# C1 — Contractor / Owner-Supplied Matrix

**Project:** Kingsford Hotel Bacolod BMS
**Generated from:** A1-io-list.yaml
**Generator:** `_playbook/tools/generate-c1-co-matrix.py`

This matrix shows, per equipment class, which **BMS-side field devices** are supplied by which party. It is the contractual-scope-boundary view derived from the points list `C/O` column.

Suppliers:
- **BMS Contractor** — we (the proposing party) supply
- **ME Contractor** — Mechanical contractor supplies (typically valves, dampers, motorized actuators)
- **EE Contractor** — Electrical contractor supplies (power metering related — varies by project)
- **Equipment Supplier** — Manufacturer / Equipment vendor supplies (auxiliary contacts on motors/pumps, native equipment data via BACnet/Modbus, VFDs)
- **Owner** — Customer / building owner supplies

---

## Overall Summary

| Supplier | Total BMS I/O Points | Share |
|----------|---------------------:|------:|
| Equipment Supplier | 447 | 62.4% |
| BMS Contractor | 215 | 30.0% |
| ME Contractor | 54 | 7.5% |
| **Total** | **716** | **100%** |

---

## Per-Equipment-Class Breakdown

### Exhaust Fan (Toilet)  ·  34 units, 102 I/O points

**Instances:** TEF-1.1, TEF-1.2, TEF-1.3, TEF-1.4, TEF-2.1, TEF-2.3, TEF-2B.3, TEF-3A.1, TEF-3A.2, TEF-3B, TEF-3C.1, TEF-3C.2, TEF-3D.1, TEF-3D.10, TEF-3D.11, TEF-3D.12, TEF-3D.13, TEF-3D.14, TEF-3D.15, TEF-3D.16, TEF-3D.17, TEF-3D.18, TEF-3D.19, TEF-3D.2, TEF-3D.20, TEF-3D.3, TEF-3D.4, TEF-3D.5, TEF-3D.6, TEF-3D.7, TEF-3D.8, TEF-3D.9, TEF-B.1, TEF-B.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 102 | Auxiliary Contact (102×) |

### Exhaust Fan (General)  ·  34 units, 102 I/O points

**Instances:** EF-1 (RD), EF-1.2A, EF-1MR.1, EF-1ST0.1, EF-2.1, EF-2.2, EF-2.3, EF-2.4, EF-2B.1, EF-2B.2, EF-3.1, EF-3.2, EF-3SF.2, EF-8R.1, EF-B.1, EF-B.2, EF-BS.1, EF-BS.2, EF-CHR.1, EF-CHR.2, EF-GLZ.1, EF-GLZ.2, EF-GS.1, EF-GS.2, EF-HP.1, EF-LPG.1, EF-MC.1, EF-MFP.1, EF-MRF.1, EF-PR.1, EF-PR.2, EF-RD.1, EF-RD.2, EF-RR.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 102 | Auxiliary Contact (102×) |

### Chiller (Package Water-Cooled)  ·  3 units, 84 I/O points

**Instances:** CH-1, CH-2, CH-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 57 | BACnet/IP gateway from chiller controller (3×), Evaporator Approach Delta Temperature (3×), Evaporator Approach Delta Pressure (3×), Evaporator Refrigerant Pressure (3×), Evaporator Refrigerant Temperature (3×), and 14 more types |
| BMS Contractor | 21 | Temperature Sensor (immersion/thermowell) (12×), Flow Sensor (insertion or in-line) (9×) |
| ME Contractor | 6 | Electric Valve Actuator (limit switch) (6×) |

### DOAS Unit  ·  3 units, 78 I/O points

**Instances:** DOAS-2W, DOAS-RD.1, DOAS-RD.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 39 | Auxiliary Contact (18×), VFD (12×), Contactor relay (6×), DOAS Controller (BACnet) (3×) |
| BMS Contractor | 27 | Temperature Sensor (duct insertion) (9×), Humidity Sensor (duct insertion) (6×), Temperature Sensor (outdoor/duct) (3×), Flow Sensor (duct insertion) (3×), Humidity Sensor (outdoor/duct) (3×), and 1 more types |
| ME Contractor | 12 | Damper Controller (limit/feedback) (3×), Damper Controller (0-10V or 4-20mA) (3×), Electric Valve Actuator (limit switch) (3×), Electric Valve Actuator (0-10V/4-20mA) (3×) |

### Multifunction Power Meter (Feeder)  ·  10 units, 60 I/O points

**Instances:** MTR-FDR-01, MTR-FDR-02, MTR-FDR-03, MTR-FDR-04, MTR-FDR-05, MTR-FDR-06, MTR-FDR-07, MTR-FDR-08, MTR-FDR-09, MTR-FDR-10

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 60 | Modbus Power Meter (10×), Active Power (kW total) (10×), Cumulative Energy (kWh total) (10×), Reactive Power (kVAR total) (10×), Average Voltage (3-phase RMS) (10×), and 1 more types |

### AHU (Chilled-Water-Served)  ·  3 units, 51 I/O points

**Instances:** CHWP-1.1, CHWP-1.2, CHWP-1.3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 18 | Auxiliary Contact (9×), VFD (6×), VFD with BACnet (3×) |
| ME Contractor | 18 | Damper Controller (limit/feedback switch) (6×), Damper Controller (0-10V or 4-20mA) (6×), Electric Valve Actuator (limit/feedback switch) (3×), Electric Valve Actuator (0-10V or 4-20mA) (3×) |
| BMS Contractor | 15 | Temperature Sensor (duct insertion) (9×), Humidity Sensor (duct insertion) (3×), CO2 Sensor (duct) (3×) |

### Steam Boiler  ·  2 units, 32 I/O points

**Instances:** SB-1, SB-2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 20 | Auxiliary Contact (16×), Level Sensor (4×) |
| BMS Contractor | 12 | Pressure Sensor (2×), Temperature Sensor (immersion/thermowell) (2×), Temperature Sensor (high-temp/duct insertion) (2×), Oxygen Sensor (2×), Electric Valve Actuator (limit switch) (2×), and 1 more types |

### AHU (Modulating CHW-served)  ·  2 units, 32 I/O points

**Instances:** AHU-2M.1, AHU-2M.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 12 | Temperature Sensor (duct insertion) (6×), Humidity Sensor (duct insertion) (2×), CO2 Sensor (duct) (2×), CO Sensor (duct) (2×) |
| Equipment Supplier | 10 | Auxiliary Contact (4×), VFD (4×), AHU Controller (BACnet) (2×) |
| ME Contractor | 10 | Damper Controller (0-10V or 4-20mA fb) (4×), Damper Controller (0-10V or 4-20mA) (4×), Electric Valve Actuator (0-10V/4-20mA) (2×) |

### Precooled Air Handling Unit  ·  2 units, 28 I/O points

**Instances:** PAHU-RD.1, PAHU-RD.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 18 | Auxiliary Contact (6×), VFD (4×), PAHU Controller (BACnet) (2×), Contactor relay (2×), Damper Controller (limit/feedback) (2×), and 1 more types |
| BMS Contractor | 8 | Temperature Sensor (outdoor/duct) (2×), Flow Sensor (duct insertion) (2×), Temperature Sensor (duct insertion) (2×), Differential Pressure Sensor (duct) (2×) |
| ME Contractor | 2 | Electric Valve Actuator (0-10V/4-20mA) (2×) |

### Cooling Tower  ·  3 units, 27 I/O points

**Instances:** CT-1, CT-2, CT-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 12 | Level Sensor / Electrode (6×), Electric Valve Actuator (6×) |
| Equipment Supplier | 9 | Auxiliary Contact (6×), Contactor relay (3×) |
| ME Contractor | 6 | Electric Valve Actuator (3×), pH Sensor / Conductivity Sensor (3×) |

### Heat Pump  ·  6 units, 18 I/O points

**Instances:** HP-HZ-1, HP-HZ-2, HP-HZ-3, HP-LZ-1, HP-LZ-2, HP-LZ-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 18 | Auxiliary Contact (9×), Auxiliary Contact (via equipment-panel gateway) (9×) |

### Recirculating Pump  ·  6 units, 18 I/O points

**Instances:** RP-HZ-1, RP-HZ-2, RP-HZ-3, RP-LZ-1, RP-LZ-2, RP-LZ-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 18 | Auxiliary Contact (9×), Auxiliary Contact (via equipment-panel gateway) (9×) |

### Multifunction Power Meter (Main)  ·  3 units, 18 I/O points

**Instances:** MTR-MAIN-1, MTR-MAIN-2, MTR-MAIN-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 18 | Active Power (kW total) (3×), Cumulative Energy (kWh total) (3×), Reactive Power (kVAR total) (3×), Average Voltage (3-phase RMS) (3×), Average Current (3-phase RMS) (3×), and 2 more types |

### Primary CHW Pump  ·  3 units, 15 I/O points

**Instances:** PCHWP-1, PCHWP-2, PCHWP-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 15 | Auxiliary Contact (9×), VFD (6×) |

### Condenser Water Pump  ·  3 units, 12 I/O points

**Instances:** COMP-1, COMP-2, COMP-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 12 | Auxiliary Contact (9×), Contactor relay (3×) |

### Calorifier (Hot Water Storage Tank)  ·  6 units, 6 I/O points

**Instances:** HWT-HZ-1, HWT-HZ-2, HWT-HZ-3, HWT-LZ-1, HWT-LZ-2, HWT-LZ-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 6 | Temperature Sensor (immersion/thermowell) (6×) |

### Hot Water Header Set  ·  2 units, 6 I/O points

**Instances:** HDR-HW-HZ, HDR-HW-LZ

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 6 | Temperature Sensor (immersion/thermowell) (6×) |

### Ozone Generator (UV-light or Corona)  ·  2 units, 6 I/O points

**Instances:** OZ-2M.1, OZ-2M.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 4 | Auxiliary Contact (4×) |
| BMS Contractor | 2 | VOC Sensor (duct) (2×) |

### Primary CHW Pump (Standby)  ·  1 unit, 5 I/O points

**Instances:** PCHWP-4

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 5 | Auxiliary Contact (3×), VFD (2×) |

### CHW Bypass Header  ·  1 unit, 4 I/O points

**Instances:** HDR-CHW-BP

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 4 | Electric Valve Actuator (2×), Differential Pressure Sensor (1×), Differential Temp Sensor (1×) |

### BTU Meter  ·  1 unit, 4 I/O points

**Instances:** BTU-CHWS-MAIN

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 4 | BTU Meter (Modbus RTU/IP) (1×), Cumulative thermal energy (kBtu) (1×), CHW Mass Flow (1×), CHW Supply-Return Delta Temperature (1×) |

### Cooling Tower (Common)  ·  1 unit, 2 I/O points

**Instances:** CT-COMMON

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (outdoor) (1×), Humidity Sensor (outdoor) (1×) |

### Condenser Water Header  ·  2 units, 2 I/O points

**Instances:** HDR-CWR-RD, HDR-CWS-RD

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (immersion) (2×) |

### CHW Supply Main Header  ·  1 unit, 2 I/O points

**Instances:** HDR-CHWS

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (immersion) (1×), Pressure Sensor (1×) |

### CHW Return Main Header  ·  1 unit, 2 I/O points

**Instances:** HDR-CHWR

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (immersion) (1×), Pressure Sensor (1×) |

---

## Notes for Proposal Inclusions/Exclusions

- BMS scope = BMS Contractor row(s) above. We supply these field devices, plus the BMS panels, controllers, network, head-end, programming, and T&C.
- Items marked **ME Contractor** or **Equipment Supplier** are **NOT in BMS supply scope** — they're supplied under Mechanical or Equipment contracts. BMS scope includes the *terminations* and *signal cables* to these devices, but not the devices themselves.
- This matrix feeds C3 (Inclusions / Exclusions / Clarifications) — the customer-facing summary of scope boundaries.