# 3.8 — Pre Commissioning

**Module:** [bms/testing-commissioning](../../../_playbook/modules/bms/testing-commissioning.md)
**WBS leaf:** 3.8
**Project:** Kingsford Hotel Bacolod — BMS (AB-Run-6)
**Date:** 2026-04-28

### Project-specific values
- **Scope:** point-to-point checks of all 744 I/O points + 7 trunk segments + 8 panel power feeds.
- **Production rate (per B3):** 678 distinct test items at avg 25 min/item = 280 hr.
- **References:** B3, A3.