# 1.2 — Engineering Design

**Module:** [bms/programming-engineering](../../../_playbook/modules/bms/programming-engineering.md)
**WBS leaf:** 1.2
**Project:** Kingsford Hotel Bacolod — BMS (AB-Run-6)
**Date:** 2026-04-28

### Project-specific values
- **Shop drawings:** A4 panel schedule, A5 network architecture, A3 cable schedule with route assumptions disclosed, A7 power-provisions schedule with placeholder circuit IDs (Q-014).
- **Working-doc inputs:** A1 (744 pts) / A2 (109 instances) / A4 (8 panels / 19 controllers) / A5 / A6 / A7.
- **Submittal cycle:** Megaworld Engineering Design Department review per BMS-01 stamp workflow (one round observed in Construction Bulletin No.8); 2 cycles assumed in D1.
- **References:** BMS-01 General Spec / Software / Hardware / System Configuration / Backups; DRC-004 Section 9.