00 Summary

DUPA SUMMARY — All BOQ Line Items
Project: SMC MRT-7 FDAS+ACS Integration | Bidder: CMR Philippines Inc. | Date: 2026-05-08
DPWH bracket (5-50M tier): OCM 11% | Profit 8% | VAT 12% (private-bid VAT-inclusive)
ItemDescriptionUnitQtyDirect (PHP)OCM (11%)Profit (8%)D+OCM+PVAT (12%)Total (PHP)% of TotalSheet
0.1Occupational Safety and Health Program (180 CD multi-site)L.S.1262,605.0428,886.5521,008.40312,500.0037,500.00350,000.001.31%01 0.1
0.2Traffic Management (12 stations + depot rotation)L.S.1300,120.0533,013.2124,009.60357,142.8642,857.14400,000.001.50%02 0.2
0.3Mobilization and Demobilization (12 stations + depot)L.S.1375,150.0641,266.5130,012.00446,428.5753,571.43500,000.001.88%03 0.3
0.4Project Manager (REE, full-time)month6675,270.1174,279.7154,021.61803,571.4396,428.57900,000.003.38%04 0.4
0.5Engineer-in-charge (REE, full-time)month6585,234.0964,375.7546,818.73696,428.5783,571.43780,000.002.93%05 0.5
0.6PEE supervisory engagement (R.A. 9292)hour80210,084.0323,109.2416,806.72250,000.0030,000.00280,000.001.05%06 0.6
0.7Site Supervisors × 2 (full-time, 6 months each)month12675,270.1174,279.7154,021.61803,571.4396,428.57900,000.003.38%07 0.7
0.8Interface Manager + Engineer (part-time blended)L.S.1337,635.0537,139.8627,010.80401,785.7148,214.29450,000.001.69%08 0.8
0.9CAR + 3rd-party + workmen's-comp insurance (180 CD)L.S.1262,605.0428,886.5521,008.40312,500.0037,500.00350,000.001.31%09 0.9
0.10Surety bonds (Adv Pay + Performance 20% + Warranty 10%)L.S.1375,150.0641,266.5130,012.00446,428.5753,571.43500,000.001.88%10 0.10
0.11All government permits (LGU + MMDA + DOLE + working)L.S.1150,060.0216,506.6012,004.80178,571.4321,428.57200,000.000.75%11 0.11
0.12BOC duties for imported items + VAT pass-throughL.S.1600,240.1066,026.4148,019.21714,285.7185,714.29800,000.003.00%12 0.12
0.13Daily/Weekly Reports + Primavera P6 monthly + As-built drawingsL.S.1187,575.0320,633.2515,006.00223,214.2926,785.71250,000.000.94%13 0.13
0.14Site office + temporary power + comms + vehicles + tools (180 CD)L.S.1450,180.0749,519.8136,014.41535,714.2964,285.71600,000.002.25%14 0.14
0.15Garbage collection + disposal (per TOR §8.21)L.S.137,515.014,126.653,001.2044,642.865,357.1450,000.000.19%15 0.15
P1-01FDAS Workstation Computer System @ OCCLot11,508,103.24165,891.36120,648.261,794,642.86215,357.142,010,000.007.54%16 P1-01
P1-02ACS Workstation Computer System @ OCCLot11,500,600.24165,066.03120,048.021,785,714.29214,285.712,000,000.007.50%17 P1-02
P1-03NIC / media converters / gateways for 12 stations × FDAS+ACS = 24 gatewaysps11,200,480.19132,052.8296,038.421,428,571.43171,428.571,600,000.006.00%18 P1-03
P1-04Control & Communication Cable @ OCC (workstation ↔ CER)ps1262,605.0428,886.5521,008.40312,500.0037,500.00350,000.001.31%19 P1-04
P1-05Power Supply Cables + Conduit + Boxes @ OCCps1187,575.0320,633.2515,006.00223,214.2926,785.71250,000.000.94%20 P1-05
P1-06Workstation Furniture @ OCC (4-PC table + ergonomic chairs)ps160,024.016,602.644,801.9271,428.578,571.4380,000.000.30%21 P1-06
P1-07Testing and Commissioning — Phase 1 (~250 hr T&C)Lot1525,210.0857,773.1142,016.81625,000.0075,000.00700,000.002.63%22 P1-07
P2-08Inter-bldg Cable (1500m FOC OS2 24-core armored + 200m FOC 12-core + 200m STP Cat6A + splices + terminations + 24 surge + pulling)Lot1675,270.1174,279.7154,021.61803,571.4396,428.57900,000.003.38%23 P2-08
P2-08bConduit + Cable Tray + Containment (1100m EMT 25mm + 200m GRC + 30 pull boxes + 50m cable tray + fittings)Lot1562,725.0961,899.7645,018.01669,642.8680,357.14750,000.002.81%24 P2-08b
P2-09NIC / media converter / gateways Phase 2 depot (5 FDAS + 5 ACS)ps1510,204.0856,122.4540,816.33607,142.8672,857.14680,000.002.55%25 P2-09
P2-10Power Supply Cables + Conduit + Boxes @ FCCRLot1150,060.0216,506.6012,004.80178,571.4321,428.57200,000.000.75%26 P2-10
P2-11Workstation Furniture @ FCCR (4-PC table + chairs)ps160,024.016,602.644,801.9271,428.578,571.4380,000.000.30%27 P2-11
P2-12Testing and Commissioning — Phase 2 (~349 hr)Lot1712,785.1178,406.3657,022.81848,214.29101,785.71950,000.003.56%28 P2-12
ADD-01FDAS Field Devices @ Genset BuildingLot1150,060.0216,506.6012,004.80178,571.4321,428.57200,000.000.75%29 ADD-01
ADD-02FDAS Field Devices @ Guard Houses GH-1, GH-2A, GH-2DLot1135,054.0214,855.9410,804.32160,714.2919,285.71180,000.000.68%30 ADD-02
ADD-03FCCR Head-End Mirror (FDAS + ACS WS at FCCR mirroring P1-01 + P1-02)Lot13,151,260.50346,638.66252,100.843,750,000.00450,000.004,200,000.0015.75%31 ADD-03
ADD-04FAT travel — Notifier facility, Northford CT, USA (3-person × 7 days)L.S.1945,378.15103,991.6075,630.251,125,000.00135,000.001,260,000.004.73%32 ADD-04
ADD-05FAT travel — Suprema facility, Seongnam, South Korea (3-person × 7 days)L.S.1461,434.5750,757.8036,914.77549,107.1465,892.86615,000.002.31%33 ADD-05
ADD-062-year recommended spare-parts kit (FDAS + ACS)Lot1487,695.0853,646.4639,015.61580,357.1469,642.86650,000.002.44%34 ADD-06
ADD-07O&M Manual + Training material + Training delivery + CertificatesLot1375,150.0641,266.5130,012.00446,428.5753,571.43500,000.001.88%35 ADD-07
ADD-083-year software support + upgrades (OnyxWorks + BioStar 2)L.S.1900,360.1499,039.6272,028.811,071,428.57128,571.431,200,000.004.50%36 ADD-08
GRAND TOTAL20,006,752.702,200,742.801,600,540.2223,808,035.712,856,964.2926,665,000.00100.00%

01 0.1

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.1Unit: L.S.Qty: 1
Description: Occupational Safety and Health Program (180 CD multi-site)
Notes: Multi-site: 13 work sites (12 stations + depot)
Customer Code: B.7(2)
A. MATERIALS / EQUIPMENTSubtotal:65,651.26
#DescriptionUnitQtyUnit CostAmount
1PPE for ~15 personnel (hardhats, vests, gloves, safety shoes)lot126,260.5026,260.50
2Safety signage at 13 siteslot119,695.3819,695.38
3First-aid + emergency kits + reporting toolslot119,695.3819,695.38
B. LABORSubtotal:157,563.03
#Designation / ActivityUnitQtyRateAmount
1Safety Officer 6 mo @ PHP 30,000/mo (full-time)ls1133,928.57133,928.57
2OSH training + monthly drill laborls123,634.4523,634.45
C. EQUIPMENT USESubtotal:39,390.76
#DescriptionUnitQtyRateAmount
1Vehicle for safety officer multi-site rotationls139,390.7639,390.76
D. SUB-TOTAL DIRECT COST (A+B+C)262,605.04
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct28,886.55
F. PROFIT — 8% of Direct21,008.40
G. SUB-TOTAL (D + E + F)312,500.00
H. VAT — 12% of (D+E+F), embedded per A-40137,500.00
I. TOTAL per L.S. (VAT-inclusive)350,000.00

02 0.2

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.2Unit: L.S.Qty: 1
Description: Traffic Management (12 stations + depot rotation)
Notes: DPWH B.8(2) typical L.S. for multi-site projects
Customer Code: B.8(2)
A. MATERIALS / EQUIPMENTSubtotal:75,030.01
#DescriptionUnitQtyUnit CostAmount
1Barricades + cones + traffic signslot145,018.0145,018.01
2Reflectorized warning signs (multi-site)lot130,012.0030,012.00
B. LABORSubtotal:180,072.03
#Designation / ActivityUnitQtyRateAmount
1Flagman labor (rotational, 4 mo)ls1180,072.03180,072.03
C. EQUIPMENT USESubtotal:45,018.01
#DescriptionUnitQtyRateAmount
1Traffic-management vehicle + flashing-light setupls145,018.0145,018.01
D. SUB-TOTAL DIRECT COST (A+B+C)300,120.05
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct33,013.21
F. PROFIT — 8% of Direct24,009.60
G. SUB-TOTAL (D + E + F)357,142.86
H. VAT — 12% of (D+E+F), embedded per A-40142,857.14
I. TOTAL per L.S. (VAT-inclusive)400,000.00

03 0.3

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.3Unit: L.S.Qty: 1
Description: Mobilization and Demobilization (12 stations + depot)
Notes: DPWH B.9 typical 1-2% of contract
Customer Code: B.9
A. MATERIALS / EQUIPMENTSubtotal:93,787.52
#DescriptionUnitQtyUnit CostAmount
1Initial stockpile materials + container office setuplot146,893.7646,893.76
2Site-establishment fittings + signagelot146,893.7646,893.76
B. LABORSubtotal:225,090.04
#Designation / ActivityUnitQtyRateAmount
1Mobilization labor (multi-site setup)ls1123,799.52123,799.52
2Demobilization labor (site clearing)ls1101,290.52101,290.52
C. EQUIPMENT USESubtotal:56,272.51
#DescriptionUnitQtyRateAmount
1Truck + lift hire for mobilization phasels133,763.5133,763.51
2Demobilization truck-hirels122,509.0022,509.00
D. SUB-TOTAL DIRECT COST (A+B+C)375,150.06
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct41,266.51
F. PROFIT — 8% of Direct30,012.00
G. SUB-TOTAL (D + E + F)446,428.57
H. VAT — 12% of (D+E+F), embedded per A-40153,571.43
I. TOTAL per L.S. (VAT-inclusive)500,000.00

04 0.4

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.4Unit: monthQty: 6
Description: Project Manager (REE, full-time)
Notes: Mid-senior REE PM rate, transit-grade infra project
A. MATERIALS / EQUIPMENTSubtotal:33,763.51
#DescriptionUnitQtyUnit CostAmount
1Office supplies + admin overhead allocationlot133,763.5133,763.51
B. LABORSubtotal:607,743.10
#Designation / ActivityUnitQtyRateAmount
1Project Manager — REE — fully loaded (salary + benefits + overhead)ls1607,743.10607,743.10
C. EQUIPMENT USESubtotal:33,763.51
#DescriptionUnitQtyRateAmount
1Mobile office equipment + comms allocationls133,763.5133,763.51
D. SUB-TOTAL DIRECT COST (A+B+C)675,270.11
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct74,279.71
F. PROFIT — 8% of Direct54,021.61
G. SUB-TOTAL (D + E + F)803,571.43
H. VAT — 12% of (D+E+F), embedded per A-40196,428.57
I. TOTAL per month (VAT-inclusive)900,000.00

05 0.5

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.5Unit: monthQty: 6
Description: Engineer-in-charge (REE, full-time)
Notes: Mid-level REE EIC rate
A. MATERIALS / EQUIPMENTSubtotal:29,261.70
#DescriptionUnitQtyUnit CostAmount
1Office supplies + admin overhead allocationlot129,261.7029,261.70
B. LABORSubtotal:526,710.68
#Designation / ActivityUnitQtyRateAmount
1Engineer-in-charge — REE — fully loadedls1526,710.68526,710.68
C. EQUIPMENT USESubtotal:29,261.70
#DescriptionUnitQtyRateAmount
1Mobile office equipment + comms allocationls129,261.7029,261.70
D. SUB-TOTAL DIRECT COST (A+B+C)585,234.09
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct64,375.75
F. PROFIT — 8% of Direct46,818.73
G. SUB-TOTAL (D + E + F)696,428.57
H. VAT — 12% of (D+E+F), embedded per A-40183,571.43
I. TOTAL per month (VAT-inclusive)780,000.00

06 0.6

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.6Unit: hourQty: 80
Description: PEE supervisory engagement (R.A. 9292)
Notes: PEE professional rate per R.A. 9292 typical engagement
A. MATERIALS / EQUIPMENTSubtotal:10,504.20
#DescriptionUnitQtyUnit CostAmount
1Document signoff seals + adminlot110,504.2010,504.20
B. LABORSubtotal:189,075.63
#Designation / ActivityUnitQtyRateAmount
1PEE supervisor (R.A. 9292) — engagement billingls1189,075.63189,075.63
C. EQUIPMENT USESubtotal:10,504.20
#DescriptionUnitQtyRateAmount
1Site visit transport allocationls110,504.2010,504.20
D. SUB-TOTAL DIRECT COST (A+B+C)210,084.03
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct23,109.24
F. PROFIT — 8% of Direct16,806.72
G. SUB-TOTAL (D + E + F)250,000.00
H. VAT — 12% of (D+E+F), embedded per A-40130,000.00
I. TOTAL per hour (VAT-inclusive)280,000.00

07 0.7

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.7Unit: monthQty: 12
Description: Site Supervisors × 2 (full-time, 6 months each)
Notes: Foreman/supervisor full-time rate
A. MATERIALS / EQUIPMENTSubtotal:33,763.51
#DescriptionUnitQtyUnit CostAmount
1Field admin + tracking toolslot133,763.5133,763.51
B. LABORSubtotal:607,743.10
#Designation / ActivityUnitQtyRateAmount
1Site Supervisor / Foreman — fully loadedls1607,743.10607,743.10
C. EQUIPMENT USESubtotal:33,763.51
#DescriptionUnitQtyRateAmount
1Mobile comms + small site toolsls133,763.5133,763.51
D. SUB-TOTAL DIRECT COST (A+B+C)675,270.11
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct74,279.71
F. PROFIT — 8% of Direct54,021.61
G. SUB-TOTAL (D + E + F)803,571.43
H. VAT — 12% of (D+E+F), embedded per A-40196,428.57
I. TOTAL per month (VAT-inclusive)900,000.00

08 0.8

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.8Unit: L.S.Qty: 1
Description: Interface Manager + Engineer (part-time blended)
Notes: Per TOR §8.5; multi-party coordination across ~17 contractors
A. MATERIALS / EQUIPMENTSubtotal:16,881.75
#DescriptionUnitQtyUnit CostAmount
1ICD authoring + coordination materialslot116,881.7516,881.75
B. LABORSubtotal:303,871.55
#Designation / ActivityUnitQtyRateAmount
1Interface Manager 4 mo @ ~50% × PHP 80Kls1167,129.35167,129.35
2Interface Engineer 5 mo @ ~50% × PHP 70Kls1136,742.20136,742.20
C. EQUIPMENT USESubtotal:16,881.75
#DescriptionUnitQtyRateAmount
1Coordination meeting facilities + conferencingls116,881.7516,881.75
D. SUB-TOTAL DIRECT COST (A+B+C)337,635.05
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct37,139.86
F. PROFIT — 8% of Direct27,010.80
G. SUB-TOTAL (D + E + F)401,785.71
H. VAT — 12% of (D+E+F), embedded per A-40148,214.29
I. TOTAL per L.S. (VAT-inclusive)450,000.00

09 0.9

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.9Unit: L.S.Qty: 1
Description: CAR + 3rd-party + workmen's-comp insurance (180 CD)
Notes: Typical PH insurance premium ~1.0-1.5% of insured value
A. MATERIALS / EQUIPMENTSubtotal:249,474.79
#DescriptionUnitQtyUnit CostAmount
1CAR insurance premium (~1% of project value)lot1137,211.13137,211.13
2Third-party liability premiumlot149,894.9649,894.96
3Workmen's compensation premium per PH labor lawlot162,368.7062,368.70
B. LABORSubtotal:13,130.25
#Designation / ActivityUnitQtyRateAmount
1Insurance broker / coordinator laborls113,130.2513,130.25
C. EQUIPMENT USESubtotal:0.00
(no equipment use for this line)
D. SUB-TOTAL DIRECT COST (A+B+C)262,605.04
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct28,886.55
F. PROFIT — 8% of Direct21,008.40
G. SUB-TOTAL (D + E + F)312,500.00
H. VAT — 12% of (D+E+F), embedded per A-40137,500.00
I. TOTAL per L.S. (VAT-inclusive)350,000.00

10 0.10

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.10Unit: L.S.Qty: 1
Description: Surety bonds (Adv Pay + Performance 20% + Warranty 10%)
Notes: Per TOR §11.6.1 + §3.2; SMC-acceptable surety panel
A. MATERIALS / EQUIPMENTSubtotal:356,392.56
#DescriptionUnitQtyUnit CostAmount
1Advance Payment Bond premiumlot153,458.8853,458.88
2Performance Bond (20% × Contract) premiumlot1178,196.28178,196.28
3Warranty Bond (10% × Contract, 2-yr) premiumlot1124,737.39124,737.39
B. LABORSubtotal:18,757.50
#Designation / ActivityUnitQtyRateAmount
1Surety coordinator laborls118,757.5018,757.50
C. EQUIPMENT USESubtotal:0.00
(no equipment use for this line)
D. SUB-TOTAL DIRECT COST (A+B+C)375,150.06
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct41,266.51
F. PROFIT — 8% of Direct30,012.00
G. SUB-TOTAL (D + E + F)446,428.57
H. VAT — 12% of (D+E+F), embedded per A-40153,571.43
I. TOTAL per L.S. (VAT-inclusive)500,000.00

11 0.11

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.11Unit: L.S.Qty: 1
Description: All government permits (LGU + MMDA + DOLE + working)
Notes: Multi-site permit cost across 13 work locations
A. MATERIALS / EQUIPMENTSubtotal:142,557.02
#DescriptionUnitQtyUnit CostAmount
1LGU electrical permits (multi-site)lot157,022.8157,022.81
2MMDA + DOLE permitslot142,767.1142,767.11
3Working permits + barangay clearanceslot142,767.1142,767.11
B. LABORSubtotal:7,503.00
#Designation / ActivityUnitQtyRateAmount
1Permits-runner laborls17,503.007,503.00
C. EQUIPMENT USESubtotal:0.00
(no equipment use for this line)
D. SUB-TOTAL DIRECT COST (A+B+C)150,060.02
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct16,506.60
F. PROFIT — 8% of Direct12,004.80
G. SUB-TOTAL (D + E + F)178,571.43
H. VAT — 12% of (D+E+F), embedded per A-40121,428.57
I. TOTAL per L.S. (VAT-inclusive)200,000.00

12 0.12

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.12Unit: L.S.Qty: 1
Description: BOC duties for imported items + VAT pass-through
Notes: Typical 5-7% landed-cost adder on imports
A. MATERIALS / EQUIPMENTSubtotal:570,228.09
#DescriptionUnitQtyUnit CostAmount
1BOC duties on imported items (Notifier, Suprema, Hirschmann, etc.)lot1484,693.88484,693.88
2Brokerage + customs clearance feeslot185,534.2185,534.21
B. LABORSubtotal:30,012.00
#Designation / ActivityUnitQtyRateAmount
1Customs broker + admin laborls130,012.0030,012.00
C. EQUIPMENT USESubtotal:0.00
(no equipment use for this line)
D. SUB-TOTAL DIRECT COST (A+B+C)600,240.10
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct66,026.41
F. PROFIT — 8% of Direct48,019.21
G. SUB-TOTAL (D + E + F)714,285.71
H. VAT — 12% of (D+E+F), embedded per A-40185,714.29
I. TOTAL per L.S. (VAT-inclusive)800,000.00

13 0.13

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.13Unit: L.S.Qty: 1
Description: Daily/Weekly Reports + Primavera P6 monthly + As-built drawings
Notes: Per TOR §4.11 + §4.16 + §8.13
A. MATERIALS / EQUIPMENTSubtotal:46,893.76
#DescriptionUnitQtyUnit CostAmount
1Reporting templates + plotting paper + bindinglot114,068.1314,068.13
2Drawing software licenses (CAD, P6)lot132,825.6332,825.63
B. LABORSubtotal:112,545.02
#Designation / ActivityUnitQtyRateAmount
1Reporting writer (part-time 6 mo)ls133,763.5133,763.51
2P6 scheduler (part-time 3 mo)ls133,763.5133,763.51
3As-built CAD drafter (~30 days)ls145,018.0145,018.01
C. EQUIPMENT USESubtotal:28,136.25
#DescriptionUnitQtyRateAmount
1Plotter + printing equipmentls128,136.2528,136.25
D. SUB-TOTAL DIRECT COST (A+B+C)187,575.03
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct20,633.25
F. PROFIT — 8% of Direct15,006.00
G. SUB-TOTAL (D + E + F)223,214.29
H. VAT — 12% of (D+E+F), embedded per A-40126,785.71
I. TOTAL per L.S. (VAT-inclusive)250,000.00

14 0.14

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.14Unit: L.S.Qty: 1
Description: Site office + temporary power + comms + vehicles + tools (180 CD)
Notes: Multi-site logistics support
A. MATERIALS / EQUIPMENTSubtotal:112,545.02
#DescriptionUnitQtyUnit CostAmount
1Container office rental + setuplot133,763.5133,763.51
2Tools + small equipment kitlot133,763.5133,763.51
3Office supplies + comms internet 6 molot145,018.0145,018.01
B. LABORSubtotal:270,108.04
#Designation / ActivityUnitQtyRateAmount
1Site logistics laborls1270,108.04270,108.04
C. EQUIPMENT USESubtotal:67,527.01
#DescriptionUnitQtyRateAmount
1Service vehicle ×2 (180 CD lease)ls154,021.6154,021.61
2Generator backup + temporary powerls113,505.4013,505.40
D. SUB-TOTAL DIRECT COST (A+B+C)450,180.07
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct49,519.81
F. PROFIT — 8% of Direct36,014.41
G. SUB-TOTAL (D + E + F)535,714.29
H. VAT — 12% of (D+E+F), embedded per A-40164,285.71
I. TOTAL per L.S. (VAT-inclusive)600,000.00

15 0.15

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: 0.15Unit: L.S.Qty: 1
Description: Garbage collection + disposal (per TOR §8.21)
Notes: Bonded waste-disposal contractor
A. MATERIALS / EQUIPMENTSubtotal:9,378.75
#DescriptionUnitQtyUnit CostAmount
1Bins + bags + sorting toolslot19,378.759,378.75
B. LABORSubtotal:22,509.00
#Designation / ActivityUnitQtyRateAmount
1Collection labor (rotational)ls122,509.0022,509.00
C. EQUIPMENT USESubtotal:5,627.25
#DescriptionUnitQtyRateAmount
1Disposal truck-hire (periodic)ls15,627.255,627.25
D. SUB-TOTAL DIRECT COST (A+B+C)37,515.01
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct4,126.65
F. PROFIT — 8% of Direct3,001.20
G. SUB-TOTAL (D + E + F)44,642.86
H. VAT — 12% of (D+E+F), embedded per A-4015,357.14
I. TOTAL per L.S. (VAT-inclusive)50,000.00

16 P1-01

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P1-01Unit: LotQty: 1
Description: FDAS Workstation Computer System @ OCC
Notes: Per ANNEX_C1 §1123.2.8; brand-locked Notifier per ANNEX_D1
Customer Code: 1123.2.8
A. MATERIALS / EQUIPMENTSubtotal:1,281,887.76
#DescriptionUnitQtyUnit CostAmount
1Notifier OnyxWorks SW (server + 1 client seat, perpetual)lot1538,392.86538,392.86
2Server (Dell PowerEdge R750, Xeon Silver, 64 GB ECC, RAID-1, Win Svr 2019 LTS, 4U)lot1410,204.08410,204.08
3Workstation PC (Intel i7 12th-gen, 32 GB DDR4, 1 TB NVMe SSD, 32" LED FHD)lot164,094.3964,094.39
4L2 Industrial Switch (Hirschmann MACH104-20TX-FR, 24G+4SFP, UL 508)lot1166,645.41166,645.41
5APC Smart-UPS On-Line 2 kVA (230V 60Hz pure sine, 15-30 min)lot164,094.3964,094.39
6HP LaserJet Color (≥30 ppm, 1200 dpi)lot125,637.7625,637.76
742U server rack + cable mgmt + labeling (APC NetShelter SX)lot112,818.8812,818.88
B. LABORSubtotal:180,972.39
#Designation / ActivityUnitQtyRateAmount
1Engineer-in-charge — 6 hr × PHP 750/hrls118,097.2418,097.24
2Programmer (OnyxWorks server install + GUI build) — 8 hr × PHP 1,000/hrls154,291.7254,291.72
3Wireman (rack assembly + power + data cable) — 8 hr × PHP 350/hrls172,388.9672,388.96
4Site Supervisor — 4 hr × PHP 470/hrls136,194.4836,194.48
C. EQUIPMENT USESubtotal:45,243.10
#DescriptionUnitQtyRateAmount
1Tools + cable certifier rental (1 day)ls122,621.5522,621.55
2Lift / staging for rack installls122,621.5522,621.55
D. SUB-TOTAL DIRECT COST (A+B+C)1,508,103.24
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct165,891.36
F. PROFIT — 8% of Direct120,648.26
G. SUB-TOTAL (D + E + F)1,794,642.86
H. VAT — 12% of (D+E+F), embedded per A-401215,357.14
I. TOTAL per Lot (VAT-inclusive)2,010,000.00

17 P1-02

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P1-02Unit: LotQty: 1
Description: ACS Workstation Computer System @ OCC
Notes: Per ANNEX_C1 §1124.2.6; brand-locked Suprema per ANNEX_D2
Customer Code: 1124.2.6
A. MATERIALS / EQUIPMENTSubtotal:1,275,510.20
#DescriptionUnitQtyUnit CostAmount
1Suprema BioStar 2 Enterprise SW (perpetual, multi-site, TLS 1.2)lot1408,163.27408,163.27
2ACS Server (Dell PowerEdge, Xeon, 64 GB ECC, Win Svr 2019)lot1408,163.27408,163.27
3L2 Switch w/ SFP (Hirschmann/Moxa, UL 508)lot1165,816.33165,816.33
4Microsoft SQL Server 2019 LTS Standardlot1165,816.33165,816.33
5Zebra ZC card printer (color, MIFARE encoding)lot176,530.6176,530.61
6Suprema BioMini Plus 2 + DE-620 encoderlot138,265.3138,265.31
742U server rack + cable mgmtlot112,755.1012,755.10
B. LABORSubtotal:180,072.03
#Designation / ActivityUnitQtyRateAmount
1Engineer-in-charge — 6 hr × PHP 750ls118,007.2018,007.20
2Programmer (BioStar 2 server install + SQL setup + cert provisioning) — 8 hr × PHP 1,000ls163,025.2163,025.21
3Wireman — 6 hr × PHP 350ls163,025.2163,025.21
4Site Supervisor — 4 hr × PHP 470ls136,014.4136,014.41
C. EQUIPMENT USESubtotal:45,018.01
#DescriptionUnitQtyRateAmount
1Tools + test instruments (1 day)ls122,509.0022,509.00
2Lift for rack installls122,509.0022,509.00
D. SUB-TOTAL DIRECT COST (A+B+C)1,500,600.24
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct165,066.03
F. PROFIT — 8% of Direct120,048.02
G. SUB-TOTAL (D + E + F)1,785,714.29
H. VAT — 12% of (D+E+F), embedded per A-401214,285.71
I. TOTAL per Lot (VAT-inclusive)2,000,000.00

18 P1-03

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P1-03Unit: psQty: 1
Description: NIC / media converters / gateways for 12 stations × FDAS+ACS = 24 gateways
Notes: 12 stations × 2 disciplines = 24 gateways
A. MATERIALS / EQUIPMENTSubtotal:1,020,408.16
#DescriptionUnitQtyUnit CostAmount
1Notifier NCM-W FDAS gateway × 12 @ ~PHP 60Klot1459,183.67459,183.67
2ACS Industrial Ethernet media converter × 12 @ ~PHP 30K (Moxa NPort)lot1234,693.88234,693.88
3DIN-rail Surge Protector (Type 2) × 24lot181,632.6581,632.65
4Wall Enclosure IP54 × 24lot1122,448.98122,448.98
5Cabling + connectors + labelinglot1122,448.98122,448.98
B. LABORSubtotal:144,057.62
#Designation / ActivityUnitQtyRateAmount
1Programmer (per-station IP config + commissioning) — 24 sessions × 1 hr × PHP 1,000ls157,623.0557,623.05
2Wireman (gateway mounting + power + termination) — 12 sessions × 4 hr × PHP 350ls172,028.8172,028.81
3Site Supervisor (multi-station rotation)ls114,405.7614,405.76
C. EQUIPMENT USESubtotal:36,014.41
#DescriptionUnitQtyRateAmount
1Service vehicle (multi-station rotation)ls121,608.6421,608.64
2Test instruments (laptop + analyzer)ls114,405.7614,405.76
D. SUB-TOTAL DIRECT COST (A+B+C)1,200,480.19
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct132,052.82
F. PROFIT — 8% of Direct96,038.42
G. SUB-TOTAL (D + E + F)1,428,571.43
H. VAT — 12% of (D+E+F), embedded per A-401171,428.57
I. TOTAL per ps (VAT-inclusive)1,600,000.00

19 P1-04

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P1-04Unit: psQty: 1
Description: Control & Communication Cable @ OCC (workstation ↔ CER)
Notes: OCC head-end internal cabling
A. MATERIALS / EQUIPMENTSubtotal:131,302.52
#DescriptionUnitQtyUnit CostAmount
1FOC patch cables OS2 single-mode (assorted)lot139,390.7639,390.76
2STP Cat6A patch + bulklot139,390.7639,390.76
3Connectors + LC terminationslot126,260.5026,260.50
4Cable management ties + labelslot126,260.5026,260.50
B. LABORSubtotal:105,042.02
#Designation / ActivityUnitQtyRateAmount
1Wireman (cable pulling + termination) — 4 days × PHP 350/hr × 8 hr × 2ls1105,042.02105,042.02
C. EQUIPMENT USESubtotal:26,260.50
#DescriptionUnitQtyRateAmount
1Fusion splicer rental (1 day)ls115,756.3015,756.30
2OTDR + light source + power meter rentalls110,504.2010,504.20
D. SUB-TOTAL DIRECT COST (A+B+C)262,605.04
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct28,886.55
F. PROFIT — 8% of Direct21,008.40
G. SUB-TOTAL (D + E + F)312,500.00
H. VAT — 12% of (D+E+F), embedded per A-40137,500.00
I. TOTAL per ps (VAT-inclusive)350,000.00

20 P1-05

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P1-05Unit: psQty: 1
Description: Power Supply Cables + Conduit + Boxes @ OCC
Notes: OCC power distribution from existing panel
A. MATERIALS / EQUIPMENTSubtotal:93,787.52
#DescriptionUnitQtyUnit CostAmount
1THW 2.5/4 mm² power cablelot137,515.0137,515.01
2EMT 25mm conduit + couplings + saddleslot128,136.2528,136.25
3Outlet/device boxes + cover plateslot128,136.2528,136.25
B. LABORSubtotal:75,030.01
#Designation / ActivityUnitQtyRateAmount
1Wireman (conduit install + cable pulling + termination) — 3 daysls175,030.0175,030.01
C. EQUIPMENT USESubtotal:18,757.50
#DescriptionUnitQtyRateAmount
1Conduit bender + threading kit + drillls118,757.5018,757.50
D. SUB-TOTAL DIRECT COST (A+B+C)187,575.03
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct20,633.25
F. PROFIT — 8% of Direct15,006.00
G. SUB-TOTAL (D + E + F)223,214.29
H. VAT — 12% of (D+E+F), embedded per A-40126,785.71
I. TOTAL per ps (VAT-inclusive)250,000.00

21 P1-06

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P1-06Unit: psQty: 1
Description: Workstation Furniture @ OCC (4-PC table + ergonomic chairs)
Notes: Per TOR §4.5
A. MATERIALS / EQUIPMENTSubtotal:48,019.21
#DescriptionUnitQtyUnit CostAmount
1Workstation table (4-PC capacity per TOR §4.5)lot119,207.6819,207.68
2Ergonomic operator chairs × 4lot119,207.6819,207.68
3Monitor arm + cable mgmt tray + accessorieslot19,603.849,603.84
B. LABORSubtotal:9,003.60
#Designation / ActivityUnitQtyRateAmount
1Furniture delivery + assemblyls19,003.609,003.60
C. EQUIPMENT USESubtotal:3,001.20
#DescriptionUnitQtyRateAmount
1Hand tools + assembly kitls13,001.203,001.20
D. SUB-TOTAL DIRECT COST (A+B+C)60,024.01
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct6,602.64
F. PROFIT — 8% of Direct4,801.92
G. SUB-TOTAL (D + E + F)71,428.57
H. VAT — 12% of (D+E+F), embedded per A-4018,571.43
I. TOTAL per ps (VAT-inclusive)80,000.00

22 P1-07

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P1-07Unit: LotQty: 1
Description: Testing and Commissioning — Phase 1 (~250 hr T&C)
Notes: Per TOR §4.21; B3 commissioning-points list
A. MATERIALS / EQUIPMENTSubtotal:52,521.01
#DescriptionUnitQtyUnit CostAmount
1Test consumables + smoke aerosol + heat-test pole + report bindinglot152,521.0152,521.01
B. LABORSubtotal:420,168.07
#Designation / ActivityUnitQtyRateAmount
1T&C Engineer 250 hr × PHP 1,500/hr (Standalone + Integration + Performance)ls1357,142.86357,142.86
2EIC supervisory presence at signoff milestonesls163,025.2163,025.21
C. EQUIPMENT USESubtotal:52,521.01
#DescriptionUnitQtyRateAmount
1OTDR + power meter + cable certifier + multimeter + insulation tester rentalls136,764.7136,764.71
2Network analyzer / Wireshark laptop + sound level meterls115,756.3015,756.30
D. SUB-TOTAL DIRECT COST (A+B+C)525,210.08
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct57,773.11
F. PROFIT — 8% of Direct42,016.81
G. SUB-TOTAL (D + E + F)625,000.00
H. VAT — 12% of (D+E+F), embedded per A-40175,000.00
I. TOTAL per Lot (VAT-inclusive)700,000.00

23 P2-08

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P2-08Unit: LotQty: 1
Description: Inter-bldg Cable (1500m FOC OS2 24-core armored + 200m FOC 12-core + 200m STP Cat6A + splices + terminations + 24 surge + pulling)
Notes: Inter-building backbone via Civil-built underground ductbank
A. MATERIALS / EQUIPMENTSubtotal:337,635.05
#DescriptionUnitQtyUnit CostAmount
1FOC OS2 24-core armored OSP × 1500 m @ PHP 250/m (Belden/Corning)lot1185,699.28185,699.28
2FOC OS2 12-core × 200 m @ PHP 180/mlot116,881.7516,881.75
3STP Cat6A outdoor-rated × 200 m @ PHP 180/mlot116,881.7516,881.75
4DIN-rail surge protector × 24 @ PHP 5,000lot160,774.3160,774.31
5Connectors + LC terminations (36) + cable markerslot157,397.9657,397.96
B. LABORSubtotal:270,108.04
#Designation / ActivityUnitQtyRateAmount
1Fusion splice technician — 27 splices × PHP 1,500ls143,217.2943,217.29
2LC termination — 36 terminations × PHP 1,200ls145,918.3745,918.37
3Pulling crew — 4 wireman × 5 days × PHP 350/hr × 8 hrls1180,972.39180,972.39
C. EQUIPMENT USESubtotal:67,527.01
#DescriptionUnitQtyRateAmount
1Fusion splicer rental (5 days)ls127,010.8027,010.80
2OTDR + power meter + light source rental (3 days)ls120,258.1020,258.10
3Cable-pulling lubricant + winch + drumls120,258.1020,258.10
D. SUB-TOTAL DIRECT COST (A+B+C)675,270.11
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct74,279.71
F. PROFIT — 8% of Direct54,021.61
G. SUB-TOTAL (D + E + F)803,571.43
H. VAT — 12% of (D+E+F), embedded per A-40196,428.57
I. TOTAL per Lot (VAT-inclusive)900,000.00

24 P2-08b

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P2-08bUnit: LotQty: 1
Description: Conduit + Cable Tray + Containment (1100m EMT 25mm + 200m GRC + 30 pull boxes + 50m cable tray + fittings)
Notes: Above-ground containment only; underground ductbank by Civil per TOR §9.1
A. MATERIALS / EQUIPMENTSubtotal:281,362.55
#DescriptionUnitQtyUnit CostAmount
1EMT 25 mm × 1100 m @ PHP 180/m (Phelps Dodge/PH)lot198,476.8998,476.89
2GRC galvanized rigid × 200 m @ PHP 350/mlot136,577.1336,577.13
3Pull/junction boxes × 30 @ PHP 2,500lot136,577.1336,577.13
4Cable tray ladder-type × 50 m @ PHP 1,800lot145,018.0145,018.01
5Cable tray fittings + hangers + supportslot130,949.8830,949.88
6Couplings + saddles + connectors + outlet boxes + markerslot133,763.5133,763.51
B. LABORSubtotal:225,090.04
#Designation / ActivityUnitQtyRateAmount
1Wireman (conduit + tray installation) — 6-person × 7 days × PHP 350/hr × 8 hrls1225,090.04225,090.04
C. EQUIPMENT USESubtotal:56,272.51
#DescriptionUnitQtyRateAmount
1Conduit bender + threading + drill (multi-day)ls122,509.0022,509.00
2Lift + scaffolding for cable-tray installls133,763.5133,763.51
D. SUB-TOTAL DIRECT COST (A+B+C)562,725.09
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct61,899.76
F. PROFIT — 8% of Direct45,018.01
G. SUB-TOTAL (D + E + F)669,642.86
H. VAT — 12% of (D+E+F), embedded per A-40180,357.14
I. TOTAL per Lot (VAT-inclusive)750,000.00

25 P2-09

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P2-09Unit: psQty: 1
Description: NIC / media converter / gateways Phase 2 depot (5 FDAS + 5 ACS)
Notes: Phase 2 depot integration: Genset, Aux, Pump 1+2, Train Wash, STP
A. MATERIALS / EQUIPMENTSubtotal:433,673.47
#DescriptionUnitQtyUnit CostAmount
1Notifier NCM-W FDAS gateway × 5lot1195,153.06195,153.06
2ACS media converter × 5 (Moxa)lot199,744.9099,744.90
3Surge protector × 10 + enclosure × 10lot186,734.6986,734.69
4Cabling + connectors + labelinglot152,040.8252,040.82
B. LABORSubtotal:61,224.49
#Designation / ActivityUnitQtyRateAmount
1Programmer (per-bldg config + commissioning) — 10 sessions × 1 hr × PHP 1,000ls118,367.3518,367.35
2Wireman (gateway mounting + termination) — 5 sessions × 4 hr × PHP 350ls133,673.4733,673.47
3Site Supervisorls19,183.679,183.67
C. EQUIPMENT USESubtotal:15,306.12
#DescriptionUnitQtyRateAmount
1Service vehicle (multi-bldg rotation)ls19,183.679,183.67
2Test instrumentsls16,122.456,122.45
D. SUB-TOTAL DIRECT COST (A+B+C)510,204.08
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct56,122.45
F. PROFIT — 8% of Direct40,816.33
G. SUB-TOTAL (D + E + F)607,142.86
H. VAT — 12% of (D+E+F), embedded per A-40172,857.14
I. TOTAL per ps (VAT-inclusive)680,000.00

26 P2-10

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P2-10Unit: LotQty: 1
Description: Power Supply Cables + Conduit + Boxes @ FCCR
Notes: FCCR head-end power, smaller scope than OCC
A. MATERIALS / EQUIPMENTSubtotal:75,030.01
#DescriptionUnitQtyUnit CostAmount
1THW 2.5/4 mm²lot130,012.0030,012.00
2EMT 25mm + couplings + saddleslot122,509.0022,509.00
3Outlet/device boxes + cover plateslot122,509.0022,509.00
B. LABORSubtotal:60,024.01
#Designation / ActivityUnitQtyRateAmount
1Wireman (FCCR power install) — 3 daysls160,024.0160,024.01
C. EQUIPMENT USESubtotal:15,006.00
#DescriptionUnitQtyRateAmount
1Conduit bender + drillls115,006.0015,006.00
D. SUB-TOTAL DIRECT COST (A+B+C)150,060.02
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct16,506.60
F. PROFIT — 8% of Direct12,004.80
G. SUB-TOTAL (D + E + F)178,571.43
H. VAT — 12% of (D+E+F), embedded per A-40121,428.57
I. TOTAL per Lot (VAT-inclusive)200,000.00

27 P2-11

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P2-11Unit: psQty: 1
Description: Workstation Furniture @ FCCR (4-PC table + chairs)
Notes: Mirror of P1-06 for FCCR
A. MATERIALS / EQUIPMENTSubtotal:48,019.21
#DescriptionUnitQtyUnit CostAmount
1Workstation table 4-PC capacitylot119,207.6819,207.68
2Ergonomic chairs × 4lot119,207.6819,207.68
3Monitor arm + cable traylot19,603.849,603.84
B. LABORSubtotal:9,003.60
#Designation / ActivityUnitQtyRateAmount
1Furniture delivery + assemblyls19,003.609,003.60
C. EQUIPMENT USESubtotal:3,001.20
#DescriptionUnitQtyRateAmount
1Hand toolsls13,001.203,001.20
D. SUB-TOTAL DIRECT COST (A+B+C)60,024.01
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct6,602.64
F. PROFIT — 8% of Direct4,801.92
G. SUB-TOTAL (D + E + F)71,428.57
H. VAT — 12% of (D+E+F), embedded per A-4018,571.43
I. TOTAL per ps (VAT-inclusive)80,000.00

28 P2-12

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: P2-12Unit: LotQty: 1
Description: Testing and Commissioning — Phase 2 (~349 hr)
Notes: Per TOR §4.21; more complex inter-bldg integration
A. MATERIALS / EQUIPMENTSubtotal:71,278.51
#DescriptionUnitQtyUnit CostAmount
1Test consumables + report bindinglot171,278.5171,278.51
B. LABORSubtotal:570,228.09
#Designation / ActivityUnitQtyRateAmount
1T&C Engineer 349 hr × PHP 1,500/hr (Standalone + Integration + Performance + inter-bldg)ls1484,693.88484,693.88
2EIC supervisory presencels185,534.2185,534.21
C. EQUIPMENT USESubtotal:71,278.51
#DescriptionUnitQtyRateAmount
1OTDR + cable certifier + multimeter rentalls149,894.9649,894.96
2Network analyzer + sound level meterls121,383.5521,383.55
D. SUB-TOTAL DIRECT COST (A+B+C)712,785.11
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct78,406.36
F. PROFIT — 8% of Direct57,022.81
G. SUB-TOTAL (D + E + F)848,214.29
H. VAT — 12% of (D+E+F), embedded per A-401101,785.71
I. TOTAL per Lot (VAT-inclusive)950,000.00

29 ADD-01

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: ADD-01Unit: LotQty: 1
Description: FDAS Field Devices @ Genset Building
Notes: Per ANNEX_C1 §1123.2.5; Resp. Matrix Phase 2 Genset row
A. MATERIALS / EQUIPMENTSubtotal:90,036.01
#DescriptionUnitQtyUnit CostAmount
1Notifier FSP-951 photoelectric smoke × 4 @ ~PHP 6,000lot118,907.5618,907.56
2Notifier FST-951 heat × 2 @ ~PHP 5,000lot18,103.248,103.24
3Notifier NBG-12LX manual pull × 2 @ ~PHP 4,500lot17,202.887,202.88
4Horn-strobe (P2W/SpectrAlert) × 2 @ ~PHP 8,000lot112,605.0412,605.04
5FMM-1 monitoring module × 2 @ ~PHP 12,000lot118,907.5618,907.56
6Back-boxes + conduit + 2C 1.5mm² FRLS shielded cablelot124,309.7224,309.72
B. LABORSubtotal:52,521.01
#Designation / ActivityUnitQtyRateAmount
1Wireman (device install + addressing + walk-test) — 2-3 days × 2-personls152,521.0152,521.01
C. EQUIPMENT USESubtotal:7,503.00
#DescriptionUnitQtyRateAmount
1Lift / scaffolding for ceiling-mountls14,501.804,501.80
2Walk-test smoke aerosol + heat polels13,001.203,001.20
D. SUB-TOTAL DIRECT COST (A+B+C)150,060.02
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct16,506.60
F. PROFIT — 8% of Direct12,004.80
G. SUB-TOTAL (D + E + F)178,571.43
H. VAT — 12% of (D+E+F), embedded per A-40121,428.57
I. TOTAL per Lot (VAT-inclusive)200,000.00

30 ADD-02

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: ADD-02Unit: LotQty: 1
Description: FDAS Field Devices @ Guard Houses GH-1, GH-2A, GH-2D
Notes: Per Resp. Matrix Phase 2 Guard Houses
A. MATERIALS / EQUIPMENTSubtotal:81,032.41
#DescriptionUnitQtyUnit CostAmount
1Notifier FSP-951 × 6lot124,309.7224,309.72
2Notifier NBG-12LX × 3lot18,913.578,913.57
3Horn-strobe × 3lot116,206.4816,206.48
4Back-boxes + conduit + FRLS cable (3 GHs)lot131,602.6431,602.64
B. LABORSubtotal:47,268.91
#Designation / ActivityUnitQtyRateAmount
1Wireman (3-GH install + addressing + walk-test)ls147,268.9147,268.91
C. EQUIPMENT USESubtotal:6,752.70
#DescriptionUnitQtyRateAmount
1Hand tools + ladderls14,051.624,051.62
2Walk-test instrumentsls12,701.082,701.08
D. SUB-TOTAL DIRECT COST (A+B+C)135,054.02
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct14,855.94
F. PROFIT — 8% of Direct10,804.32
G. SUB-TOTAL (D + E + F)160,714.29
H. VAT — 12% of (D+E+F), embedded per A-40119,285.71
I. TOTAL per Lot (VAT-inclusive)180,000.00

31 ADD-03

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: ADD-03Unit: LotQty: 1
Description: FCCR Head-End Mirror (FDAS + ACS WS at FCCR mirroring P1-01 + P1-02)
Notes: Bidder-Added Phase 2 redundancy at FCCR
A. MATERIALS / EQUIPMENTSubtotal:2,678,571.43
#DescriptionUnitQtyUnit CostAmount
1FDAS Mirror @ FCCR (Server + WS + UPS + L2 + Printer + Rack — mirror of P1-01)lot11,232,142.861,232,142.86
2ACS Mirror @ FCCR (Server + WS + UPS + L2 + Badge Printer + Rack — mirror of P1-02)lot11,205,357.141,205,357.14
3Additional client seats: OnyxWorks + BioStar 2lot1160,714.29160,714.29
4Furniture set @ FCCR (table + chairs)lot153,571.4353,571.43
5Cabling + accessorieslot126,785.7126,785.71
B. LABORSubtotal:378,151.26
#Designation / ActivityUnitQtyRateAmount
1Programmer (FDAS mirror sync + replication + ACS mirror sync) — 2 days × PHP 1,000/hr × 8 hrls1151,260.50151,260.50
2Wireman (rack assembly × 2 + cabling) — 2 days × 2-person × PHP 350/hr × 8 hrls1151,260.50151,260.50
3EIC supervisory + Site Supervisorls175,630.2575,630.25
C. EQUIPMENT USESubtotal:94,537.82
#DescriptionUnitQtyRateAmount
1Lift + tools (2 days)ls194,537.8294,537.82
D. SUB-TOTAL DIRECT COST (A+B+C)3,151,260.50
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct346,638.66
F. PROFIT — 8% of Direct252,100.84
G. SUB-TOTAL (D + E + F)3,750,000.00
H. VAT — 12% of (D+E+F), embedded per A-401450,000.00
I. TOTAL per Lot (VAT-inclusive)4,200,000.00

32 ADD-04

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: ADD-04Unit: L.S.Qty: 1
Description: FAT travel — Notifier facility, Northford CT, USA (3-person × 7 days)
Notes: Per TOR §3.8 + §8.11; D-016 separate line item
A. MATERIALS / EQUIPMENTSubtotal:661,764.71
#DescriptionUnitQtyUnit CostAmount
1Business RT airfare MNL ↔ Hartford × 3 @ PHP 250Klot1522,794.12522,794.12
2Hotel (Northford, 7 nights × 3 @ PHP 12K/night)lot1178,676.47178,676.47
3Travel insurance + visa + ground transportlot139,705.8839,705.88
B. LABORSubtotal:236,344.54
#Designation / ActivityUnitQtyRateAmount
1Per diem (USD 100/day × 7 × 3 = USD 2,100) + witness feesls1200,892.86200,892.86
2Pre-trip prep + reporting laborls135,451.6835,451.68
C. EQUIPMENT USESubtotal:47,268.91
#DescriptionUnitQtyRateAmount
1Documentation + recording equipment for FATls147,268.9147,268.91
D. SUB-TOTAL DIRECT COST (A+B+C)945,378.15
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct103,991.60
F. PROFIT — 8% of Direct75,630.25
G. SUB-TOTAL (D + E + F)1,125,000.00
H. VAT — 12% of (D+E+F), embedded per A-401135,000.00
I. TOTAL per L.S. (VAT-inclusive)1,260,000.00

33 ADD-05

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: ADD-05Unit: L.S.Qty: 1
Description: FAT travel — Suprema facility, Seongnam, South Korea (3-person × 7 days)
Notes: Per TOR §3.8 + §8.11
A. MATERIALS / EQUIPMENTSubtotal:323,004.20
#DescriptionUnitQtyUnit CostAmount
1RT airfare MNL ↔ ICN × 3 @ PHP 80Klot1180,882.35180,882.35
2Hotel (Seongnam, 7 nights × 3 @ PHP 8K)lot1125,971.64125,971.64
3Visa + travel insurance + ground transportlot116,150.2116,150.21
B. LABORSubtotal:115,358.64
#Designation / ActivityUnitQtyRateAmount
1Per diem + witness fees (Korea)ls198,054.8598,054.85
2Pre-trip prep + reportingls117,303.8017,303.80
C. EQUIPMENT USESubtotal:23,071.73
#DescriptionUnitQtyRateAmount
1Documentation equipment for FATls123,071.7323,071.73
D. SUB-TOTAL DIRECT COST (A+B+C)461,434.57
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct50,757.80
F. PROFIT — 8% of Direct36,914.77
G. SUB-TOTAL (D + E + F)549,107.14
H. VAT — 12% of (D+E+F), embedded per A-40165,892.86
I. TOTAL per L.S. (VAT-inclusive)615,000.00

34 ADD-06

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: ADD-06Unit: LotQty: 1
Description: 2-year recommended spare-parts kit (FDAS + ACS)
Notes: Per TOR §4.18-4.19; ~3-5% of equipment value
A. MATERIALS / EQUIPMENTSubtotal:463,310.32
#DescriptionUnitQtyUnit CostAmount
1Notifier device spares (smoke 10%, modules, batteries)lot1185,324.13185,324.13
2Suprema spares (controller spare, BioMini Plus 2 backup, certificates kit)lot1115,827.58115,827.58
3L2 switch spare (Hirschmann)lot1148,259.30148,259.30
4UPS battery spare stringslot113,899.3113,899.31
B. LABORSubtotal:24,384.75
#Designation / ActivityUnitQtyRateAmount
1Inventory log + tagging + storage prepls124,384.7524,384.75
C. EQUIPMENT USESubtotal:0.00
(no equipment use for this line)
D. SUB-TOTAL DIRECT COST (A+B+C)487,695.08
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct53,646.46
F. PROFIT — 8% of Direct39,015.61
G. SUB-TOTAL (D + E + F)580,357.14
H. VAT — 12% of (D+E+F), embedded per A-40169,642.86
I. TOTAL per Lot (VAT-inclusive)650,000.00

35 ADD-07

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: ADD-07Unit: LotQty: 1
Description: O&M Manual + Training material + Training delivery + Certificates
Notes: Per TOR §4.16-4.17, §4.22
A. MATERIALS / EQUIPMENTSubtotal:112,545.02
#DescriptionUnitQtyUnit CostAmount
1Manual binding + signed/sealed copieslot145,018.0145,018.01
2Slide decks + lab guides + quick-reference cardslot133,763.5133,763.51
3Training certificates + venue preplot133,763.5133,763.51
B. LABORSubtotal:243,847.54
#Designation / ActivityUnitQtyRateAmount
1Manual authoring (FDAS + ACS) — ~120 hr × PHP 1,000/hrls1109,731.39109,731.39
2Training delivery — 2 sessions × 2 days × PHP 8,000/day × 2 trainerls173,154.2673,154.26
3Slide/lab guide development — ~80 hr × PHP 1,000/hrls160,961.8860,961.88
C. EQUIPMENT USESubtotal:18,757.50
#DescriptionUnitQtyRateAmount
1Projector + lab kit + handouts printingls118,757.5018,757.50
D. SUB-TOTAL DIRECT COST (A+B+C)375,150.06
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct41,266.51
F. PROFIT — 8% of Direct30,012.00
G. SUB-TOTAL (D + E + F)446,428.57
H. VAT — 12% of (D+E+F), embedded per A-40153,571.43
I. TOTAL per Lot (VAT-inclusive)500,000.00

36 ADD-08

DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No.: ADD-08Unit: L.S.Qty: 1
Description: 3-year software support + upgrades (OnyxWorks + BioStar 2)
Notes: Per TOR §4.23; 30-day notice procedure
A. MATERIALS / EQUIPMENTSubtotal:810,324.13
#DescriptionUnitQtyUnit CostAmount
1OnyxWorks 3-yr support contract (Notifier ASEAN)lot1405,162.06405,162.06
2BioStar 2 3-yr support contract (Suprema)lot1267,406.96267,406.96
3Completion-version upgrade allowancelot1137,755.10137,755.10
B. LABORSubtotal:90,036.01
#Designation / ActivityUnitQtyRateAmount
1Annual upgrade coordination + remote support (allocation)ls190,036.0190,036.01
C. EQUIPMENT USESubtotal:0.00
(no equipment use for this line)
D. SUB-TOTAL DIRECT COST (A+B+C)900,360.14
E. OCM (Overhead, Contingencies, Miscellaneous) — 11% of Direct99,039.62
F. PROFIT — 8% of Direct72,028.81
G. SUB-TOTAL (D + E + F)1,071,428.57
H. VAT — 12% of (D+E+F), embedded per A-401128,571.43
I. TOTAL per L.S. (VAT-inclusive)1,200,000.00