec-rules.yaml spare_strategy)
2.3.5DI input modules (32-channel)8each30000240000203 DI + 15% spare ÷ 32 (per A3-cable-spec-rules.yaml spare_strategy)
2.3.5DO output modules (16-channel)14each35000490000183 DO + 15% spare ÷ 16 (per A3-cable-spec-rules.yaml spare_strategy)
2.3.524VDC switching power supplies (5A, redundant for 6 critical panels)24each800019200018 panels + 6 redundant
2.3.5Terminal blocks (push-in 2.5 mm²)900each8072000(716 I/O × 1.25)
2.3.5Surge protection (signal-level SPD)36each50001800002 per panel × 18
2.3.5Cable management hardware (DIN rail, ducts, ferrules) per panel18lot8000144000per A4 panel
2.4.1Temperature sensor — immersion/thermowell (water-side)12each450054000A1 BMS-supplied immersion temps
2.4.1Temperature sensor — duct insertion50each3000150000A1 BMS-supplied duct temps
2.4.1Temperature sensor — outdoor (weatherproof)1each60006000A1 ct-common.outside-air-temp
2.4.2Humidity sensor (duct/outdoor)24each6500156000A1 BMS-supplied RH sensors
2.4.3Pressure sensor — water-side6each800048000A1 BMS-supplied pressure
2.4.3Differential pressure sensor (CHW header)1each1200012000A1 hdr-chw-bp.diff-press
2.4.3Pressure sensor — duct static4each800032000A1 EAF static pressure
2.4.4Flow sensor — water (insertion)9each25000225000A1 chiller branch flows
2.4.4BTU meter (ultrasonic, Modbus)1each8000080000A1 BTU-CHWS-MAIN
2.4.5Modulating valve actuator (BMS-supplied for CHW bypass)1each1200012000A1 hdr-chw-bp.iso-vlv-cmd
2.4.8CO2 sensor (duct return)5each800040000A1 return-air-co2
2.4.8CO sensor (duct return, casino)2each1000020000A1 return-air-co
2.4.8VOC sensor (ozonizer return)2each1200024000A1 ozonizer voc
2.4Mounting brackets, thermowells, valve fittings1lot20002000per device count + 5% spare
2.5.1Tank temperature sensor (calorifiers)6each350021000A1 calorifier tank temps
2.5.2HW header temperature sensors (supply/return/MUCW)6each450027000A1 hdr-hw-* temps
2.5.3Pump aux-contact wiring kits (heat pumps + recirc pumps)12each150018000A1 HP + RP rows
2.5.4Boiler steam pressure sensor2each1200024000A1 sb-*.steam-pressure
2.5.4Boiler feedwater temperature sensor2each45009000A1 sb-*.feedwater-temp
2.5.4Boiler fluegas temperature sensor (high-temp)2each800016000A1 sb-*.fluegas-temp
2.5.4Boiler fluegas O2 sensor (zirconia)2each3000060000A1 sb-*.fluegas-o2
2.5.4Boiler motorized blowdown valve (BMS-supplied actuator)2each1800036000A1 sb-*.blowdown-vlv-cmd
2.6.1Multifunction power meter (Main switchgear class)3each90000270000A1 MTR-MAIN-*
2.6.1Multifunction power meter (Sub-feeder class)10each35000350000A1 MTR-FDR-*
2.6.2Current transformers (split-core, sized per ampacity)39each400015600013 meters × 3 phases
2.6.4Modbus serial-to-IP gateway2each25000500001 per switchgear group
2.6Modbus shielded TP cable300m8024000A3 ee_metering trunks
2.7.14C × 1.5 mm² shielded FRLS control/signal cable6314m95599830A3 field cables (BMS/ME/EQ-supplier)
2.7.16C × 1.5 mm² shielded FRLS (where conductor count > 4)549m13071370A3 field cables (wider runs)
2.7.2BACnet MS/TP shielded TP cable (low-cap)150m9013500A3 trunk
2.7.3Cat6 4P × 23 AWG U/UTP FRLS cable700m9063000A3 network drops + trunk
2.7.5Conduit (PVC HW 25 mm)2233m12026796030% of total cable length
2.73C × 2.5 mm² FRLS panel power feed cable96m11010560A3 panel power feeds
2.7.6Cable identification (labels, ferrules, marker tags) — full project lot1lot3000030000per cable count
2.7.5Cable management (junction boxes, cable ties) per panel field18lot500090000per panel

3.0 Installation

WBSDescriptionQtyUnitUnit Price (PHP)Extended (PHP)SourceRFQ?
3.0Installation labor — Wireman / Electrician (cable pulling, conduit, panel install, terminations)2839.6hr350993860B4 total 4368.6 hr × 65% trade split
3.0Installation labor — BMS Technician (testing, pre-comm)1092.2hr700764540B4 total 4368.6 hr × 25%
3.0Installation labor — Engineer / Supervisor (oversight, fault resolution)436.9hr1200524280B4 total 4368.6 hr × 10%

4.0 Programming

WBSDescriptionQtyUnitUnit Price (PHP)Extended (PHP)SourceRFQ?
4.1Controller programming (point database, control loops, schedules, alarms, reports, trends)193.1hr1200231720B1 programming hours
4.2Graphics development (35 pages: navigation, floor, system, popups, alarm, trend, reports)165hr1100181500B2 graphics hours

5.0 T&C

WBSDescriptionQtyUnitUnit Price (PHP)Extended (PHP)SourceRFQ?
5.1Pre-commissioning (cable continuity, megger, panel power-up smoke test) — covered in B40lot00B4 covered
5.2Point-to-point (P2P) testing78.5hr70054950B3 h_p2p
5.3Functional testing per equipment241.5hr700169050B3 h_functional
5.4Integrated commissioning (cross-system sequences, energy savings)32hr120038400B3 h_integrated
5.5Owner T&C / SAT support (1 week)40hr120048000D2 SAT week
5.6Snagging / punch-list resolution30hr70021000typical for medium project
5.7As-built documentation package (drawings, O&M, point database, programming archive)1lot8000080000D2 docs allocation
5.7As-built documentation engineer hours80hr120096000D2 docs allocation

6.0 Training

WBSDescriptionQtyUnitUnit Price (PHP)Extended (PHP)SourceRFQ?
6.1Operator training — on-site, 16 hours over 2 days, up to 6 operators1lot6000060000A-013 (default)
6.1Training delivery hours (1 trainer × 16 hr)16hr120019200trainer time
6.3Documentation handover (formal, with sign-off)8hr150012000week 16

7.0 Optional

WBSDescriptionQtyUnitUnit Price (PHP)Extended (PHP)SourceRFQ?
7.1[OPTION] 1-year preventive maintenance contract (post-warranty)1yr00Q-016 dependent — quote separately
7.2[OPTION] Additional administrator training (8 hr session)0lot300000Q-015 dependent
7.3[OPTION] FDAS integration (BACnet/Modbus from fire panel + smoke control sequences)0lot00Q-012 dependent — TBD
7.4[OPTION] PMS integration (guestroom occupancy → BMS for FCU control)0lot00Q-012 dependent — TBD

RFQ Required

WBSDescriptionQtyUnitPlaceholder Rate (PHP)Extended (PHP)
2.1.1BMS Server (Primary) — dual-CPU, 16+ GB RAM, redundant PSU1each350000350000
2.1.1BMS Server (Standby, redundancy)1each350000350000
2.1.2Operator Workstation2each80000160000
2.1.3Graphics PC + 55-inch Display1set150000150000
2.1.4Head-End UPS (3 kVA, 30-min runtime)1each9000090000
2.1.5Software licenses (server + 3 client + energy module + graphics editor)1lot600000600000
2.1.6Server-room peripherals (KVM, console monitor, color laser printer, 19-inch rack)1lot8000080000
2.2.1Core managed L2/L3 switch (24-port + 4 SFP)1each120000120000
2.2.2Edge managed L2 switch (16-port + 2 SFP)3each35000105000
2.2.2Edge managed L2 switch (8-port + 2 SFP)3each1800054000
2.2.3Riser fiber, OM3 multimode 6-strand armored300m28084000
2.2.3Fiber transceivers (1G SX/LX, paired)14each8000112000
2.2.4IDF wall-mount enclosures (9U)6each18000108000
2.3.1+2.3.2+2.3.3+2.3.4BMS field cabinet (small, IP54 wall-mount)10each40000400000
2.3.1+2.3.2+2.3.3+2.3.4BMS field cabinet (medium, IP54 wall-mount)6each80000480000
2.3.1+2.3.2+2.3.3+2.3.4BMS field cabinet (large, IP54 wall-mount)2each150000300000
2.3.5DDC controllers (incl. network gateway controllers)30each900002700000
2.3.5AI input modules (16-channel)8each40000320000
2.3.5AO output modules (16-channel)4each45000180000
2.3.5DI input modules (32-channel)8each30000240000
2.3.5DO output modules (16-channel)14each35000490000
2.3.524VDC switching power supplies (5A, redundant for 6 critical panels)24each8000192000
2.3.5Terminal blocks (push-in 2.5 mm²)900each8072000
2.3.5Surge protection (signal-level SPD)36each5000180000
2.3.5Cable management hardware (DIN rail, ducts, ferrules) per panel18lot8000144000
2.4.1Temperature sensor — immersion/thermowell (water-side)12each450054000
2.4.1Temperature sensor — duct insertion50each3000150000
2.4.1Temperature sensor — outdoor (weatherproof)1each60006000
2.4.2Humidity sensor (duct/outdoor)24each6500156000
2.4.3Pressure sensor — water-side6each800048000
2.4.3Differential pressure sensor (CHW header)1each1200012000
2.4.3Pressure sensor — duct static4each800032000
2.4.4Flow sensor — water (insertion)9each25000225000
2.4.4BTU meter (ultrasonic, Modbus)1each8000080000
2.4.5Modulating valve actuator (BMS-supplied for CHW bypass)1each1200012000
2.4.8CO2 sensor (duct return)5each800040000
2.4.8CO sensor (duct return, casino)2each1000020000
2.4.8VOC sensor (ozonizer return)2each1200024000
2.4Mounting brackets, thermowells, valve fittings1lot20002000
2.5.1Tank temperature sensor (calorifiers)6each350021000
2.5.2HW header temperature sensors (supply/return/MUCW)6each450027000
2.5.3Pump aux-contact wiring kits (heat pumps + recirc pumps)12each150018000
2.5.4Boiler steam pressure sensor2each1200024000
2.5.4Boiler feedwater temperature sensor2each45009000
2.5.4Boiler fluegas temperature sensor (high-temp)2each800016000
2.5.4Boiler fluegas O2 sensor (zirconia)2each3000060000
2.5.4Boiler motorized blowdown valve (BMS-supplied actuator)2each1800036000
2.6.1Multifunction power meter (Main switchgear class)3each90000270000
2.6.1Multifunction power meter (Sub-feeder class)10each35000350000
2.6.2Current transformers (split-core, sized per ampacity)39each4000156000
2.6.4Modbus serial-to-IP gateway2each2500050000
2.6Modbus shielded TP cable300m8024000
2.7.14C × 1.5 mm² shielded FRLS control/signal cable6314m95599830
2.7.16C × 1.5 mm² shielded FRLS (where conductor count > 4)549m13071370
2.7.2BACnet MS/TP shielded TP cable (low-cap)150m9013500
2.7.3Cat6 4P × 23 AWG U/UTP FRLS cable700m9063000
2.7.5Conduit (PVC HW 25 mm)2233m120267960
2.73C × 2.5 mm² FRLS panel power feed cable96m11010560
2.7.6Cable identification (labels, ferrules, marker tags) — full project lot1lot3000030000
2.7.5Cable management (junction boxes, cable ties) per panel field18lot500090000
7.1[OPTION] 1-year preventive maintenance contract (post-warranty)1yr00
7.3[OPTION] FDAS integration (BACnet/Modbus from fire panel + smoke control sequences)0lot00
7.4[OPTION] PMS integration (guestroom occupancy → BMS for FCU control)0lot00