# A7 — Power Provisions Schedule
# ================================
# Project:  Kingsford Hotel Bacolod BMS
# Date:     2026-04-27
# Source:   A4 (panel schedule — power per panel) + A6 (head-end load) + A5 (network)
#
# This schedule lists every BMS-side power requirement for coordination with
# the EE contractor (BMS does NOT supply the breakers/feeders TO our panels;
# we supply the panel's internal power distribution + UPS where applicable).

metadata:
  project: Kingsford Hotel Bacolod BMS
  source: "A4 + A6 + A5; A7 itself is BMS-coordination doc, not an A1 derivative"
  status: draft

# ----- BMS Field Panels (18 panels per A4) -----
# Each panel needs a 240V single-phase 16A circuit from the nearest local
# panelboard (provided by EE contractor under PER per WBS 7.9).
field_panels:
  feed_voltage: 240V single-phase
  feed_breaker_each: 16A
  cable_each: "3C × 2.5 mm² FRLS, 30 m typical (per A3 panel-power-feed)"
  ups_protected: false   # only head-end + CORE switch are UPS-backed in this scope
  panels:
    - { panel: PNL-CH-PLANT-GND,  load_w: 75,  source: "Local lighting/MEP panelboard at chiller plant",        critical: true }
    - { panel: PNL-CHWP-L2,       load_w: 75,  source: "Local panelboard at 2F pump room",                       critical: true }
    - { panel: PNL-CT-RD,         load_w: 50,  source: "Local panelboard at roofdeck cooling tower area",         critical: false }
    - { panel: PNL-CHWP-GND,      load_w: 50,  source: "Local panelboard at GND BOH",                             critical: true }
    - { panel: PNL-PL-LZ,         load_w: 50,  source: "Local panelboard at LZ hot water plant",                  critical: false }
    - { panel: PNL-PL-HZ,         load_w: 50,  source: "Local panelboard at roofdeck HW plant",                   critical: false }
    - { panel: PNL-VENT-GF,       load_w: 50,  source: "Local panelboard at GF main lobby",                       critical: false }
    - { panel: PNL-VENT-L2,       load_w: 50,  source: "Local panelboard at 2F",                                  critical: false }
    - { panel: PNL-VENT-L3,       load_w: 50,  source: "Local panelboard at 3F amenity",                          critical: false }
    - { panel: PNL-VENT-BSMT,     load_w: 50,  source: "Local panelboard at basement",                            critical: false }
    - { panel: PNL-VENT-RD,       load_w: 50,  source: "Local panelboard at roofdeck",                            critical: false }
    - { panel: PNL-BL-LZ,         load_w: 50,  source: "Local panelboard at LZ boiler room",                      critical: true }
    - { panel: PNL-DOAS-L2,       load_w: 50,  source: "Local panelboard at 2F casino MVAC",                      critical: true }
    - { panel: PNL-DOAS-RD,       load_w: 50,  source: "Local panelboard at roofdeck DOAS plant",                 critical: false }
    - { panel: PNL-AHU-L2,        load_w: 75,  source: "Local panelboard at 2F casino MVAC",                      critical: true }
    - { panel: PNL-PAHU-RD,       load_w: 50,  source: "Local panelboard at roofdeck PAHU plant",                 critical: false }
    - { panel: PNL-EE-MAIN,       load_w: 50,  source: "Local panelboard at main switchgear room",                critical: true }
    - { panel: PNL-EE-DIST,       load_w: 50,  source: "Local panelboard at distribution room",                   critical: false }
  total_panel_load_w: 975
  notes:
    - "Each panel needs its own dedicated breaker — do NOT share circuits between BMS panels."
    - "Loads are conservative (per controller + I/O + switching power supply). Refine after equipment selection."

# ----- Head-End -----
head_end:
  location: BMS Server Room (TBD per Q-005, assumed Lower Ground or GF BOH)
  feed_voltage: 240V single-phase
  feed_breaker: 32A (with 25% spare capacity)
  ups_protected: true
  loads:
    - { item: HE-SVR-01 (Primary Server),                              load_w: 600 }
    - { item: HE-SVR-02 (Standby Server),                              load_w: 600 }
    - { item: HE-WS-01 (Operator WS Server Room),                      load_w: 250 }
    - { item: HE-WS-02 (Operator WS Front Desk),                       load_w: 250 }
    - { item: HE-GFX-01 (Graphics PC + 55" Display),                   load_w: 200 }
    - { item: HE-PRINTER-01 (Color Laser),                             load_w: 100 }
    - { item: CORE switch + management,                                load_w: 75 }
    - { item: KVM + console monitor,                                   load_w: 50 }
    - { item: Server-room rack lighting + power strip,                 load_w: 25 }
  total_head_end_load_w: 2150
  ups_size: "3 kVA online double-conversion, 30-min runtime at full load (HE-UPS-01 per A6)"
  ups_input: "240V single-phase 16A from server-room panelboard"
  ups_output_distribution: "PDU/strip in rack — distributes to all head-end equipment"

# ----- Network Edge -----
network_edge:
  total_edge_switch_count: 6
  load_per_edge_switch_w: 30
  total_edge_load_w: 180
  ups_protected: false   # optional in OPT line item; not in base
  notes:
    - "Edge switches powered from local panelboards near their IDF locations"
    - "Optional UPS protection for edge switches available as priced option"

# ----- Summary -----
summary:
  total_bms_load_w: 3305       # 975 panels + 2150 head-end + 180 edge switches
  ups_protected_load_w: 2150   # head-end only (CORE switch included via head-end UPS)
  non_ups_load_w: 1155
  number_of_240v_circuits_required:
    field_panels: 18
    head_end: 1
    edge_switches: 6
    total: 25
  responsibility:
    bms_contractor:  "Supplies internal panel distribution (DIN-rail breakers, terminal blocks, surge protection) + head-end UPS + power strip in server rack"
    ee_contractor:   "Supplies the 25 dedicated 240V circuits FROM building distribution panels TO the BMS panels and head-end. Includes feeder cables and breakers in EE-supplied panelboards."
    coordination:    "BMS submits 'Power Provisions Schedule' (this doc) to EE contractor as part of submittal package; EE contractor confirms feeder availability or requests revisions."

# ----- Open Q's affecting A7 -----
open_questions:
  - id: Q-CHW-FCU
    text: "If guestroom FCUs in scope (Q-019), each FCU controller needs a small 24V power feed — typically from the local floor BMS panel. Adds load to PNL-VENT-L3 etc."
  - id: Q-EE-BMS
    text: "Does customer want the BMS panel power feed in EE scope or BMS scope? Standard split is EE provides the dedicated circuits; BMS provides internal panel distribution. Confirm with Q-009."