# 5.3 — Integrated Systems Testing

**Module:** [bms/testing-commissioning](../../../_playbook/modules/bms/testing-commissioning.md)
**WBS leaf:** 5.3
**Project:** Kingsford Hotel Bacolod — BMS (AB-Run-6)
**Date:** 2026-04-28

### Project-specific values
- **Joint with:** ME contractor (water systems), EE contractor (energy meters + DBV-MECH), Casino fit-out (Air Ionizer + DOAS-2M), FDAS contractor (FACP gateway).
- **Sequence:** chiller plant first (5.3.1), then boiler (5.3.2), then casino (parallel with FDAS), then full integrated demo for owner SAT.
- **References:** B3, C2 coordination matrix, D1 phase 10.