# A3 — Cable Schedule
# Generated from A1-io-list.yaml; lengths per A-001
#
metadata:
  project: "Kingsford Hotel Bacolod \u2014 BMS"
  generated_from: A1-io-list.yaml
  generator: _playbook/tools/generate-a3-cable-schedule.py
  assumptions:
  - 'A-001: 30 m average panel-to-device run; 80 m trunk per floor'
  - Cable conductor count = (points + 2 spare), rounded up to standard 4/6/8/12 sizes
  - Cat6 for all BACnet/IP network drops
  - BACnet MS/TP backbone interconnects all BMS panels (refine after Q-008)
  - 240V single-phase power feed to each BMS panel @ 30 m default length
summary:
  total_field_cable_runs: 205
  total_field_cable_length_m: 4293
  total_trunk_cable_length_m: 800
  total_power_feed_length_m: 80
  grand_total_cable_length_m: 5173
  field_cable_by_type_m:
    "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)": 2097
    "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)": 802
    "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)": 796
    "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)": 598
  field_cable_by_panel_m:
    DDC-GF-BOH: 18
    DDC-2M-CASINO: 18
    DDC-2F-BOH: 61
    DDC-2F-CHILLER: 29
    DDC-RD-PLANT: 34
    DDC-3F: 12
    DDC-B1-BOH: 20
    DDC-LG-PLANT: 13
field_cables:
- id: C0001
  from: DDC-GF-BOH
  to: AHU-1.1 (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0533
  - P-0534
  - P-0535
  - P-0538
  - P-0539
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_gf)
- id: C0002
  from: DDC-GF-BOH
  to: AHU-1.1 (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 4
  carries_point_ids:
  - P-0536
  - P-0537
  - P-0541
  - P-0542
  notes: 4 I/O points carried, 4C cable; length 25 m (typical_range:boh_gf)
- id: C0003
  from: DDC-GF-BOH
  to: AHU-1.1 (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0531
  - P-0532
  - P-0540
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_gf)
- id: C0004
  from: DDC-GF-BOH
  to: AHU-1.2 (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0548
  - P-0549
  - P-0550
  - P-0553
  - P-0554
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_gf)
- id: C0005
  from: DDC-GF-BOH
  to: AHU-1.2 (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 4
  carries_point_ids:
  - P-0551
  - P-0552
  - P-0556
  - P-0557
  notes: 4 I/O points carried, 4C cable; length 25 m (typical_range:boh_gf)
- id: C0006
  from: DDC-GF-BOH
  to: AHU-1.2 (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0546
  - P-0547
  - P-0555
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_gf)
- id: C0007
  from: DDC-GF-BOH
  to: AHU-1.3 (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0563
  - P-0564
  - P-0565
  - P-0568
  - P-0569
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_gf)
- id: C0008
  from: DDC-GF-BOH
  to: AHU-1.3 (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 4
  carries_point_ids:
  - P-0566
  - P-0567
  - P-0571
  - P-0572
  notes: 4 I/O points carried, 4C cable; length 25 m (typical_range:boh_gf)
- id: C0009
  from: DDC-GF-BOH
  to: AHU-1.3 (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0561
  - P-0562
  - P-0570
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_gf)
- id: C0010
  from: DDC-2M-CASINO
  to: AHU-2M.1 (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 5
  carries_point_ids:
  - P-0330
  - P-0331
  - P-0332
  - P-0335
  - P-0336
  notes: 5 I/O points carried, 6C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0011
  from: DDC-2M-CASINO
  to: AHU-2M.1 (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 4
  carries_point_ids:
  - P-0333
  - P-0334
  - P-0338
  - P-0339
  notes: 4 I/O points carried, 4C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0012
  from: DDC-2M-CASINO
  to: AHU-2M.1 (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 3
  carries_point_ids:
  - P-0328
  - P-0329
  - P-0337
  notes: 3 I/O points carried, 4C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0013
  from: DDC-2M-CASINO
  to: AHU-2M.2 (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 5
  carries_point_ids:
  - P-0345
  - P-0346
  - P-0347
  - P-0350
  - P-0351
  notes: 5 I/O points carried, 6C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0014
  from: DDC-2M-CASINO
  to: AHU-2M.2 (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 4
  carries_point_ids:
  - P-0348
  - P-0349
  - P-0353
  - P-0354
  notes: 4 I/O points carried, 4C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0015
  from: DDC-2M-CASINO
  to: AHU-2M.2 (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 3
  carries_point_ids:
  - P-0343
  - P-0344
  - P-0352
  notes: 3 I/O points carried, 4C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0016
  from: DDC-2F-BOH
  to: AHU-B.1 (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0368
  - P-0369
  - P-0370
  - P-0373
  - P-0374
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0017
  from: DDC-2F-BOH
  to: AHU-B.1 (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 4
  carries_point_ids:
  - P-0371
  - P-0372
  - P-0376
  - P-0377
  notes: 4 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0018
  from: DDC-2F-BOH
  to: AHU-B.1 (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0366
  - P-0367
  - P-0375
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0019
  from: DDC-2F-BOH
  to: AHU-B.2 (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0383
  - P-0384
  - P-0385
  - P-0388
  - P-0389
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0020
  from: DDC-2F-BOH
  to: AHU-B.2 (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 4
  carries_point_ids:
  - P-0386
  - P-0387
  - P-0391
  - P-0392
  notes: 4 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0021
  from: DDC-2F-BOH
  to: AHU-B.2 (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0381
  - P-0382
  - P-0390
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0022
  from: DDC-2F-BOH
  to: AHU-B.3 (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0398
  - P-0399
  - P-0400
  - P-0403
  - P-0404
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0023
  from: DDC-2F-BOH
  to: AHU-B.3 (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 4
  carries_point_ids:
  - P-0401
  - P-0402
  - P-0406
  - P-0407
  notes: 4 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0024
  from: DDC-2F-BOH
  to: AHU-B.3 (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0396
  - P-0397
  - P-0405
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0025
  from: DDC-2F-BOH
  to: AHU-EL (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Executive Lounge
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0428
  - P-0429
  - P-0430
  - P-0433
  - P-0434
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0026
  from: DDC-2F-BOH
  to: AHU-EL (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Executive Lounge
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 4
  carries_point_ids:
  - P-0431
  - P-0432
  - P-0436
  - P-0437
  notes: 4 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0027
  from: DDC-2F-BOH
  to: AHU-EL (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Executive Lounge
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0426
  - P-0427
  - P-0435
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0028
  from: DDC-2F-BOH
  to: AHU-FR2 (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Function Room 2
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0443
  - P-0444
  - P-0445
  - P-0448
  - P-0449
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0029
  from: DDC-2F-BOH
  to: AHU-FR2 (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Function Room 2
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 4
  carries_point_ids:
  - P-0446
  - P-0447
  - P-0451
  - P-0452
  notes: 4 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0030
  from: DDC-2F-BOH
  to: AHU-FR2 (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Function Room 2
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0441
  - P-0442
  - P-0450
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0031
  from: DDC-2F-BOH
  to: AHU-FR3 (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Function Room 3
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0458
  - P-0459
  - P-0460
  - P-0463
  - P-0464
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0032
  from: DDC-2F-BOH
  to: AHU-FR3 (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Function Room 3
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 4
  carries_point_ids:
  - P-0461
  - P-0462
  - P-0466
  - P-0467
  notes: 4 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0033
  from: DDC-2F-BOH
  to: AHU-FR3 (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Function Room 3
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0456
  - P-0457
  - P-0465
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0034
  from: DDC-2F-BOH
  to: AHU-PF (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Pre-Function
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0413
  - P-0414
  - P-0415
  - P-0418
  - P-0419
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0035
  from: DDC-2F-BOH
  to: AHU-PF (Equipment Supplier)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Pre-Function
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 4
  carries_point_ids:
  - P-0416
  - P-0417
  - P-0421
  - P-0422
  notes: 4 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0036
  from: DDC-2F-BOH
  to: AHU-PF (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Pre-Function
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0411
  - P-0412
  - P-0420
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0037
  from: DDC-2M-CASINO
  to: AIR-ION-2M.1 (BMS Contractor)
  equipment_class: Air Ionizer (Casino)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 1
  carries_point_ids:
  - P-0358
  notes: 1 I/O points carried, 4C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0038
  from: DDC-2M-CASINO
  to: AIR-ION-2M.1 (Equipment Supplier)
  equipment_class: Air Ionizer (Casino)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 2
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 2
  carries_point_ids:
  - P-0359
  - P-0360
  notes: 2 I/O points carried, 4C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0039
  from: DDC-2M-CASINO
  to: AIR-ION-2M.2 (BMS Contractor)
  equipment_class: Air Ionizer (Casino)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 1
  carries_point_ids:
  - P-0362
  notes: 1 I/O points carried, 4C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0040
  from: DDC-2M-CASINO
  to: AIR-ION-2M.2 (Equipment Supplier)
  equipment_class: Air Ionizer (Casino)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 2
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 2
  carries_point_ids:
  - P-0363
  - P-0364
  notes: 2 I/O points carried, 4C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0041
  from: DDC-2F-CHILLER
  to: CH-1 (BMS Contractor)
  equipment_class: Chiller (Package Water-Cooled)
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 7
  conductor_count_required: 9
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 7
  carries_point_ids:
  - P-0001
  - P-0002
  - P-0004
  - P-0005
  - P-0007
  - '...'
  notes: 7 I/O points carried, 12C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0042
  from: DDC-2F-CHILLER
  to: CH-1 (ME Contractor)
  equipment_class: Chiller (Package Water-Cooled)
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    DI: 2
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 2
  carries_point_ids:
  - P-0003
  - P-0006
  notes: 2 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0043
  from: DDC-2F-CHILLER
  to: CH-2 (BMS Contractor)
  equipment_class: Chiller (Package Water-Cooled)
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 7
  conductor_count_required: 9
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 7
  carries_point_ids:
  - P-0029
  - P-0030
  - P-0032
  - P-0033
  - P-0035
  - '...'
  notes: 7 I/O points carried, 12C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0044
  from: DDC-2F-CHILLER
  to: CH-2 (ME Contractor)
  equipment_class: Chiller (Package Water-Cooled)
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    DI: 2
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 2
  carries_point_ids:
  - P-0031
  - P-0034
  notes: 2 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0045
  from: DDC-2F-CHILLER
  to: CH-3 (BMS Contractor)
  equipment_class: Chiller (Package Water-Cooled)
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 7
  conductor_count_required: 9
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 7
  carries_point_ids:
  - P-0057
  - P-0058
  - P-0060
  - P-0061
  - P-0063
  - '...'
  notes: 7 I/O points carried, 12C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0046
  from: DDC-2F-CHILLER
  to: CH-3 (ME Contractor)
  equipment_class: Chiller (Package Water-Cooled)
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    DI: 2
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 2
  carries_point_ids:
  - P-0059
  - P-0062
  notes: 2 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0047
  from: DDC-2F-CHILLER
  to: CHW-DIFF (BMS Contractor)
  equipment_class: CHW Bypass Header
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 2
    DI: 1
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 3
  carries_point_ids:
  - P-0142
  - P-0143
  - P-0144
  notes: 3 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0048
  from: DDC-2F-CHILLER
  to: CHW-RET-HDR (BMS Contractor)
  equipment_class: CHW Return Main Header
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 2
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 2
  carries_point_ids:
  - P-0140
  - P-0141
  notes: 2 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0049
  from: DDC-2F-CHILLER
  to: CHW-SUP-HDR (BMS Contractor)
  equipment_class: CHW Supply Main Header
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 2
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 2
  carries_point_ids:
  - P-0138
  - P-0139
  notes: 2 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0050
  from: DDC-2F-CHILLER
  to: COWP-1 (Equipment Supplier)
  equipment_class: Condenser Water Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 4
  carries_point_ids:
  - P-0126
  - P-0127
  - P-0128
  - P-0129
  notes: 4 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0051
  from: DDC-2F-CHILLER
  to: COWP-2 (Equipment Supplier)
  equipment_class: Condenser Water Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 4
  carries_point_ids:
  - P-0130
  - P-0131
  - P-0132
  - P-0133
  notes: 4 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0052
  from: DDC-2F-CHILLER
  to: COWP-3 (Equipment Supplier)
  equipment_class: Condenser Water Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 4
  carries_point_ids:
  - P-0134
  - P-0135
  - P-0136
  - P-0137
  notes: 4 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0053
  from: DDC-RD-PLANT
  to: CT-1 (BMS Contractor)
  equipment_class: Cooling Tower
  system: AC
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 4
  carries_point_ids:
  - P-0150
  - P-0151
  - P-0154
  - P-0155
  notes: 4 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0054
  from: DDC-RD-PLANT
  to: CT-1 (Equipment Supplier)
  equipment_class: Cooling Tower
  system: AC
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 2
    DO: 1
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0147
  - P-0148
  - P-0149
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0055
  from: DDC-RD-PLANT
  to: CT-1 (ME Contractor)
  equipment_class: Cooling Tower
  system: AC
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    DI: 1
    AI: 1
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 2
  carries_point_ids:
  - P-0152
  - P-0153
  notes: 2 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0056
  from: DDC-RD-PLANT
  to: CT-2 (BMS Contractor)
  equipment_class: Cooling Tower
  system: AC
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 4
  carries_point_ids:
  - P-0159
  - P-0160
  - P-0163
  - P-0164
  notes: 4 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0057
  from: DDC-RD-PLANT
  to: CT-2 (Equipment Supplier)
  equipment_class: Cooling Tower
  system: AC
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 2
    DO: 1
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0156
  - P-0157
  - P-0158
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0058
  from: DDC-RD-PLANT
  to: CT-2 (ME Contractor)
  equipment_class: Cooling Tower
  system: AC
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    DI: 1
    AI: 1
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 2
  carries_point_ids:
  - P-0161
  - P-0162
  notes: 2 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0059
  from: DDC-RD-PLANT
  to: CT-3 (BMS Contractor)
  equipment_class: Cooling Tower
  system: AC
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 4
  carries_point_ids:
  - P-0168
  - P-0169
  - P-0172
  - P-0173
  notes: 4 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0060
  from: DDC-RD-PLANT
  to: CT-3 (Equipment Supplier)
  equipment_class: Cooling Tower
  system: AC
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 2
    DO: 1
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0165
  - P-0166
  - P-0167
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0061
  from: DDC-RD-PLANT
  to: CT-3 (ME Contractor)
  equipment_class: Cooling Tower
  system: AC
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    DI: 1
    AI: 1
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 2
  carries_point_ids:
  - P-0170
  - P-0171
  notes: 2 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0062
  from: DDC-RD-PLANT
  to: CT-COMMON (BMS Contractor)
  equipment_class: Cooling Tower (Common)
  system: AC
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 4
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 4
  carries_point_ids:
  - P-0174
  - P-0175
  - P-0176
  - P-0177
  notes: 4 I/O points carried, 6C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0063
  from: DDC-RD-PLANT
  to: CW-HDR (BMS Contractor)
  equipment_class: Condenser Water Header
  system: AC
  location: Roof Deck CT Area
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 2
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 2
  carries_point_ids:
  - P-0145
  - P-0146
  notes: 2 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0064
  from: DDC-2M-CASINO
  to: DOAS-2M (BMS Contractor)
  equipment_class: "DOAS Unit (Casino \u2014 with CO/VOC)"
  system: VENT
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 5
  conductor_count_required: 6
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 5
  carries_point_ids:
  - P-0306
  - P-0307
  - P-0308
  - P-0321
  - P-0322
  notes: 5 I/O points carried, 6C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0065
  from: DDC-2M-CASINO
  to: DOAS-2M (Equipment Supplier)
  equipment_class: "DOAS Unit (Casino \u2014 with CO/VOC)"
  system: VENT
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 7
    AI: 2
  conductor_count_required: 10
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 9
  carries_point_ids:
  - P-0311
  - P-0312
  - P-0313
  - P-0314
  - P-0315
  - '...'
  notes: 9 I/O points carried, 12C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0066
  from: DDC-2M-CASINO
  to: DOAS-2M (ME Contractor)
  equipment_class: "DOAS Unit (Casino \u2014 with CO/VOC)"
  system: VENT
  location: 2nd Mezzanine (Casino)
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 1
    AO: 2
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 3
  carries_point_ids:
  - P-0309
  - P-0310
  - P-0320
  notes: 3 I/O points carried, 4C cable; length 18 m (typical_range:casino_2m_localized)
- id: C0067
  from: DDC-RD-PLANT
  to: DOAS-RD.1 (BMS Contractor)
  equipment_class: DOAS Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 6
  conductor_count_required: 8
  conductor_count_specified: 8
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 6
  carries_point_ids:
  - P-0232
  - P-0233
  - P-0234
  - P-0248
  - P-0249
  - '...'
  notes: 6 I/O points carried, 8C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0068
  from: DDC-RD-PLANT
  to: DOAS-RD.1 (Equipment Supplier)
  equipment_class: DOAS Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 8
    AI: 2
  conductor_count_required: 11
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 10
  carries_point_ids:
  - P-0237
  - P-0238
  - P-0239
  - P-0240
  - P-0241
  - '...'
  notes: 10 I/O points carried, 12C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0069
  from: DDC-RD-PLANT
  to: DOAS-RD.1 (ME Contractor)
  equipment_class: DOAS Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 2
    AO: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 4
  carries_point_ids:
  - P-0235
  - P-0236
  - P-0246
  - P-0247
  notes: 4 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0070
  from: DDC-RD-PLANT
  to: DOAS-RD.2 (BMS Contractor)
  equipment_class: DOAS Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 6
  conductor_count_required: 8
  conductor_count_specified: 8
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 6
  carries_point_ids:
  - P-0257
  - P-0258
  - P-0259
  - P-0273
  - P-0274
  - '...'
  notes: 6 I/O points carried, 8C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0071
  from: DDC-RD-PLANT
  to: DOAS-RD.2 (Equipment Supplier)
  equipment_class: DOAS Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 8
    AI: 2
  conductor_count_required: 11
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 10
  carries_point_ids:
  - P-0262
  - P-0263
  - P-0264
  - P-0265
  - P-0266
  - '...'
  notes: 10 I/O points carried, 12C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0072
  from: DDC-RD-PLANT
  to: DOAS-RD.2 (ME Contractor)
  equipment_class: DOAS Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AI: 2
    AO: 2
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 4
  carries_point_ids:
  - P-0260
  - P-0261
  - P-0271
  - P-0272
  notes: 4 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0073
  from: DDC-RD-PLANT
  to: EF-1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0726
  - P-0727
  - P-0728
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0074
  from: DDC-2F-BOH
  to: EF-2.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 2nd Floor
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0621
  - P-0622
  - P-0623
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0075
  from: DDC-2F-BOH
  to: EF-2.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 2nd Floor
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0624
  - P-0625
  - P-0626
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0076
  from: DDC-2F-BOH
  to: EF-2.3 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 2nd Floor
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0627
  - P-0628
  - P-0629
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0077
  from: DDC-2F-BOH
  to: EF-2.4 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 2nd Floor
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0630
  - P-0631
  - P-0632
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0078
  from: DDC-2F-BOH
  to: EF-2B.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 2nd Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0609
  - P-0610
  - P-0611
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0079
  from: DDC-2F-BOH
  to: EF-2B.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 2nd Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0612
  - P-0613
  - P-0614
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0080
  from: DDC-3F
  to: EF-3.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 3rd Floor
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0654
  - P-0655
  - P-0656
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0081
  from: DDC-3F
  to: EF-3.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 3rd Floor
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0657
  - P-0658
  - P-0659
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0082
  from: DDC-3F
  to: EF-3.3 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 3rd Floor
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0660
  - P-0661
  - P-0662
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0083
  from: DDC-3F
  to: EF-3.4 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 3rd Floor
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0663
  - P-0664
  - P-0665
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0084
  from: DDC-3F
  to: EF-3B-G (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 3rd Floor BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0666
  - P-0667
  - P-0668
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0085
  from: DDC-3F
  to: EF-3C.1-G (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 3rd Floor
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0669
  - P-0670
  - P-0671
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0086
  from: DDC-B1-BOH
  to: EF-B.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0678
  - P-0679
  - P-0680
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0087
  from: DDC-B1-BOH
  to: EF-B.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0681
  - P-0682
  - P-0683
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0088
  from: DDC-B1-BOH
  to: EF-BR.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Battery Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0699
  - P-0700
  - P-0701
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0089
  from: DDC-B1-BOH
  to: EF-BR.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Battery Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0702
  - P-0703
  - P-0704
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0090
  from: DDC-B1-BOH
  to: EF-BS.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Service
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0684
  - P-0685
  - P-0686
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0091
  from: DDC-B1-BOH
  to: EF-BS.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Service
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0687
  - P-0688
  - P-0689
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0092
  from: DDC-B1-BOH
  to: EF-FOST.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement FOST Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0696
  - P-0697
  - P-0698
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0093
  from: DDC-B1-BOH
  to: EF-GL.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Garbage Lobby
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0690
  - P-0691
  - P-0692
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0094
  from: DDC-B1-BOH
  to: EF-GL.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Garbage Lobby
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0693
  - P-0694
  - P-0695
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0095
  from: DDC-2F-BOH
  to: EF-GS.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 2nd Floor General Service
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0615
  - P-0616
  - P-0617
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0096
  from: DDC-2F-BOH
  to: EF-GS.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 2nd Floor General Service
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0618
  - P-0619
  - P-0620
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0097
  from: DDC-B1-BOH
  to: EF-MFR.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Main Fire Riser
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0717
  - P-0718
  - P-0719
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0098
  from: DDC-B1-BOH
  to: EF-MP.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Mech / Pump
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0708
  - P-0709
  - P-0710
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0099
  from: DDC-2F-BOH
  to: EF-OHRv2 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: 2nd Floor OHR
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0633
  - P-0634
  - P-0635
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0100
  from: DDC-B1-BOH
  to: EF-PR.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Pump Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0711
  - P-0712
  - P-0713
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0101
  from: DDC-B1-BOH
  to: EF-PR.3 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Pump Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0714
  - P-0715
  - P-0716
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0102
  from: DDC-RD-PLANT
  to: EF-RD.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0720
  - P-0721
  - P-0722
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0103
  from: DDC-RD-PLANT
  to: EF-RO.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0723
  - P-0724
  - P-0725
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0104
  from: DDC-B1-BOH
  to: EF-WS.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (General)
  system: VENT
  location: Basement Wash Service
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0705
  - P-0706
  - P-0707
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0105
  from: DDC-RD-PLANT
  to: HP-HZ (Equipment Supplier)
  equipment_class: Heat Pump
  system: HWL
  location: Roof Deck HWL Area
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0223
  - P-0224
  - P-0225
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0106
  from: DDC-LG-PLANT
  to: HP-LZ (Equipment Supplier)
  equipment_class: Heat Pump
  system: HWL
  location: Lower Ground HWL Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0220
  - P-0221
  - P-0222
  notes: 3 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_lg_boiler_hwl)
- id: C0107
  from: DDC-RD-PLANT
  to: HWH-HZ (BMS Contractor)
  equipment_class: Hot Water Header Set
  system: HWL
  location: Roof Deck HWL Area
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0217
  - P-0218
  - P-0219
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0108
  from: DDC-LG-PLANT
  to: HWH-LZ (BMS Contractor)
  equipment_class: Hot Water Header Set
  system: HWL
  location: Lower Ground HWL Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0214
  - P-0215
  - P-0216
  notes: 3 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_lg_boiler_hwl)
- id: C0109
  from: DDC-RD-PLANT
  to: HWT-HZ (BMS Contractor)
  equipment_class: Calorifier (Hot Water Storage Tank)
  system: HWL
  location: Roof Deck HWL Area
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 1
  carries_point_ids:
  - P-0213
  notes: 1 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0110
  from: DDC-LG-PLANT
  to: HWT-LZ (BMS Contractor)
  equipment_class: Calorifier (Hot Water Storage Tank)
  system: HWL
  location: Lower Ground HWL Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0212
  notes: 1 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_lg_boiler_hwl)
- id: C0111
  from: DDC-B1-BOH
  to: PAHU-0.1 (BMS Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Basement
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0578
  - P-0579
  - P-0584
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0112
  from: DDC-B1-BOH
  to: PAHU-0.1 (Equipment Supplier)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Basement
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 3
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 5
  carries_point_ids:
  - P-0576
  - P-0577
  - P-0581
  - P-0582
  - P-0583
  notes: 5 I/O points carried, 6C cable; length 28 m (typical_range:boh_b1)
- id: C0113
  from: DDC-B1-BOH
  to: PAHU-0.1 (ME Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Basement
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AO: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 1
  carries_point_ids:
  - P-0580
  notes: 1 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0114
  from: DDC-2F-BOH
  to: PAHU-B.1 (BMS Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0473
  - P-0474
  - P-0479
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0115
  from: DDC-2F-BOH
  to: PAHU-B.1 (Equipment Supplier)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 3
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0471
  - P-0472
  - P-0476
  - P-0477
  - P-0478
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0116
  from: DDC-2F-BOH
  to: PAHU-B.1 (ME Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AO: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0475
  notes: 1 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0117
  from: DDC-2F-BOH
  to: PAHU-B.2 (BMS Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0485
  - P-0486
  - P-0491
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0118
  from: DDC-2F-BOH
  to: PAHU-B.2 (Equipment Supplier)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 3
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0483
  - P-0484
  - P-0488
  - P-0489
  - P-0490
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0119
  from: DDC-2F-BOH
  to: PAHU-B.2 (ME Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AO: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0487
  notes: 1 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0120
  from: DDC-2F-BOH
  to: PAHU-B.3 (BMS Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0497
  - P-0498
  - P-0503
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0121
  from: DDC-2F-BOH
  to: PAHU-B.3 (Equipment Supplier)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 3
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0495
  - P-0496
  - P-0500
  - P-0501
  - P-0502
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0122
  from: DDC-2F-BOH
  to: PAHU-B.3 (ME Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AO: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0499
  notes: 1 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0123
  from: DDC-2F-BOH
  to: PAHU-FR (BMS Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level Function Rooms
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0521
  - P-0522
  - P-0527
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0124
  from: DDC-2F-BOH
  to: PAHU-FR (Equipment Supplier)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level Function Rooms
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 3
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0519
  - P-0520
  - P-0524
  - P-0525
  - P-0526
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0125
  from: DDC-2F-BOH
  to: PAHU-FR (ME Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level Function Rooms
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AO: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0523
  notes: 1 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0126
  from: DDC-2F-BOH
  to: PAHU-PF (BMS Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level Pre-Function
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0509
  - P-0510
  - P-0515
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0127
  from: DDC-2F-BOH
  to: PAHU-PF (Equipment Supplier)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level Pre-Function
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 3
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 5
  carries_point_ids:
  - P-0507
  - P-0508
  - P-0512
  - P-0513
  - P-0514
  notes: 5 I/O points carried, 6C cable; length 25 m (typical_range:boh_2f)
- id: C0128
  from: DDC-2F-BOH
  to: PAHU-PF (ME Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level Pre-Function
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AO: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0511
  notes: 1 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0129
  from: DDC-RD-PLANT
  to: PAHU-r.1 (BMS Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0284
  - P-0285
  - P-0290
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0130
  from: DDC-RD-PLANT
  to: PAHU-r.1 (Equipment Supplier)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 3
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 5
  carries_point_ids:
  - P-0282
  - P-0283
  - P-0287
  - P-0288
  - P-0289
  notes: 5 I/O points carried, 6C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0131
  from: DDC-RD-PLANT
  to: PAHU-r.1 (ME Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AO: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 1
  carries_point_ids:
  - P-0286
  notes: 1 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0132
  from: DDC-RD-PLANT
  to: PAHU-r.2 (BMS Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0296
  - P-0297
  - P-0302
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0133
  from: DDC-RD-PLANT
  to: PAHU-r.2 (Equipment Supplier)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    AI: 1
    AO: 1
    DI: 3
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 5
  carries_point_ids:
  - P-0294
  - P-0295
  - P-0299
  - P-0300
  - P-0301
  notes: 5 I/O points carried, 6C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0134
  from: DDC-RD-PLANT
  to: PAHU-r.2 (ME Contractor)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Roof Deck
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (ME-supplied valves/dampers \u2014 status + control)"
  spec_source: rule:me_actuator_default
  spec_basis: ME-Contractor-supplied actuators (electric valves, motorized dampers) carry status and modulating commands; shielding driven by signal-type rather than C/O
  by_class:
    AO: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 1
  carries_point_ids:
  - P-0298
  notes: 1 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0135
  from: DDC-2F-CHILLER
  to: PCHWP-1 (BMS Contractor)
  equipment_class: Primary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0089
  notes: 1 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0136
  from: DDC-2F-CHILLER
  to: PCHWP-1 (Equipment Supplier)
  equipment_class: Primary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 4
  carries_point_ids:
  - P-0085
  - P-0086
  - P-0087
  - P-0088
  notes: 4 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0137
  from: DDC-2F-CHILLER
  to: PCHWP-2 (BMS Contractor)
  equipment_class: Primary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 1
  conductor_count_required: 1
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0097
  notes: 1 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0138
  from: DDC-2F-CHILLER
  to: PCHWP-2 (Equipment Supplier)
  equipment_class: Primary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 4
  carries_point_ids:
  - P-0093
  - P-0094
  - P-0095
  - P-0096
  notes: 4 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0139
  from: DDC-2F-CHILLER
  to: PCHWP-3 (Equipment Supplier)
  equipment_class: Primary CHW Pump (Standby)
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 4
  carries_point_ids:
  - P-0101
  - P-0102
  - P-0103
  - P-0104
  notes: 4 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0140
  from: DDC-RD-PLANT
  to: RP-HZ (Equipment Supplier)
  equipment_class: Recirculating Pump
  system: HWL
  location: Roof Deck HWL Area
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 3
  carries_point_ids:
  - P-0229
  - P-0230
  - P-0231
  notes: 3 I/O points carried, 4C cable; length 15 m (typical_range:plant_room_rd_plant)
- id: C0141
  from: DDC-LG-PLANT
  to: RP-LZ (Equipment Supplier)
  equipment_class: Recirculating Pump
  system: HWL
  location: Lower Ground HWL Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0226
  - P-0227
  - P-0228
  notes: 3 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_lg_boiler_hwl)
- id: C0142
  from: DDC-LG-PLANT
  to: SB-1 (BMS Contractor)
  equipment_class: Steam Boiler
  system: VENT
  location: Lower Ground Boiler Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 4
    DI: 1
    DO: 1
  conductor_count_required: 7
  conductor_count_specified: 8
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 6
  carries_point_ids:
  - P-0178
  - P-0189
  - P-0190
  - P-0191
  - P-0192
  - '...'
  notes: 6 I/O points carried, 8C cable; length 12 m (typical_range:plant_room_lg_boiler_hwl)
- id: C0143
  from: DDC-LG-PLANT
  to: SB-1 (Equipment Supplier)
  equipment_class: Steam Boiler
  system: VENT
  location: Lower Ground Boiler Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 2
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 2
  carries_point_ids:
  - P-0179
  - P-0180
  notes: 2 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_lg_boiler_hwl)
- id: C0144
  from: DDC-LG-PLANT
  to: SB-2 (BMS Contractor)
  equipment_class: Steam Boiler
  system: VENT
  location: Lower Ground Boiler Room
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS signal \u2014 BMS-supplied sensors)"
  spec_source: rule:bms_signal_default
  spec_basis: "DRC-004 mandates FRLS jacket; sensor-grade BMS signals universally specified at 1.5 mm\xB2 for typical 5-30 m panel-to-device runs; shielding mandatory adjacent to lighting/power tray per\
    \ PEC-1 Article 10.3"
  by_class:
    AI: 4
    DI: 1
    DO: 1
  conductor_count_required: 7
  conductor_count_specified: 8
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 6
  carries_point_ids:
  - P-0195
  - P-0206
  - P-0207
  - P-0208
  - P-0209
  - '...'
  notes: 6 I/O points carried, 8C cable; length 12 m (typical_range:plant_room_lg_boiler_hwl)
- id: C0145
  from: DDC-LG-PLANT
  to: SB-2 (Equipment Supplier)
  equipment_class: Steam Boiler
  system: VENT
  location: Lower Ground Boiler Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 2
  conductor_count_required: 2
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 2
  carries_point_ids:
  - P-0196
  - P-0197
  notes: 2 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_lg_boiler_hwl)
- id: C0146
  from: DDC-2F-CHILLER
  to: SCHWP-1 (Equipment Supplier)
  equipment_class: Secondary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 4
  carries_point_ids:
  - P-0105
  - P-0106
  - P-0107
  - P-0108
  notes: 4 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0147
  from: DDC-2F-CHILLER
  to: SCHWP-2 (Equipment Supplier)
  equipment_class: Secondary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 4
  carries_point_ids:
  - P-0112
  - P-0113
  - P-0114
  - P-0115
  notes: 4 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0148
  from: DDC-2F-CHILLER
  to: SCHWP-3 (Equipment Supplier)
  equipment_class: Secondary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
    DO: 1
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 4
  carries_point_ids:
  - P-0119
  - P-0120
  - P-0121
  - P-0122
  notes: 4 I/O points carried, 4C cable; length 12 m (typical_range:plant_room_chiller_2f)
- id: C0149
  from: DDC-GF-BOH
  to: TEF-1.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: GF Main Lobby Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0588
  - P-0589
  - P-0590
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_gf)
- id: C0150
  from: DDC-GF-BOH
  to: TEF-1.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: GF Main Lobby Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0591
  - P-0592
  - P-0593
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_gf)
- id: C0151
  from: DDC-GF-BOH
  to: TEF-1.3 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: GF Main Lobby Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0594
  - P-0595
  - P-0596
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_gf)
- id: C0152
  from: DDC-GF-BOH
  to: TEF-1.4 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: GF Main Lobby Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0597
  - P-0598
  - P-0599
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_gf)
- id: C0153
  from: DDC-2F-BOH
  to: TEF-2.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: 2nd Floor Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0600
  - P-0601
  - P-0602
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0154
  from: DDC-2F-BOH
  to: TEF-2.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: 2nd Floor Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0603
  - P-0604
  - P-0605
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0155
  from: DDC-2F-BOH
  to: TEF-2B.3 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: 2nd Floor BOH Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0606
  - P-0607
  - P-0608
  notes: 3 I/O points carried, 4C cable; length 25 m (typical_range:boh_2f)
- id: C0156
  from: DDC-3F
  to: TEF-30.20 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: 3rd Floor Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0651
  - P-0652
  - P-0653
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0157
  from: DDC-3F
  to: TEF-3A.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: 3rd Floor Amenity Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0636
  - P-0637
  - P-0638
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0158
  from: DDC-3F
  to: TEF-3A.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: 3rd Floor Amenity Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0639
  - P-0640
  - P-0641
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0159
  from: DDC-3F
  to: TEF-3B (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: 3rd Floor Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0642
  - P-0643
  - P-0644
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0160
  from: DDC-3F
  to: TEF-3C.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: 3rd Floor Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0645
  - P-0646
  - P-0647
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0161
  from: DDC-3F
  to: TEF-3C.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: 3rd Floor Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:amenity_3f
  length_basis: "3rd Floor is amenity + first guestroom floor with a long corridor (~75-90 m visible in ECE-09). Field devices distributed along corridor and at amenity-zone perimeter. Panel sited at service-core\
    \ west end. Average run \u2248 32 m horizontal + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 3
  carries_point_ids:
  - P-0648
  - P-0649
  - P-0650
  notes: 3 I/O points carried, 4C cable; length 35 m (typical_range:amenity_3f)
- id: C0162
  from: DDC-B1-BOH
  to: TEF-B.1 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: Basement Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0672
  - P-0673
  - P-0674
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0163
  from: DDC-B1-BOH
  to: TEF-B.2 (Equipment Supplier)
  equipment_class: Exhaust Fan (Toilet)
  system: VENT
  location: Basement Toilet
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment auxiliary contacts \u2014 status/HOA/trip/start-stop)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier dry-contact signals; same FRLS jacket; shielding not required for digital signals; conductor count = required + spare per spare_strategy
  by_class:
    DI: 3
  conductor_count_required: 3
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 3
  carries_point_ids:
  - P-0675
  - P-0676
  - P-0677
  notes: 3 I/O points carried, 4C cable; length 28 m (typical_range:boh_b1)
- id: C0164
  from: DDC-2F-CHILLER
  to: CH-1 (Network)
  equipment_class: Chiller (Package Water-Cooled)
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0010
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_chiller_2f)"
- id: C0165
  from: DDC-2F-CHILLER
  to: CH-2 (Network)
  equipment_class: Chiller (Package Water-Cooled)
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0038
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_chiller_2f)"
- id: C0166
  from: DDC-2F-CHILLER
  to: CH-3 (Network)
  equipment_class: Chiller (Package Water-Cooled)
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0066
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_chiller_2f)"
- id: C0167
  from: DDC-2F-CHILLER
  to: PCHWP-1 (Network)
  equipment_class: Primary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0092
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_chiller_2f)"
- id: C0168
  from: DDC-2F-CHILLER
  to: PCHWP-2 (Network)
  equipment_class: Primary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0100
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_chiller_2f)"
- id: C0169
  from: DDC-2F-CHILLER
  to: SCHWP-1 (Network)
  equipment_class: Secondary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0111
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_chiller_2f)"
- id: C0170
  from: DDC-2F-CHILLER
  to: SCHWP-2 (Network)
  equipment_class: Secondary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0118
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_chiller_2f)"
- id: C0171
  from: DDC-2F-CHILLER
  to: SCHWP-3 (Network)
  equipment_class: Secondary CHW Pump
  system: AC
  location: 2nd Level Chiller Room
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0125
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_chiller_2f)"
- id: C0172
  from: DDC-LG-PLANT
  to: SB-1 (Network)
  equipment_class: Steam Boiler
  system: VENT
  location: Lower Ground Boiler Room
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0194
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_lg_boiler_hwl)"
- id: C0173
  from: DDC-LG-PLANT
  to: SB-2 (Network)
  equipment_class: Steam Boiler
  system: VENT
  location: Lower Ground Boiler Room
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0211
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_lg_boiler_hwl)"
- id: C0174
  from: DDC-RD-PLANT
  to: DOAS-RD.1 (Network)
  equipment_class: DOAS Unit
  system: VENT
  location: Roof Deck
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 1
  carries_point_ids:
  - P-0256
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 15 m (typical_range:plant_room_rd_plant)"
- id: C0175
  from: DDC-RD-PLANT
  to: DOAS-RD.2 (Network)
  equipment_class: DOAS Unit
  system: VENT
  location: Roof Deck
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 1
  carries_point_ids:
  - P-0281
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 15 m (typical_range:plant_room_rd_plant)"
- id: C0176
  from: DDC-RD-PLANT
  to: PAHU-r.1 (Network)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Roof Deck
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 1
  carries_point_ids:
  - P-0293
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 15 m (typical_range:plant_room_rd_plant)"
- id: C0177
  from: DDC-RD-PLANT
  to: PAHU-r.2 (Network)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Roof Deck
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 15
  length_method: typical_range:plant_room_rd_plant
  length_basis: "Roof-deck plant area is more spread out than indoor plant rooms (cooling towers separated for thermal isolation, calorifiers in adjacent enclosure). Allow 15 m typical with breakdown 12\
    \ m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering. Roof Deck exhaust fans (EF-RD.1, EF-RO.2, EF-1) also covered by this panel \u2014 same envelope."
  carries_io_points: 1
  carries_point_ids:
  - P-0305
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 15 m (typical_range:plant_room_rd_plant)"
- id: C0178
  from: DDC-2M-CASINO
  to: DOAS-2M (Network)
  equipment_class: "DOAS Unit (Casino \u2014 with CO/VOC)"
  system: VENT
  location: 2nd Mezzanine (Casino)
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 1
  carries_point_ids:
  - P-0327
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 18 m (typical_range:casino_2m_localized)"
- id: C0179
  from: DDC-2M-CASINO
  to: AHU-2M.1 (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 1
  carries_point_ids:
  - P-0342
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 18 m (typical_range:casino_2m_localized)"
- id: C0180
  from: DDC-2M-CASINO
  to: AHU-2M.2 (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 1
  carries_point_ids:
  - P-0357
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 18 m (typical_range:casino_2m_localized)"
- id: C0181
  from: DDC-2M-CASINO
  to: AIR-ION-2M.1 (Network)
  equipment_class: Air Ionizer (Casino)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 1
  carries_point_ids:
  - P-0361
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 18 m (typical_range:casino_2m_localized)"
- id: C0182
  from: DDC-2M-CASINO
  to: AIR-ION-2M.2 (Network)
  equipment_class: Air Ionizer (Casino)
  system: AC
  location: 2nd Mezzanine (Casino)
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 18
  length_method: typical_range:casino_2m_localized
  length_basis: Casino mezzanine plant zone is mid-sized; AHU and DOAS spread across the 2M MEP corridor with the panel central. Allow 18 m typical (15 horizontal + 1.5 vertical + 1 termination + 0.5 cornering).
  carries_io_points: 1
  carries_point_ids:
  - P-0365
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 18 m (typical_range:casino_2m_localized)"
- id: C0183
  from: DDC-2F-BOH
  to: AHU-B.1 (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0380
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0184
  from: DDC-2F-BOH
  to: AHU-B.2 (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0395
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0185
  from: DDC-2F-BOH
  to: AHU-B.3 (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level BOH
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0410
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0186
  from: DDC-2F-BOH
  to: AHU-PF (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Pre-Function
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0425
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0187
  from: DDC-2F-BOH
  to: AHU-EL (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Executive Lounge
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0440
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0188
  from: DDC-2F-BOH
  to: AHU-FR2 (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Function Room 2
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0455
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0189
  from: DDC-2F-BOH
  to: AHU-FR3 (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: 2nd Level Function Room 3
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0470
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0190
  from: DDC-2F-BOH
  to: PAHU-B.1 (Network)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0482
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0191
  from: DDC-2F-BOH
  to: PAHU-B.2 (Network)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0494
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0192
  from: DDC-2F-BOH
  to: PAHU-B.3 (Network)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level BOH
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0506
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0193
  from: DDC-2F-BOH
  to: PAHU-PF (Network)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level Pre-Function
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0518
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0194
  from: DDC-2F-BOH
  to: PAHU-FR (Network)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: 2nd Level Function Rooms
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0530
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0195
  from: DDC-GF-BOH
  to: AHU-1.1 (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0545
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_gf)"
- id: C0196
  from: DDC-GF-BOH
  to: AHU-1.2 (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0560
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_gf)"
- id: C0197
  from: DDC-GF-BOH
  to: AHU-1.3 (Network)
  equipment_class: AHU (Chilled-Water-Served)
  system: AC
  location: Ground Floor BOH
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0575
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_gf)"
- id: C0198
  from: DDC-B1-BOH
  to: PAHU-0.1 (Network)
  equipment_class: Precooled Air Handling Unit
  system: VENT
  location: Basement
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 28
  length_method: typical_range:boh_b1
  length_basis: Basement-1 has parking + service + multiple equipment rooms (sewage, fuel, pump, battery, mechanical); fans are widely scattered. Panel sited near B1 service-core IDF / mechanical room.
    Average run 25 m horizontal + 1 m vertical + 1 m termination + 1 m cornering = 28 m.
  carries_io_points: 1
  carries_point_ids:
  - P-0587
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 28 m (typical_range:boh_b1)"
- id: C0199
  from: DDC-LG-PLANT
  to: MPM-MAIN (Network)
  equipment_class: Multifunction Power Meter (Main)
  system: EL
  location: Lower Ground Main Switchroom
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0730
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_lg_boiler_hwl)"
- id: C0200
  from: DDC-2F-CHILLER
  to: MPM-CHILLER (Network)
  equipment_class: Multifunction Power Meter (Feeder)
  system: EL
  location: 2nd Level Chiller MCC
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_chiller_2f
  length_basis: "Industry-typical plant-room same-room run with allowances for tray drop + cornering + 0.5 m terminations on each end. Baseline: chiller room ~10\xD78 m envelope; longest run from panel\
    \ corner to far chiller skid \u2248 10 m + 1 m vertical drop + 1 m termination tails."
  carries_io_points: 1
  carries_point_ids:
  - P-0732
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_chiller_2f)"
- id: C0201
  from: DDC-2F-BOH
  to: MPM-AHU-2F (Network)
  equipment_class: Multifunction Power Meter (Feeder)
  system: EL
  location: 2nd Level AHU MCC
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_2f
  length_basis: "2nd Floor BOH zone is large (function-room program + multiple AHU rooms + service areas); panel sited near 2F service-core IDF on the west end. Average run from panel to BOH AHU/PAHU rooms\
    \ \u2248 22 m horizontal + 1 m vertical (slab pen) + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0734
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_2f)"
- id: C0202
  from: DDC-GF-BOH
  to: MPM-AHU-GF (Network)
  equipment_class: Multifunction Power Meter (Feeder)
  system: EL
  location: Ground Floor AHU MCC
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0736
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_gf)"
- id: C0203
  from: DDC-LG-PLANT
  to: MPM-LIGHT-A (Network)
  equipment_class: Multifunction Power Meter (Feeder)
  system: EL
  location: Lower Ground Lighting Panel A
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0738
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_lg_boiler_hwl)"
- id: C0204
  from: DDC-LG-PLANT
  to: MPM-LIGHT-B (Network)
  equipment_class: Multifunction Power Meter (Feeder)
  system: EL
  location: Lower Ground Lighting Panel B
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 12
  length_method: typical_range:plant_room_lg_boiler_hwl
  length_basis: "Industry-typical plant-room same-room run. Boiler room and HWL plant adjacent on Lower Ground; combined envelope ~12\xD78 m with panel central. Longest run \u2248 9 m horizontal + 1 m vertical\
    \ drop + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0740
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 12 m (typical_range:plant_room_lg_boiler_hwl)"
- id: C0205
  from: DDC-GF-BOH
  to: FACP-GW (Network)
  equipment_class: FACP Gateway
  system: FDAS
  location: Ground Floor Fire Command Center
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP)"
  conductor_count_required: 4P (8 wires)
  conductor_count_specified: Cat6 patch + permanent link
  length_m: 25
  length_method: typical_range:boh_gf
  length_basis: "Ground Floor includes lobby + F&B + retail + BOH; AHUs are spread across BOH zones, FACP at FCC near main entrance. Average run from panel (service-core IDF) to remote AHU \u2248 22 m horizontal\
    \ + 1 m vertical + 1 m termination + 1 m cornering."
  carries_io_points: 1
  carries_point_ids:
  - P-0744
  notes: "BACnet/IP or Modbus TCP \u2014 Cat6 to equipment controller; length 25 m (typical_range:boh_gf)"
trunk_cables:
- id: T0206
  from: BMS Server Room (head-end)
  to: All BMS panels at 2nd Floor
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP) \u2014 riser fiber + Cat6 trunk"
  length_m: 80
  notes: "Network trunk for 2nd Floor \u2014 fiber to floor switch + Cat6 distribution to floor's BMS panels"
- id: T0207
  from: BMS Server Room (head-end)
  to: All BMS panels at 3rd Floor
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP) \u2014 riser fiber + Cat6 trunk"
  length_m: 80
  notes: "Network trunk for 3rd Floor \u2014 fiber to floor switch + Cat6 distribution to floor's BMS panels"
- id: T0208
  from: BMS Server Room (head-end)
  to: All BMS panels at Basement
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP) \u2014 riser fiber + Cat6 trunk"
  length_m: 80
  notes: "Network trunk for Basement \u2014 fiber to floor switch + Cat6 distribution to floor's BMS panels"
- id: T0209
  from: BMS Server Room (head-end)
  to: All BMS panels at Ground
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP) \u2014 riser fiber + Cat6 trunk"
  length_m: 80
  notes: "Network trunk for Ground \u2014 fiber to floor switch + Cat6 distribution to floor's BMS panels"
- id: T0210
  from: BMS Server Room (head-end)
  to: All BMS panels at Lower Ground
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP) \u2014 riser fiber + Cat6 trunk"
  length_m: 80
  notes: "Network trunk for Lower Ground \u2014 fiber to floor switch + Cat6 distribution to floor's BMS panels"
- id: T0211
  from: BMS Server Room (head-end)
  to: BMS panel controllers (per topology id mstp_field_backbone)
  cable_type: "BACnet MS/TP shielded twisted-pair trunk, 1pr \xD7 22 AWG low-cap"
  length_m: 250
  length_method: typical_range
  length_basis: "MS/TP field backbone connects DDC-2F-CHILLER, DDC-2F-BOH, DDC-2M-CASINO, DDC-RD-PLANT, DDC-LG-PLANT, DDC-GF-BOH, DDC-B1-BOH, DDC-3F. Routed via service-core IDF stack on west end (per ECE\
    \ auxiliary layouts) + horizontal BOH-corridor tray on each panel's floor. Vertical span B1 \u2192 RD \u2248 13 floors \xD7 4.5 m = 58.5 m + 8 panel-side horizontal segments at ~25 m each \u2248 200\
    \ m + 25% routing factor \u2248 250 m typical."
  notes: "MS/TP field backbone connects DDC-2F-CHILLER, DDC-2F-BOH, DDC-2M-CASINO, DDC-RD-PLANT, DDC-LG-PLANT, DDC-GF-BOH, DDC-B1-BOH, DDC-3F. Routed via service-core IDF stack on west end (per ECE auxiliary\
    \ layouts) + horizontal BOH-corridor tray on each panel's floor. Vertical span B1 \u2192 RD \u2248 13 floors \xD7 4.5 m = 58.5 m + 8 panel-side horizontal segments at ~25 m each \u2248 200 m + 25% routing\
    \ factor \u2248 250 m typical."
- id: T0212
  from: BMS Server Room (head-end)
  to: BMS panel controllers (per topology id bacnet_ip_backbone)
  cable_type: "BACnet MS/TP shielded twisted-pair trunk, 1pr \xD7 22 AWG low-cap"
  length_m: 150
  length_method: typical_range
  length_basis: "BACnet/IP backbone is fibre + Cat6: head-end (Lower Ground IT room per Q-011) \u2192 core switch \u2192 riser fibre to per-floor IDF edge switches \u2192 Cat6 to each DDC field panel. Vertical\
    \ fibre run LG \u2192 RD \u2248 13 floors \xD7 4.5 m = 58.5 m. 8 horizontal fibre segments at ~5 m each. Total \u2248 100-150 m measured; allow 150 m typical."
  notes: "BACnet/IP backbone is fibre + Cat6: head-end (Lower Ground IT room per Q-011) \u2192 core switch \u2192 riser fibre to per-floor IDF edge switches \u2192 Cat6 to each DDC field panel. Vertical\
    \ fibre run LG \u2192 RD \u2248 13 floors \xD7 4.5 m = 58.5 m. 8 horizontal fibre segments at ~5 m each. Total \u2248 100-150 m measured; allow 150 m typical."
panel_power_feeds:
- id: P0213
  from: Local panelboard / EE-supplied feeder
  to: "DDC-2F-BOH \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 10
  length_method: typical_range:panel_power_feed_local
  length_basis: Each BMS DDC panel sits adjacent to the floor's electrical closet / IDF. Industry typical 8-12 m from the floor distribution panelboard breaker to the BMS panel. Allow 10 m with breakdown
    7 m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering.
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 10 m (typical_range:panel_power_feed_local)
- id: P0214
  from: Local panelboard / EE-supplied feeder
  to: "DDC-2F-CHILLER \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 10
  length_method: typical_range:panel_power_feed_local
  length_basis: Each BMS DDC panel sits adjacent to the floor's electrical closet / IDF. Industry typical 8-12 m from the floor distribution panelboard breaker to the BMS panel. Allow 10 m with breakdown
    7 m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering.
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 10 m (typical_range:panel_power_feed_local)
- id: P0215
  from: Local panelboard / EE-supplied feeder
  to: "DDC-2M-CASINO \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 10
  length_method: typical_range:panel_power_feed_local
  length_basis: Each BMS DDC panel sits adjacent to the floor's electrical closet / IDF. Industry typical 8-12 m from the floor distribution panelboard breaker to the BMS panel. Allow 10 m with breakdown
    7 m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering.
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 10 m (typical_range:panel_power_feed_local)
- id: P0216
  from: Local panelboard / EE-supplied feeder
  to: "DDC-3F \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 10
  length_method: typical_range:panel_power_feed_local
  length_basis: Each BMS DDC panel sits adjacent to the floor's electrical closet / IDF. Industry typical 8-12 m from the floor distribution panelboard breaker to the BMS panel. Allow 10 m with breakdown
    7 m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering.
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 10 m (typical_range:panel_power_feed_local)
- id: P0217
  from: Local panelboard / EE-supplied feeder
  to: "DDC-B1-BOH \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 10
  length_method: typical_range:panel_power_feed_local
  length_basis: Each BMS DDC panel sits adjacent to the floor's electrical closet / IDF. Industry typical 8-12 m from the floor distribution panelboard breaker to the BMS panel. Allow 10 m with breakdown
    7 m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering.
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 10 m (typical_range:panel_power_feed_local)
- id: P0218
  from: Local panelboard / EE-supplied feeder
  to: "DDC-GF-BOH \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 10
  length_method: typical_range:panel_power_feed_local
  length_basis: Each BMS DDC panel sits adjacent to the floor's electrical closet / IDF. Industry typical 8-12 m from the floor distribution panelboard breaker to the BMS panel. Allow 10 m with breakdown
    7 m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering.
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 10 m (typical_range:panel_power_feed_local)
- id: P0219
  from: Local panelboard / EE-supplied feeder
  to: "DDC-LG-PLANT \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 10
  length_method: typical_range:panel_power_feed_local
  length_basis: Each BMS DDC panel sits adjacent to the floor's electrical closet / IDF. Industry typical 8-12 m from the floor distribution panelboard breaker to the BMS panel. Allow 10 m with breakdown
    7 m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering.
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 10 m (typical_range:panel_power_feed_local)
- id: P0220
  from: Local panelboard / EE-supplied feeder
  to: "DDC-RD-PLANT \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 10
  length_method: typical_range:panel_power_feed_local
  length_basis: Each BMS DDC panel sits adjacent to the floor's electrical closet / IDF. Industry typical 8-12 m from the floor distribution panelboard breaker to the BMS panel. Allow 10 m with breakdown
    7 m horizontal + 1.5 m vertical drop + 1 m termination + 0.5 m cornering.
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 10 m (typical_range:panel_power_feed_local)