# 3.5.1 — Field Device Install Hvac

**Module:** [bms/field-devices-hvac](../../../_playbook/modules/bms/field-devices-hvac.md)
**WBS leaf:** 3.5.1
**Project:** Kingsford Hotel Bacolod — BMS (AB-Run-6)
**Date:** 2026-04-28

### Project-specific values
- **Scope:** install all BMS-supplied HVAC field devices per A2 / B4 device_install_rates_by_class.
- **Production rates per class** documented in B4-site-factors.yaml.
- **Sequence:** plant rooms first (chiller room, RD plant, LG boiler/HWL), then BOH AHU/PAHU rooms, then exhaust-fan motor terminations on each floor.
- **References:** B4, A2, MC Standards ME C/O column.