# 5.3.1 — Integrated Test Chiller Plant

**Module:** [bms/testing-commissioning](../../../_playbook/modules/bms/testing-commissioning.md)
**WBS leaf:** 5.3.1
**Project:** Kingsford Hotel Bacolod — BMS (AB-Run-6)
**Date:** 2026-04-28

### Project-specific values
- **Joint test:** ME contractor (chillers, pumps, valves) + BMS (sensors, HLI integration).
- **Scope:** chiller plant manager handshake, lead/lag rotation, free-cooling logic, pump-fail + chiller-trip alarm propagation.
- **References:** MC Standards ME chiller block, BMS-03 chiller P&ID.