Summary

A2 — Equipment Takeoff, Audit View
ProjectKingsford Hotel Bacolod — BMS (AB-Run-2)
Canonical sourceA2-equipment-takeoff.yaml
How to record correctionsEdit the canonical YAML directly — add a verification: block to the affected row(s)
Totals
Total equipment instances59
Equipment classes25
Locations13
Verification status
StatusCount% of total
verified00%
needs_correction00%
uncertain00%
unverified59100%
⚠ Known weak points
Verify quantities and locations against mechanical / electrical drawings. The 'Make/Model' field is a generic class default — supplier RFQ refines.
How corrections flow
Edit A2-equipment-takeoff.yaml — add a verification: block to the affected row when location or count is confirmed/corrected.

By Class

Equipment classCount
Multifunction Power Meter (Feeder)8
AHU (Chilled-Water-Served)5
Exhaust Fan (General)5
Exhaust Fan (Toilet)4
AHU (Modulating CHW-served)3
Condenser Water Pump3
DOAS Unit3
Recirculating Pump3
Precooled Air Handling Unit3
Steam Boiler2
Calorifier (Hot Water Storage Tank)2
Chiller (Package Water-Cooled)2
Primary CHW Pump2
Cooling Tower2
Heat Pump2
BTU Meter1
CHW Bypass Header1
CHW Return Main Header1
CHW Supply Main Header1
Primary CHW Pump (Standby)1
Cooling Tower (Common)1
Condenser Water Header1
Hot Water Header Set1
Ozone Generator (UV-light or Corona)1
Multifunction Power Meter (Main)1
TOTAL59

By Location

LocationCount
2F Chiller Plant Room13
2F Common Public7
Roofdeck DOAS7
Lower Ground Calorifier Room6
Roofdeck Cooling Tower5
Ground Floor Casino4
Ground Floor Lobby4
Lower Ground Boiler Room4
3F Amenity3
Basement BOH3
Ground Floor Casino Lobby1
Ground Floor Restaurant1
Lower Ground Main Switchgear1

Detail

IDClassLocationPanelPrimary C/OStatusVerified byDateDrawing refNotes
AHU-2F-AAHU (Chilled-Water-Served)2F Common PublicPNL-AIR-2FEquipment Supplierunverified
AHU-2F-BAHU (Chilled-Water-Served)2F Common PublicPNL-AIR-2FEquipment Supplierunverified
AHU-3F-AMAHU (Chilled-Water-Served)3F AmenityPNL-AIR-3FEquipment Supplierunverified
AHU-CASINO-1AHU (Modulating CHW-served)Ground Floor CasinoPNL-CASINO-GFEquipment Supplierunverified
AHU-CASINO-2AHU (Modulating CHW-served)Ground Floor CasinoPNL-CASINO-GFEquipment Supplierunverified
AHU-GF-CASINOAHU (Modulating CHW-served)Ground Floor Casino LobbyPNL-CASINO-GFEquipment Supplierunverified
AHU-GF-LOBAHU (Chilled-Water-Served)Ground Floor LobbyPNL-AIR-GFEquipment Supplierunverified
AHU-GF-RESTAHU (Chilled-Water-Served)Ground Floor RestaurantPNL-AIR-GFEquipment Supplierunverified
BLR-1Steam BoilerLower Ground Boiler RoomPNL-BLR-LGEquipment Supplierunverified
BLR-2Steam BoilerLower Ground Boiler RoomPNL-BLR-LGEquipment Supplierunverified
BTU-CHW-MAINBTU Meter2F Chiller Plant RoomPNL-CH-PLANT-2FBMS Contractorunverified
CALOR-LGCalorifier (Hot Water Storage Tank)Lower Ground Calorifier RoomPNL-PL-LGBMS Contractorunverified
CALOR-ROOFCalorifier (Hot Water Storage Tank)Roofdeck DOASPNL-AIR-ROOFBMS Contractorunverified
CH-1Chiller (Package Water-Cooled)2F Chiller Plant RoomPNL-CH-PLANT-2FEquipment Supplierunverified
CH-2Chiller (Package Water-Cooled)2F Chiller Plant RoomPNL-CH-PLANT-2FEquipment Supplierunverified
CHW-BYPCHW Bypass Header2F Chiller Plant RoomPNL-CH-PLANT-2FBMS Contractorunverified
CHW-RET-HDRCHW Return Main Header2F Chiller Plant RoomPNL-CH-PLANT-2FBMS Contractorunverified
CHW-SUP-HDRCHW Supply Main Header2F Chiller Plant RoomPNL-CH-PLANT-2FBMS Contractorunverified
CHWP-1Primary CHW Pump2F Chiller Plant RoomPNL-CH-PLANT-2FEquipment Supplierunverified
CHWP-2Primary CHW Pump2F Chiller Plant RoomPNL-CH-PLANT-2FEquipment Supplierunverified
CHWP-3Primary CHW Pump (Standby)2F Chiller Plant RoomPNL-CH-PLANT-2FEquipment Supplierunverified
CT-1Cooling TowerRoofdeck Cooling TowerPNL-CT-ROOFBMS Contractorunverified
CT-2Cooling TowerRoofdeck Cooling TowerPNL-CT-ROOFBMS Contractorunverified
CT-COMMONCooling Tower (Common)Roofdeck Cooling TowerPNL-CT-ROOFBMS Contractorunverified
CW-HDRCondenser Water HeaderRoofdeck Cooling TowerPNL-CT-ROOFBMS Contractorunverified
CWP-1Condenser Water Pump2F Chiller Plant RoomPNL-CH-PLANT-2FEquipment Supplierunverified
CWP-2Condenser Water Pump2F Chiller Plant RoomPNL-CH-PLANT-2FEquipment Supplierunverified
CWP-3Condenser Water Pump2F Chiller Plant RoomPNL-CH-PLANT-2FEquipment Supplierunverified
DOAS-2FDOAS Unit2F Common PublicPNL-AIR-2FEquipment Supplierunverified
DOAS-RD1DOAS UnitRoofdeck DOASPNL-AIR-ROOFEquipment Supplierunverified
DOAS-RD2DOAS UnitRoofdeck DOASPNL-AIR-ROOFEquipment Supplierunverified
EAS-GEN-2FExhaust Fan (General)2F Common PublicPNL-AIR-2FEquipment Supplierunverified
EAS-GEN-3FExhaust Fan (General)3F AmenityPNL-AIR-3FEquipment Supplierunverified
EAS-GEN-BSMTExhaust Fan (General)Basement BOHPNL-AIR-BSMTEquipment Supplierunverified
EAS-GEN-GFExhaust Fan (General)Ground Floor LobbyPNL-AIR-GFEquipment Supplierunverified
EAS-GEN-ROOFExhaust Fan (General)Roofdeck DOASPNL-AIR-ROOFEquipment Supplierunverified
EAS-TOILET-2FExhaust Fan (Toilet)2F Common PublicPNL-AIR-2FEquipment Supplierunverified
EAS-TOILET-3FExhaust Fan (Toilet)3F AmenityPNL-AIR-3FEquipment Supplierunverified
EAS-TOILET-BSMTExhaust Fan (Toilet)Basement BOHPNL-AIR-BSMTEquipment Supplierunverified
EAS-TOILET-GFExhaust Fan (Toilet)Ground Floor LobbyPNL-AIR-GFEquipment Supplierunverified
HP-LG-1Heat PumpLower Ground Calorifier RoomPNL-PL-LGEquipment Supplierunverified
HP-ROOF-1Heat PumpRoofdeck DOASPNL-AIR-ROOFEquipment Supplierunverified
HW-HEADERS-LGHot Water Header SetLower Ground Calorifier RoomPNL-PL-LGBMS Contractorunverified
HW-PUMP-LG-1Recirculating PumpLower Ground Calorifier RoomPNL-PL-LGEquipment Supplierunverified
HW-PUMP-LG-2Recirculating PumpLower Ground Calorifier RoomPNL-PL-LGEquipment Supplierunverified
HW-PUMP-ROOF-1Recirculating PumpRoofdeck DOASPNL-AIR-ROOFEquipment Supplierunverified
OZ-CASINO-1Ozone Generator (UV-light or Corona)Ground Floor CasinoPNL-CASINO-GFEquipment Supplierunverified
PAHU-2FPrecooled Air Handling Unit2F Common PublicPNL-AIR-2FEquipment Supplierunverified
PAHU-BSMTPrecooled Air Handling UnitBasement BOHPNL-AIR-BSMTEquipment Supplierunverified
PAHU-ROOFPrecooled Air Handling UnitRoofdeck DOASPNL-AIR-ROOFEquipment Supplierunverified
PM-AIR-2FMultifunction Power Meter (Feeder)2F Common PublicPNL-AIR-2FBMS Contractorunverified
PM-AIR-GFMultifunction Power Meter (Feeder)Ground Floor LobbyPNL-AIR-GFBMS Contractorunverified
PM-BOILERMultifunction Power Meter (Feeder)Lower Ground Boiler RoomPNL-BLR-LGBMS Contractorunverified
PM-CASINOMultifunction Power Meter (Feeder)Ground Floor CasinoPNL-CASINO-GFBMS Contractorunverified
PM-CHILLERMultifunction Power Meter (Feeder)2F Chiller Plant RoomPNL-CH-PLANT-2FBMS Contractorunverified
PM-COOLINGMultifunction Power Meter (Feeder)Roofdeck Cooling TowerPNL-CT-ROOFBMS Contractorunverified
PM-FIREPMPMultifunction Power Meter (Feeder)Lower Ground Boiler RoomPNL-PL-LGBMS Contractorunverified
PM-MAIN-LGMultifunction Power Meter (Main)Lower Ground Main SwitchgearPNL-PM-LGBMS Contractorunverified
PM-PLUMBMultifunction Power Meter (Feeder)Lower Ground Calorifier RoomPNL-PL-LGBMS Contractorunverified

Verification schema

How to record verification / corrections in A2-equipment-takeoff.yaml
Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block:
- id: AHU-01
verification: # ADDED by team
status: needs_correction # unverified | verified | needs_correction | uncertain
corrected_location: 3rd Floor Mech Room # team's measured / confirmed value
verified_by: J. Cruz
verified_date: 2026-05-10
drawing_ref: "EE-09 grid B-2"
notes: ""
After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project>
Corrections propagate to B4 manhours, BOQ, and final deliverables automatically.
Recommended verification methods (priority order):
1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion).
2. Properly-scaled architectural drawings.
3. Mechanical contractor's tray layout combined with BMS panel locations.
4. A-001 default with ±20% contingency in BOQ — last resort.