Summary

A2 — Equipment Takeoff, Audit View
ProjectKingsford Hotel Bacolod — BMS Rehabilitation (A/B run)
Canonical sourceA2-equipment-takeoff.yaml
How to record correctionsEdit the canonical YAML directly — add a verification: block to the affected row(s)
Totals
Total equipment instances125
Equipment classes24
Locations10
Verification status
StatusCount% of total
verified00%
needs_correction00%
uncertain00%
unverified125100%
⚠ Known weak points
Verify quantities and locations against mechanical / electrical drawings. The 'Make/Model' field is a generic class default — supplier RFQ refines.
How corrections flow
Edit A2-equipment-takeoff.yaml — add a verification: block to the affected row when location or count is confirmed/corrected.

By Class

Equipment classCount
Exhaust Fan (Toilet)32
Exhaust Fan (General)17
AHU (Chilled-Water-Served)10
Precooled Air Handling Unit8
Multifunction Power Meter (Feeder)7
Heat Pump6
Calorifier (Hot Water Storage Tank)6
Recirculating Pump6
Multifunction Power Meter (Main)4
Chiller (Package Water-Cooled)3
Cooling Tower3
DOAS Unit3
Primary CHW Pump3
Condenser Water Pump3
AHU (Modulating CHW-served)2
Steam Boiler2
Hot Water Header Set2
Ozone Generator (UV-light or Corona)2
CHW Bypass Header1
CHW Return Main Header1
CHW Supply Main Header1
Condenser Water Header1
Cooling Tower (Common)1
Primary CHW Pump (Standby)1
TOTAL125

By Location

LocationCount
2nd Floor25
2nd Floor (Plant Room)22
3rd Floor (Guestroom)20
Roofdeck19
Ground Floor12
Lower Ground12
3rd Floor (Amenity)7
2nd Floor (Casino)5
Basement (Genset)2
Basement1

Detail

IDClassLocationPanelPrimary C/OStatusVerified byDateDrawing refNotes
AHU-1.1AHU (Chilled-Water-Served)Ground FloorFCP-GFEquipment Supplierunverified
AHU-1.2AHU (Chilled-Water-Served)Ground FloorFCP-GFEquipment Supplierunverified
AHU-1.3AHU (Chilled-Water-Served)Ground FloorFCP-GFEquipment Supplierunverified
AHU-2M.1AHU (Modulating CHW-served)2nd Floor (Casino)FCP-2FBMS Contractorunverified
AHU-2M.2AHU (Modulating CHW-served)2nd Floor (Casino)FCP-2FBMS Contractorunverified
AHU-B.1AHU (Chilled-Water-Served)2nd FloorFCP-2FEquipment Supplierunverified
AHU-B.2AHU (Chilled-Water-Served)2nd FloorFCP-2FEquipment Supplierunverified
AHU-B.3AHU (Chilled-Water-Served)2nd FloorFCP-2FEquipment Supplierunverified
AHU-ELAHU (Chilled-Water-Served)2nd FloorFCP-2FEquipment Supplierunverified
AHU-FR2AHU (Chilled-Water-Served)2nd FloorFCP-2FEquipment Supplierunverified
AHU-FR3AHU (Chilled-Water-Served)2nd FloorFCP-2FEquipment Supplierunverified
AHU-PFAHU (Chilled-Water-Served)2nd FloorFCP-2FEquipment Supplierunverified
ATS-1Multifunction Power Meter (Main)Basement (Genset)FCP-BSMTEE Contractorunverified
BLR-1Steam BoilerLower GroundFCP-BSMTEquipment Supplierunverified
BLR-2Steam BoilerLower GroundFCP-BSMTEquipment Supplierunverified
CH-1Chiller (Package Water-Cooled)2nd Floor (Plant Room)MCP-PLANTEquipment Supplierunverified
CH-2Chiller (Package Water-Cooled)2nd Floor (Plant Room)MCP-PLANTEquipment Supplierunverified
CH-3Chiller (Package Water-Cooled)2nd Floor (Plant Room)MCP-PLANTEquipment Supplierunverified
CHW-BYPASSCHW Bypass Header2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
CHW-HDR-RCHW Return Main Header2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
CHW-HDR-SCHW Supply Main Header2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
COW-HDRCondenser Water HeaderRoofdeckFCP-RDBMS Contractorunverified
CT-1Cooling TowerRoofdeckFCP-RDBMS Contractorunverified
CT-2Cooling TowerRoofdeckFCP-RDBMS Contractorunverified
CT-3Cooling TowerRoofdeckFCP-RDBMS Contractorunverified
CT-COMMONCooling Tower (Common)RoofdeckFCP-RDBMS Contractorunverified
DOAS-2MDOAS Unit2nd Floor (Casino)FCP-2FEquipment Supplierunverified
DOAS-RD.1DOAS UnitRoofdeckFCP-RDEquipment Supplierunverified
DOAS-RD.2DOAS UnitRoofdeckFCP-RDEquipment Supplierunverified
EF-1.2AExhaust Fan (General)Ground FloorFCP-GFEquipment Supplierunverified
EF-1MR.1Exhaust Fan (General)Ground FloorFCP-GFEquipment Supplierunverified
EF-1ST0.1Exhaust Fan (General)Ground FloorFCP-GFEquipment Supplierunverified
EF-2.1Exhaust Fan (General)2nd FloorFCP-2FEquipment Supplierunverified
EF-2.2Exhaust Fan (General)2nd FloorFCP-2FEquipment Supplierunverified
EF-2.3Exhaust Fan (General)2nd FloorFCP-2FEquipment Supplierunverified
EF-2.4Exhaust Fan (General)2nd FloorFCP-2FEquipment Supplierunverified
EF-2B.1Exhaust Fan (General)2nd FloorFCP-2FEquipment Supplierunverified
EF-2B.2Exhaust Fan (General)2nd FloorFCP-2FEquipment Supplierunverified
EF-3GE.1Exhaust Fan (General)3rd Floor (Amenity)FCP-3FEquipment Supplierunverified
EF-3GE.2Exhaust Fan (General)3rd Floor (Amenity)FCP-3FEquipment Supplierunverified
EF-CHR.1Exhaust Fan (General)2nd FloorFCP-2FEquipment Supplierunverified
EF-CHR.2Exhaust Fan (General)2nd FloorFCP-2FEquipment Supplierunverified
EF-GS.1Exhaust Fan (General)2nd FloorFCP-2FEquipment Supplierunverified
EF-GS.2Exhaust Fan (General)2nd FloorFCP-2FEquipment Supplierunverified
EF-LPG.1Exhaust Fan (General)Ground FloorFCP-GFEquipment Supplierunverified
EF-MRF.1Exhaust Fan (General)Ground FloorFCP-GFEquipment Supplierunverified
GEN-1Multifunction Power Meter (Main)Basement (Genset)FCP-BSMTEE Contractorunverified
HP-HZ.1Heat PumpRoofdeckFCP-RDEquipment Supplierunverified
HP-HZ.2Heat PumpRoofdeckFCP-RDEquipment Supplierunverified
HP-HZ.3Heat PumpRoofdeckFCP-RDEquipment Supplierunverified
HP-LZ.1Heat PumpLower GroundFCP-BSMTEquipment Supplierunverified
HP-LZ.2Heat PumpLower GroundFCP-BSMTEquipment Supplierunverified
HP-LZ.3Heat PumpLower GroundFCP-BSMTEquipment Supplierunverified
HW-HDR-HZHot Water Header SetRoofdeckFCP-RDBMS Contractorunverified
HW-HDR-LZHot Water Header SetLower GroundFCP-BSMTBMS Contractorunverified
HWT-HZ.1Calorifier (Hot Water Storage Tank)RoofdeckFCP-RDBMS Contractorunverified
HWT-HZ.2Calorifier (Hot Water Storage Tank)RoofdeckFCP-RDBMS Contractorunverified
HWT-HZ.3Calorifier (Hot Water Storage Tank)RoofdeckFCP-RDBMS Contractorunverified
HWT-LZ.1Calorifier (Hot Water Storage Tank)Lower GroundFCP-BSMTBMS Contractorunverified
HWT-LZ.2Calorifier (Hot Water Storage Tank)Lower GroundFCP-BSMTBMS Contractorunverified
HWT-LZ.3Calorifier (Hot Water Storage Tank)Lower GroundFCP-BSMTBMS Contractorunverified
ION-2M.1Ozone Generator (UV-light or Corona)2nd Floor (Casino)FCP-2FEquipment Supplierunverified
ION-2M.2Ozone Generator (UV-light or Corona)2nd Floor (Casino)FCP-2FEquipment Supplierunverified
PAHU-0.1Precooled Air Handling UnitBasementFCP-BSMTEquipment Supplierunverified
PAHU-B1Precooled Air Handling Unit2nd FloorFCP-2FEquipment Supplierunverified
PAHU-B2Precooled Air Handling Unit2nd FloorFCP-2FEquipment Supplierunverified
PAHU-B3Precooled Air Handling Unit2nd FloorFCP-2FEquipment Supplierunverified
PAHU-FRPrecooled Air Handling Unit2nd FloorFCP-2FEquipment Supplierunverified
PAHU-PFPrecooled Air Handling Unit2nd FloorFCP-2FEquipment Supplierunverified
PAHU-RD.1Precooled Air Handling UnitRoofdeckFCP-RDEquipment Supplierunverified
PAHU-RD.2Precooled Air Handling UnitRoofdeckFCP-RDEquipment Supplierunverified
PCHW-1Primary CHW Pump2nd Floor (Plant Room)MCP-PLANTEquipment Supplierunverified
PCHW-2Primary CHW Pump2nd Floor (Plant Room)MCP-PLANTEquipment Supplierunverified
PCHW-3Primary CHW Pump2nd Floor (Plant Room)MCP-PLANTEquipment Supplierunverified
PCHW-SPrimary CHW Pump (Standby)2nd Floor (Plant Room)MCP-PLANTEquipment Supplierunverified
PCOW-1Condenser Water Pump2nd Floor (Plant Room)MCP-PLANTEquipment Supplierunverified
PCOW-2Condenser Water Pump2nd Floor (Plant Room)MCP-PLANTEquipment Supplierunverified
PCOW-3Condenser Water Pump2nd Floor (Plant Room)MCP-PLANTEquipment Supplierunverified
PM-GENMultifunction Power Meter (Main)2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
PM-MAINMultifunction Power Meter (Main)2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
PM-MCC-BOILERMultifunction Power Meter (Feeder)2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
PM-MCC-CHILLERMultifunction Power Meter (Feeder)2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
PM-MCC-CTMultifunction Power Meter (Feeder)2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
PM-MCC-FIRE-PUMPMultifunction Power Meter (Feeder)2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
PM-MCC-MDP-1Multifunction Power Meter (Feeder)2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
PM-MCC-MDP-2Multifunction Power Meter (Feeder)2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
PM-MCC-MDP-3Multifunction Power Meter (Feeder)2nd Floor (Plant Room)MCP-PLANTBMS Contractorunverified
RP-HZ.1Recirculating PumpRoofdeckFCP-RDEquipment Supplierunverified
RP-HZ.2Recirculating PumpRoofdeckFCP-RDEquipment Supplierunverified
RP-HZ.3Recirculating PumpRoofdeckFCP-RDEquipment Supplierunverified
RP-LZ.1Recirculating PumpLower GroundFCP-BSMTEquipment Supplierunverified
RP-LZ.2Recirculating PumpLower GroundFCP-BSMTEquipment Supplierunverified
RP-LZ.3Recirculating PumpLower GroundFCP-BSMTEquipment Supplierunverified
TEF-1.1Exhaust Fan (Toilet)Ground FloorFCP-GFEquipment Supplierunverified
TEF-1.2Exhaust Fan (Toilet)Ground FloorFCP-GFEquipment Supplierunverified
TEF-1.3Exhaust Fan (Toilet)Ground FloorFCP-GFEquipment Supplierunverified
TEF-1.4Exhaust Fan (Toilet)Ground FloorFCP-GFEquipment Supplierunverified
TEF-2.1Exhaust Fan (Toilet)2nd FloorFCP-2FEquipment Supplierunverified
TEF-2.3Exhaust Fan (Toilet)2nd FloorFCP-2FEquipment Supplierunverified
TEF-2B.3Exhaust Fan (Toilet)2nd FloorFCP-2FEquipment Supplierunverified
TEF-3A.1Exhaust Fan (Toilet)3rd Floor (Amenity)FCP-3FEquipment Supplierunverified
TEF-3A.2Exhaust Fan (Toilet)3rd Floor (Amenity)FCP-3FEquipment Supplierunverified
TEF-3B.1Exhaust Fan (Toilet)3rd Floor (Amenity)FCP-3FEquipment Supplierunverified
TEF-3C.1Exhaust Fan (Toilet)3rd Floor (Amenity)FCP-3FEquipment Supplierunverified
TEF-3C.2Exhaust Fan (Toilet)3rd Floor (Amenity)FCP-3FEquipment Supplierunverified
TEF-3D.1Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.10Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.11Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.12Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.13Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.14Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.15Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.16Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.17Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.18Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.19Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.2Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.20Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.3Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.4Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.5Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.6Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.7Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.8Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified
TEF-3D.9Exhaust Fan (Toilet)3rd Floor (Guestroom)FCP-3FEquipment Supplierunverified

Verification schema

How to record verification / corrections in A2-equipment-takeoff.yaml
Find the affected row in the YAML by ID (Detail sheet column A) and add a verification: block:
- id: AHU-01
verification: # ADDED by team
status: needs_correction # unverified | verified | needs_correction | uncertain
corrected_location: 3rd Floor Mech Room # team's measured / confirmed value
verified_by: J. Cruz
verified_date: 2026-05-10
drawing_ref: "EE-09 grid B-2"
notes: ""
After saving, re-run: python3 _playbook/tools/generate-deliverables.py <project>
Corrections propagate to B4 manhours, BOQ, and final deliverables automatically.
Recommended verification methods (priority order):
1. Site walkthrough with measurement (most accurate; for cable lengths, after structural completion).
2. Properly-scaled architectural drawings.
3. Mechanical contractor's tray layout combined with BMS panel locations.
4. A-001 default with ±20% contingency in BOQ — last resort.