# C1 — Contractor / Owner-Supplied Matrix

**Project:** Kingsford Hotel Bacolod — BMS
**Generated from:** A1-io-list.yaml
**Generator:** `_playbook/tools/generate-c1-co-matrix.py`

This matrix shows, per equipment class, which **BMS-side field devices** are supplied by which party. It is the contractual-scope-boundary view derived from the points list `C/O` column.

Suppliers:
- **BMS Contractor** — we (the proposing party) supply
- **ME Contractor** — Mechanical contractor supplies (typically valves, dampers, motorized actuators)
- **EE Contractor** — Electrical contractor supplies (power metering related — varies by project)
- **Equipment Supplier** — Manufacturer / Equipment vendor supplies (auxiliary contacts on motors/pumps, native equipment data via BACnet/Modbus, VFDs)
- **Owner** — Customer / building owner supplies

---

## Overall Summary

| Supplier | Total BMS I/O Points | Share |
|----------|---------------------:|------:|
| Equipment Supplier | 490 | 65.9% |
| BMS Contractor | 183 | 24.6% |
| ME Contractor | 67 | 9.0% |
| EE Contractor | 4 | 0.5% |
| **Total** | **744** | **100%** |

---

## Per-Equipment-Class Breakdown

### AHU (Chilled-Water-Served)  ·  12 units, 180 I/O points

**Instances:** AHU-1.1, AHU-1.2, AHU-1.3, AHU-2M.1, AHU-2M.2, AHU-B.1, AHU-B.2, AHU-B.3, AHU-EL, AHU-FR2, AHU-FR3, AHU-PF

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 84 | Damper Controller (24×), Auxiliary Contact (24×), VFD (24×), VFD BACnet card (12×) |
| BMS Contractor | 60 | Temperature Sensor (48×), CO2 Sensor (12×) |
| ME Contractor | 36 | Damper Controller (24×), Electric Valve Actuator (12×) |

### Precooled Air Handling Unit  ·  8 units, 96 I/O points

**Instances:** PAHU-0.1, PAHU-B.1, PAHU-B.2, PAHU-B.3, PAHU-FR, PAHU-PF, PAHU-r.1, PAHU-r.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 64 | Auxiliary Contact (24×), Damper Controller (16×), VFD (16×), VFD BACnet card (8×) |
| BMS Contractor | 24 | Temperature Sensor (16×), Flow Sensor (8×) |
| ME Contractor | 8 | Electric Valve Actuator (8×) |

### Exhaust Fan (General)  ·  32 units, 96 I/O points

**Instances:** EF-1, EF-2.1, EF-2.2, EF-2.3, EF-2.4, EF-2B.1, EF-2B.2, EF-3.1, EF-3.2, EF-3.3, EF-3.4, EF-3B-G, EF-3C.1-G, EF-B.1, EF-B.2, EF-BR.1, EF-BR.2, EF-BS.1, EF-BS.2, EF-FOST.1, EF-GL.1, EF-GL.2, EF-GS.1, EF-GS.2, EF-MFR.1, EF-MP.1, EF-OHRv2, EF-PR.1, EF-PR.3, EF-RD.1, EF-RO.2, EF-WS.1

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 96 | Auxiliary Contact (96×) |

### Chiller (Package Water-Cooled)  ·  3 units, 84 I/O points

**Instances:** CH-1, CH-2, CH-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 57 | Chiller PLC (51×), Chiller PLC + BACnet gateway (3×), Chiller PLC + BTU meter (3×) |
| BMS Contractor | 21 | Temperature Sensor (12×), Flow Sensor (9×) |
| ME Contractor | 6 | Electric Valve Actuator (6×) |

### DOAS Unit  ·  2 units, 50 I/O points

**Instances:** DOAS-RD.1, DOAS-RD.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 30 | Auxiliary Contact (16×), VFD (8×), Temperature Sensor (2×), Humidity Sensor (2×), VFD BACnet card (2×) |
| BMS Contractor | 12 | Temperature Sensor (6×), Humidity Sensor (4×), Flow Sensor (2×) |
| ME Contractor | 8 | Damper Controller (4×), Electric Valve Actuator (4×) |

### Exhaust Fan (Toilet)  ·  15 units, 45 I/O points

**Instances:** TEF-1.1, TEF-1.2, TEF-1.3, TEF-1.4, TEF-2.1, TEF-2.2, TEF-2B.3, TEF-30.20, TEF-3A.1, TEF-3A.2, TEF-3B, TEF-3C.1, TEF-3C.2, TEF-B.1, TEF-B.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 45 | Auxiliary Contact (45×) |

### Steam Boiler  ·  2 units, 34 I/O points

**Instances:** SB-1, SB-2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 22 | Burner Controller (16×), Level Sensor (4×), Burner Controller gateway (2×) |
| BMS Contractor | 12 | Electric Valve Actuator (4×), Temperature Sensor (4×), Pressure Sensor (2×), Oxygen Sensor (2×) |

### Cooling Tower  ·  3 units, 27 I/O points

**Instances:** CT-1, CT-2, CT-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 12 | Level Sensor / Electrode (6×), Electric Valve Actuator (6×) |
| Equipment Supplier | 9 | Auxiliary Contact (9×) |
| ME Contractor | 6 | Electric Valve Actuator (3×), pH Sensor / Conductivity Sensor (3×) |

### DOAS Unit (Casino — with CO/VOC)  ·  1 unit, 22 I/O points

**Instances:** DOAS-2M

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 14 | Auxiliary Contact (7×), VFD (4×), Temperature Sensor (1×), Humidity Sensor (1×), VFD BACnet card (1×) |
| BMS Contractor | 5 | Temperature Sensor (1×), Flow Sensor (1×), Humidity Sensor (1×), CO2 Sensor (1×), CO Sensor (1×) |
| ME Contractor | 3 | Damper Controller (2×), Electric Valve Actuator (1×) |

### Secondary CHW Pump  ·  3 units, 21 I/O points

**Instances:** SCHWP-1, SCHWP-2, SCHWP-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 21 | Auxiliary Contact (12×), VFD (6×), VFD BACnet card (3×) |

### Primary CHW Pump  ·  2 units, 16 I/O points

**Instances:** PCHWP-1, PCHWP-2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 14 | Auxiliary Contact (8×), VFD (4×), VFD BACnet card (2×) |
| BMS Contractor | 2 | Pressure Sensor (2×) |

### Condenser Water Pump  ·  3 units, 12 I/O points

**Instances:** COWP-1, COWP-2, COWP-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 12 | Auxiliary Contact (12×) |

### Multifunction Power Meter (Feeder)  ·  5 units, 10 I/O points

**Instances:** MPM-AHU-2F, MPM-AHU-GF, MPM-CHILLER, MPM-LIGHT-A, MPM-LIGHT-B

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 10 | Multifunction Power Meter (10×) |

### Air Ionizer (Casino)  ·  2 units, 8 I/O points

**Instances:** AIR-ION-2M.1, AIR-ION-2M.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 6 | Auxiliary Contact / Modbus (4×), Ionizer Controller (2×) |
| BMS Contractor | 2 | VOC Sensor (2×) |

### Hot Water Header Set  ·  2 units, 6 I/O points

**Instances:** HWH-HZ, HWH-LZ

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 6 | Temperature Sensor (6×) |

### Heat Pump  ·  2 units, 6 I/O points

**Instances:** HP-HZ, HP-LZ

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 6 | Auxiliary Contact (6×) |

### Recirculating Pump  ·  2 units, 6 I/O points

**Instances:** RP-HZ, RP-LZ

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 6 | Auxiliary Contact (6×) |

### Primary CHW Pump (Standby)  ·  1 unit, 4 I/O points

**Instances:** PCHWP-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 4 | Auxiliary Contact (4×) |

### Cooling Tower (Common)  ·  1 unit, 4 I/O points

**Instances:** CT-COMMON

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 4 | Temperature Sensor (3×), Humidity Sensor (1×) |

### FACP Gateway  ·  1 unit, 4 I/O points

**Instances:** FACP-GW

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| EE Contractor | 4 | FACP BACnet Gateway (4×) |

### CHW Bypass Header  ·  1 unit, 3 I/O points

**Instances:** CHW-DIFF

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 3 | Diff. Pressure Sensor (2×), Electric Valve Actuator (1×) |

### CHW Supply Main Header  ·  1 unit, 2 I/O points

**Instances:** CHW-SUP-HDR

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Pressure Sensor (1×), Temperature Sensor (1×) |

### CHW Return Main Header  ·  1 unit, 2 I/O points

**Instances:** CHW-RET-HDR

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Pressure Sensor (1×), Temperature Sensor (1×) |

### Condenser Water Header  ·  1 unit, 2 I/O points

**Instances:** CW-HDR

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (2×) |

### Calorifier (Hot Water Storage Tank)  ·  2 units, 2 I/O points

**Instances:** HWT-HZ, HWT-LZ

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (2×) |

### Multifunction Power Meter (Main)  ·  1 unit, 2 I/O points

**Instances:** MPM-MAIN

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Multifunction Power Meter (2×) |

---

## Notes for Proposal Inclusions/Exclusions

- BMS scope = BMS Contractor row(s) above. We supply these field devices, plus the BMS panels, controllers, network, head-end, programming, and T&C.
- Items marked **ME Contractor** or **Equipment Supplier** are **NOT in BMS supply scope** — they're supplied under Mechanical or Equipment contracts. BMS scope includes the *terminations* and *signal cables* to these devices, but not the devices themselves.
- This matrix feeds C3 (Inclusions / Exclusions / Clarifications) — the customer-facing summary of scope boundaries.