# 3.3 — Cable Pulling

**Module:** [bms/cabling-and-containment](../../../_playbook/modules/bms/cabling-and-containment.md)
**WBS leaf:** 3.3
**Project:** Kingsford Hotel Bacolod — BMS (AB-Run-6)
**Date:** 2026-04-28

### Project-specific values
- **Scope:** ~5,170 m total cable across MS/TP backbone + BACnet/IP fibre + Cat6 + field control + Modbus.
- **Production rate (per B4):** see B4 cable_pull_per_m line; modifier 1.05 (high-ceiling rigging at chiller room + roof deck).
- **Sequence:** backbone first (riser shaft + main BOH corridor), then plant-room field cables, then floor branches.
- **References:** B4, A3, D1.