# B3 — Commissioning Point Inventory
#
metadata:
  project: Kingsford Hotel Bacolod BMS
  generated_from: A1-io-list.yaml + A2-equipment-takeoff.yaml
  generator: _playbook/tools/generate-b1-b3-programming-and-commissioning.py
  rates:
    hrs_per_p2p_point: 0.15
    hrs_per_functional_test: 1.5
    hrs_per_integrated_test: 4.0
summary:
  p2p_points: 523
  functional_tests: 135
  integrated_tests: 8
  total_test_items: 666
tc_hours:
  point_to_point: 78.5
  functional_per_equipment: 202.5
  integrated_sequences: 32.0
  total_tc_hours: 313.0
  person_days_at_8hr: 39.1
p2p_breakdown_by_panel:
  PNL-VENT-L3: 81
  PNL-VENT-BSMT: 48
  PNL-CHWP-GND: 42
  PNL-DOAS-RD: 42
  PNL-CHWP-L2: 40
  PNL-VENT-L2: 39
  PNL-BL-LZ: 32
  PNL-AHU-L2: 32
  PNL-CT-RD: 31
  PNL-CH-PLANT-GND: 27
  PNL-VENT-GF: 27
  PNL-PL-LZ: 24
  PNL-PAHU-RD: 22
  PNL-DOAS-L2: 21
  PNL-VENT-RD: 9
  PNL-PL-HZ: 6
functional_test_inventory:
- equipment: AHU-2M.1
  equipment_class: AHU (Modulating CHW-served)
  location: 2nd Level/Casino MVAC Plant
- equipment: AHU-2M.2
  equipment_class: AHU (Modulating CHW-served)
  location: 2nd Level/Casino MVAC Plant
- equipment: BTU-CHWS-MAIN
  equipment_class: BTU Meter
  location: 2F/CHW Pump Room
- equipment: CH-1
  equipment_class: Chiller (Package Water-Cooled)
  location: GND/Chiller Plant Room
- equipment: CH-2
  equipment_class: Chiller (Package Water-Cooled)
  location: GND/Chiller Plant Room
- equipment: CH-3
  equipment_class: Chiller (Package Water-Cooled)
  location: GND/Chiller Plant Room
- equipment: CHWP-1.1
  equipment_class: AHU (Chilled-Water-Served)
  location: GND/BOH AHU Area
- equipment: CHWP-1.2
  equipment_class: AHU (Chilled-Water-Served)
  location: GND/BOH AHU Area
- equipment: CHWP-1.3
  equipment_class: AHU (Chilled-Water-Served)
  location: GND/BOH AHU Area
- equipment: COMP-1
  equipment_class: Condenser Water Pump
  location: 2F/CHW Pump Room
- equipment: COMP-2
  equipment_class: Condenser Water Pump
  location: 2F/CHW Pump Room
- equipment: COMP-3
  equipment_class: Condenser Water Pump
  location: 2F/CHW Pump Room
- equipment: CT-1
  equipment_class: Cooling Tower
  location: Roofdeck/Cooling Tower Area
- equipment: CT-2
  equipment_class: Cooling Tower
  location: Roofdeck/Cooling Tower Area
- equipment: CT-3
  equipment_class: Cooling Tower
  location: Roofdeck/Cooling Tower Area
- equipment: CT-COMMON
  equipment_class: Cooling Tower (Common)
  location: Roofdeck/Cooling Tower Area
- equipment: DOAS-2W
  equipment_class: DOAS Unit
  location: 2nd Level/Casino MVAC Plant
- equipment: DOAS-RD.1
  equipment_class: DOAS Unit
  location: Roofdeck/Hotel DOAS Plant
- equipment: DOAS-RD.2
  equipment_class: DOAS Unit
  location: Roofdeck/Hotel DOAS Plant
- equipment: EF-1 (RD)
  equipment_class: Exhaust Fan (General)
  location: Roofdeck
- equipment: EF-1.2A
  equipment_class: Exhaust Fan (General)
  location: GF Main Lobby
- equipment: EF-1MR.1
  equipment_class: Exhaust Fan (General)
  location: GF Main Lobby
- equipment: EF-1ST0.1
  equipment_class: Exhaust Fan (General)
  location: GF Main Lobby
- equipment: EF-2.1
  equipment_class: Exhaust Fan (General)
  location: 2nd Floor
- equipment: EF-2.2
  equipment_class: Exhaust Fan (General)
  location: 2nd Floor
- equipment: EF-2.3
  equipment_class: Exhaust Fan (General)
  location: 2nd Floor
- equipment: EF-2.4
  equipment_class: Exhaust Fan (General)
  location: 2nd Floor
- equipment: EF-2B.1
  equipment_class: Exhaust Fan (General)
  location: 2nd Floor
- equipment: EF-2B.2
  equipment_class: Exhaust Fan (General)
  location: 2nd Floor
- equipment: EF-3.1
  equipment_class: Exhaust Fan (General)
  location: 3rd Amenity & Guestroom
- equipment: EF-3.2
  equipment_class: Exhaust Fan (General)
  location: 3rd Amenity & Guestroom
- equipment: EF-3SF.2
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-8R.1
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-B.1
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-B.2
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-BS.1
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-BS.2
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-CHR.1
  equipment_class: Exhaust Fan (General)
  location: 2nd Floor
- equipment: EF-CHR.2
  equipment_class: Exhaust Fan (General)
  location: 2nd Floor
- equipment: EF-GLZ.1
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-GLZ.2
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-GS.1
  equipment_class: Exhaust Fan (General)
  location: 2nd Floor
- equipment: EF-GS.2
  equipment_class: Exhaust Fan (General)
  location: 2nd Floor
- equipment: EF-HP.1
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-LPG.1
  equipment_class: Exhaust Fan (General)
  location: GF Main Lobby
- equipment: EF-MC.1
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-MFP.1
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-MRF.1
  equipment_class: Exhaust Fan (General)
  location: GF Main Lobby
- equipment: EF-PR.1
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-PR.2
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: EF-RD.1
  equipment_class: Exhaust Fan (General)
  location: Roofdeck
- equipment: EF-RD.2
  equipment_class: Exhaust Fan (General)
  location: Roofdeck
- equipment: EF-RR.2
  equipment_class: Exhaust Fan (General)
  location: Basement
- equipment: HDR-CHW-BP
  equipment_class: CHW Bypass Header
  location: 2F/CHW Pump Room
- equipment: HDR-CHWR
  equipment_class: CHW Return Main Header
  location: 2F/CHW Pump Room
- equipment: HDR-CHWS
  equipment_class: CHW Supply Main Header
  location: 2F/CHW Pump Room
- equipment: HDR-CWR-RD
  equipment_class: Condenser Water Header
  location: Roofdeck/Cooling Tower Area
- equipment: HDR-CWS-RD
  equipment_class: Condenser Water Header
  location: Roofdeck/Cooling Tower Area
- equipment: HDR-HW-HZ
  equipment_class: Hot Water Header Set
  location: Roofdeck/HW Plant
- equipment: HDR-HW-LZ
  equipment_class: Hot Water Header Set
  location: Lower Ground/HW Plant
- equipment: HP-HZ-1
  equipment_class: Heat Pump
  location: Roofdeck/HW Plant
- equipment: HP-HZ-2
  equipment_class: Heat Pump
  location: Roofdeck/HW Plant
- equipment: HP-HZ-3
  equipment_class: Heat Pump
  location: Roofdeck/HW Plant
- equipment: HP-LZ-1
  equipment_class: Heat Pump
  location: Lower Ground/HW Plant
- equipment: HP-LZ-2
  equipment_class: Heat Pump
  location: Lower Ground/HW Plant
- equipment: HP-LZ-3
  equipment_class: Heat Pump
  location: Lower Ground/HW Plant
- equipment: HWT-HZ-1
  equipment_class: Calorifier (Hot Water Storage Tank)
  location: Roofdeck/HW Plant
- equipment: HWT-HZ-2
  equipment_class: Calorifier (Hot Water Storage Tank)
  location: Roofdeck/HW Plant
- equipment: HWT-HZ-3
  equipment_class: Calorifier (Hot Water Storage Tank)
  location: Roofdeck/HW Plant
- equipment: HWT-LZ-1
  equipment_class: Calorifier (Hot Water Storage Tank)
  location: Lower Ground/HW Plant
- equipment: HWT-LZ-2
  equipment_class: Calorifier (Hot Water Storage Tank)
  location: Lower Ground/HW Plant
- equipment: HWT-LZ-3
  equipment_class: Calorifier (Hot Water Storage Tank)
  location: Lower Ground/HW Plant
- equipment: MTR-FDR-01
  equipment_class: Multifunction Power Meter (Feeder)
  location: Distribution (per A4)
- equipment: MTR-FDR-02
  equipment_class: Multifunction Power Meter (Feeder)
  location: Distribution (per A4)
- equipment: MTR-FDR-03
  equipment_class: Multifunction Power Meter (Feeder)
  location: Distribution (per A4)
- equipment: MTR-FDR-04
  equipment_class: Multifunction Power Meter (Feeder)
  location: Distribution (per A4)
- equipment: MTR-FDR-05
  equipment_class: Multifunction Power Meter (Feeder)
  location: Distribution (per A4)
- equipment: MTR-FDR-06
  equipment_class: Multifunction Power Meter (Feeder)
  location: Distribution (per A4)
- equipment: MTR-FDR-07
  equipment_class: Multifunction Power Meter (Feeder)
  location: Distribution (per A4)
- equipment: MTR-FDR-08
  equipment_class: Multifunction Power Meter (Feeder)
  location: Distribution (per A4)
- equipment: MTR-FDR-09
  equipment_class: Multifunction Power Meter (Feeder)
  location: Distribution (per A4)
- equipment: MTR-FDR-10
  equipment_class: Multifunction Power Meter (Feeder)
  location: Distribution (per A4)
- equipment: MTR-MAIN-1
  equipment_class: Multifunction Power Meter (Main)
  location: Main Switchgear Room
- equipment: MTR-MAIN-2
  equipment_class: Multifunction Power Meter (Main)
  location: Main Switchgear Room
- equipment: MTR-MAIN-3
  equipment_class: Multifunction Power Meter (Main)
  location: Main Switchgear Room
- equipment: OZ-2M.1
  equipment_class: Ozone Generator (UV-light or Corona)
  location: 2nd Level/Casino MVAC Plant
- equipment: OZ-2M.2
  equipment_class: Ozone Generator (UV-light or Corona)
  location: 2nd Level/Casino MVAC Plant
- equipment: PAHU-RD.1
  equipment_class: Precooled Air Handling Unit
  location: Roofdeck/PAHU Plant
- equipment: PAHU-RD.2
  equipment_class: Precooled Air Handling Unit
  location: Roofdeck/PAHU Plant
- equipment: PCHWP-1
  equipment_class: Primary CHW Pump
  location: 2F/CHW Pump Room
- equipment: PCHWP-2
  equipment_class: Primary CHW Pump
  location: 2F/CHW Pump Room
- equipment: PCHWP-3
  equipment_class: Primary CHW Pump
  location: 2F/CHW Pump Room
- equipment: PCHWP-4
  equipment_class: Primary CHW Pump (Standby)
  location: 2F/CHW Pump Room
- equipment: RP-HZ-1
  equipment_class: Recirculating Pump
  location: Roofdeck/HW Plant
- equipment: RP-HZ-2
  equipment_class: Recirculating Pump
  location: Roofdeck/HW Plant
- equipment: RP-HZ-3
  equipment_class: Recirculating Pump
  location: Roofdeck/HW Plant
- equipment: RP-LZ-1
  equipment_class: Recirculating Pump
  location: Lower Ground/HW Plant
- equipment: RP-LZ-2
  equipment_class: Recirculating Pump
  location: Lower Ground/HW Plant
- equipment: RP-LZ-3
  equipment_class: Recirculating Pump
  location: Lower Ground/HW Plant
- equipment: SB-1
  equipment_class: Steam Boiler
  location: Lower Ground/Boiler Room
- equipment: SB-2
  equipment_class: Steam Boiler
  location: Lower Ground/Boiler Room
- equipment: TEF-1.1
  equipment_class: Exhaust Fan (Toilet)
  location: GF Main Lobby
- equipment: TEF-1.2
  equipment_class: Exhaust Fan (Toilet)
  location: GF Main Lobby
- equipment: TEF-1.3
  equipment_class: Exhaust Fan (Toilet)
  location: GF Main Lobby
- equipment: TEF-1.4
  equipment_class: Exhaust Fan (Toilet)
  location: GF Main Lobby
- equipment: TEF-2.1
  equipment_class: Exhaust Fan (Toilet)
  location: 2nd Floor
- equipment: TEF-2.3
  equipment_class: Exhaust Fan (Toilet)
  location: 2nd Floor
- equipment: TEF-2B.3
  equipment_class: Exhaust Fan (Toilet)
  location: 2nd Floor
- equipment: TEF-3A.1
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3A.2
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3B
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3C.1
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3C.2
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.1
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.10
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.11
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.12
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.13
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.14
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.15
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.16
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.17
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.18
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.19
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.2
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.20
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.3
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.4
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.5
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.6
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.7
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.8
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-3D.9
  equipment_class: Exhaust Fan (Toilet)
  location: 3rd Amenity & Guestroom
- equipment: TEF-B.1
  equipment_class: Exhaust Fan (Toilet)
  location: Basement
- equipment: TEF-B.2
  equipment_class: Exhaust Fan (Toilet)
  location: Basement
integrated_test_inventory:
- Chiller plant sequencing (chiller staging + CHW pump + COW pump + cooling tower fan)
- CHW differential pressure control (PCHWP VFD speed via header dP)
- AHU supply-air temperature control (modulating CHW valve loop)
- DOAS demand-controlled ventilation (CO2-based fresh air modulation)
- Hotwater system sequencing (heat pump + recirculating pump + tank temp)
- Boiler firing rate vs. steam pressure
- Cooling tower fan staging vs. condenser water temperature
- Energy savings algorithm verification (max-demand limiting + load shedding)
notes:
- 'P2P = point-to-point verification: every physical I/O calibrated, range-checked, polarity verified, scaled correctly.'
- 'Functional test: per-equipment sequence verification (e.g., does the AHU CHW valve modulate correctly to maintain supply air temp?).'
- 'Integrated test: cross-system sequence (e.g., chiller staging triggers correctly when load increases).'
- "Owner T&C / SAT: separate from this \u2014 handled in proposal as an item under 5.5 in WBS."