# D1 — Project Schedule

**Project:** Kingsford Hotel Bacolod — BMS
**Date:** 2026-04-28
**Basis:** A-011 (14-week comfortable timeline). Pending Q-003 confirmation.

## Phase plan

```mermaid
gantt
    dateFormat  YYYY-MM-DD
    title  Kingsford Hotel Bacolod — BMS Schedule (14 weeks)
    section Engineering
    PO + Mobilization                  :a1, 2026-05-15, 7d
    Engineering & Submittals           :a2, after a1, 21d
    FAT                                :a3, after a2, 5d
    section Material
    Long-lead procurement              :b1, after a1, 35d
    Field-device procurement           :b2, after a1, 28d
    Panel fabrication                  :b3, after a2, 14d
    section Installation
    Containment + risers (vertical)    :c1, 2026-06-12, 14d
    Cable pull (control + network)     :c2, after c1, 21d
    Panel installation                 :c3, after c2, 10d
    Field-device installation          :c4, after c3, 14d
    Head-end installation              :c5, after c3, 7d
    section Programming
    Controller programming             :d1, after c3, 21d
    Graphics + reports                 :d2, after d1, 14d
    section T&C
    Pre-commissioning (P2P)            :e1, after c4, 10d
    Functional + integrated tests      :e2, after e1, 14d
    Owner SAT                          :e3, after e2, 5d
    section Handover
    Training + As-builts               :f1, after e3, 5d
    12-month warranty support          :f2, after f1, 365d
```

## Milestones

| Date | Milestone |
|------|-----------|
| 2026-05-15 | Notice to Proceed / PO |
| 2026-06-05 | Engineering submittals approved |
| 2026-06-19 | Long-lead equipment in shop |
| 2026-06-26 | First containment crew on site |
| 2026-08-21 | Field installation 80% complete |
| 2026-09-04 | Programming complete |
| 2026-09-18 | Functional T&C complete |
| 2026-09-25 | Owner SAT complete; substantial completion |
| 2027-09-25 | Warranty period ends |

## Notes

- Greenfield assumption: standard daytime hours, no after-hours premium, no hot cutover.
- Ready-to-test prerequisites: ME equipment delivered + powered; structural openings cut.
- Compressed-timeline scenario (<10 weeks): re-plan with double-shift T&C — adds ~+20% labor.