# 02 — Classification

**Project:** Kingsford Hotel Bacolod — Building Management System
**Customer:** Megaworld Corporation (slug: `megaworld`; customer-kb entry: yes — STUB at `_customer-kb/megaworld/approved-brands.md`)
**Date:** 2026-04-28

## Discipline

- **Primary:** BMS
- **Secondary:** none — but the BMS scope spans HVAC monitoring, plumbing (domestic hot-water), and electrical-coordination boundaries documented in C1/C2.

## Stage

- **Greenfield (new construction)**
- Cited evidence:
  - EE Plan cover letter — *"Construction Bulletin No.8"* dated 2025-11-05, "For Construction" status referencing *"electrical revisions due to the adjusted mechanical layout and the added power provisions for the kitchen layouts from Basement to 3rd floor"* (`00-customer-inputs/EE Plan (TUEC).pdf`, page 1).
  - BMS Points list bears stamp *"CONSTRUCTION BULLETIN / DATE OCTOBER 2025"* with reviewer signature dated 05Dec25 on sheets BMS-01 / BMS-02 / BMS-03 (`00-customer-inputs/BMS Points list (TUEC).pdf`).
  - **Absence** of any existing-system inventory, demolition scope, phasing/cutover plan, or "as-is" documentation in the inputs.
- Cover-letter wording mismatch: requirement letter uses the word *"Rehabilitation"* but the technical evidence is unambiguously new construction. **Per Phase 2 triangulation rule, technical evidence wins.** Raise `Q-001` to confirm wording vs intent with the customer.

## Scope type (legacy multi-select)

- [x] Supply
- [x] Installation
- [x] Programming
- [x] Testing & Commissioning
- [x] Training (assumed unless stated — refine in Phase 8)
- [ ] Maintenance / O&M post-handover (not stated — flag for Phase 8)

## Scope shape (Op#12)

```yaml
scope_shape:
  supply: full
  supply_categories: []
  installation: full
  osm_categories: []
  services: full
  notes: |
    Turnkey BMS — Supply, Delivery, Installation, Testing and Commissioning per the
    customer's request. Matches Pattern 1 (Turnkey BMS, Kingsford-shape) in
    _playbook/checklists/pathway-activation.md. All pathways ACTIVE.
```

Pattern citation: **Pattern 1 — Turnkey BMS** (`_playbook/checklists/pathway-activation.md`). No clone-and-modify needed.

## Facility type

- **Hotel / Hospitality** (Megaworld condotel-grade hotel; mixed program — guestrooms, amenity floors, F&B, BOH/MEP)

## Estimated tier

- **Medium** — basis: BMS points list spans 6+ MEP system families across 7+ levels (Basement, Lower Ground, Ground, 2F, 3F amenity, guestroom levels, Roof Deck). Point count to be confirmed by Tier 3 extraction; the per-class scope from MC Standards reads at the upper end of Medium (~600–700 physical points typical for a hospitality property of this footprint).

## Implications for later phases

- **Required-doc checklist key:** `bms-greenfield-hospitality` (consult `_playbook/checklists/required-docs-by-project-type.md` row that matches BMS / Greenfield / Hotel).
- **Module catalog:** `_playbook/modules/bms/` (no electrical-overlay clone needed for AB6 — the kickoff's Patch B references the recently added electrical overlay but that's for a future Electrical project; this project is BMS-shaped).
- **Stage-specific assumptions:** greenfield-set (no demolition / no cutover / no after-hours premium / no existing-system reuse). Phase 7 carries forward.
- **Customer KB:** `_customer-kb/megaworld/approved-brands.md` is a STUB. Brand selections will use internal preferred (`Siemens` for BMS / PLC / FDAS / SCADA, `Dell` for PCs) and surface as Megaworld-review assumptions. Q-MW-001 / Q-MW-002 / Q-MW-003 from the KB carry forward into this project's RFI list as appropriate.
- **Drawing-availability outlook:** EE Plan present (22 A4 pages, mostly electrical power layouts — limited BMS-direct routing value); no architectural or mechanical layouts. Phase 3 triage will commit measure-vs-fallback per working doc.
- **Special considerations:**
  - Wording-mismatch RFI (rehabilitation vs new construction) — `Q-001`.
  - EL-points-list addendum may be issued separately — pending; flag for Phase 8.
  - Plumbing scope appears limited to domestic hot water (no fire pumps, sump pumps, transfer pumps in PL points list) — confirm in Phase 8 whether expanded plumbing monitoring is in BMS scope.
  - Casino/gaming-floor adjacency cited in the customer-kb (CO sensors at return air per gaming-board minimums) — Kingsford Hotel Bacolod is co-located with Kingsford casino floors; verify gaming-floor IAQ requirements when finalizing C1 scope split.