# B3 — Commissioning Point Inventory
#
metadata:
  project: "Kingsford Hotel Bacolod \u2014 BMS"
  generated_from: A1-io-list.yaml + A2-equipment-takeoff.yaml
  generator: _playbook/tools/generate-b1-b3-programming-and-commissioning.py
  rates:
    hrs_per_p2p_point: 0.15
    hrs_per_functional_test: 1.5
    hrs_per_integrated_test: 4.0
summary:
  p2p_points: 570
  functional_tests: 23
  integrated_tests: 8
  total_test_items: 601
tc_hours:
  point_to_point: 85.5
  functional_per_equipment: 34.5
  integrated_sequences: 32.0
  total_tc_hours: 152.0
  person_days_at_8hr: 19.0
p2p_breakdown_by_panel:
  BMS-PNL-CHWPLANT-2F: 121
  BMS-PNL-BOHAHU-2F: 120
  BMS-PNL-VENT-3F: 81
  BMS-PNL-AHU-RD: 44
  BMS-PNL-VENT-2F: 39
  BMS-PNL-CT-RD: 35
  BMS-PNL-CASINO-2F: 30
  BMS-PNL-VENT-GF: 27
  BMS-PNL-BOILER-LG: 22
  BMS-PNL-PLUMBING-LG: 18
  BMS-PNL-AHU-2F: 12
  BMS-PNL-PLUMBING-RD: 12
  BMS-PNL-VENT-RD: 9
functional_test_inventory:
- equipment: AHU-2/B.2/B.3/PP/CL/FRE/FRD
  equipment_class: AHU (Chilled-Water-Served)
  location: 2F
- equipment: AHU-RD (with CHW mod valve)
  equipment_class: AHU (Chilled-Water-Served)
  location: RD
- equipment: CDWP-1 to CDWP-3
  equipment_class: Condenser Water Pump
  location: 2F
- equipment: CH-1 to CH-3
  equipment_class: Chiller (Package Water-Cooled)
  location: 2F
- equipment: CHW Supply & Return Main Header
  equipment_class: CHW Supply Main Header
  location: 2F
- equipment: CHWP-1 to CHWP-3
  equipment_class: Primary CHW Pump
  location: 2F
- equipment: CT-1 to CT-3
  equipment_class: Cooling Tower
  location: RD
- equipment: "DOAS (Casino) \u2014 2 units"
  equipment_class: DOAS Unit
  location: 2F
- equipment: EF-RD.1/RD.2, EF-1
  equipment_class: Exhaust Fan (General)
  location: RD
- equipment: "HP-HZ (\xD73)"
  equipment_class: Heat Pump
  location: RD
- equipment: "HP-LZ (\xD73)"
  equipment_class: Heat Pump
  location: LG
- equipment: HW Supply & Return Header (LG)
  equipment_class: CHW Supply Main Header
  location: LG
- equipment: "HWT-HZ (\xD73)"
  equipment_class: Calorifier (Hot Water Storage Tank)
  location: RD
- equipment: "HWT-LZ (\xD73)"
  equipment_class: Calorifier (Hot Water Storage Tank)
  location: LG
- equipment: PAHU-0.1
  equipment_class: Precooled Air Handling Unit
  location: 2F
- equipment: "PAHU-RD (\xD72)"
  equipment_class: Precooled Air Handling Unit
  location: RD
- equipment: "RP-HZ (\xD73)"
  equipment_class: Recirculating Pump
  location: RD
- equipment: "RP-LZ (\xD73)"
  equipment_class: Recirculating Pump
  location: LG
- equipment: SB-1 & SB-2
  equipment_class: Steam Boiler
  location: LG
- equipment: Sanitizer for AHU-2M.1/2M.2
  equipment_class: Ozone Generator (UV-light or Corona)
  location: 2F
- equipment: TEF-1.1 to 1.4 + EF-1.2A/LPG.1/1MR.1/1STO.1/MRF.1
  equipment_class: Exhaust Fan (General)
  location: GF
- equipment: TEF-2.1/2.3/2B.3 + EF-2B.1/2B.2/GS.1&GS.2 + EF-2.1 to 2.4 + EF-CHRx2
  equipment_class: Exhaust Fan (General)
  location: 2F
- equipment: TEF-3Ax2/3B/3Cx2/3Dx20 + others
  equipment_class: Exhaust Fan (General)
  location: 3F
integrated_test_inventory:
- Chiller plant sequencing (chiller staging + CHW pump + COW pump + cooling tower fan)
- CHW differential pressure control (PCHWP VFD speed via header dP)
- AHU supply-air temperature control (modulating CHW valve loop)
- DOAS demand-controlled ventilation (CO2-based fresh air modulation)
- Hotwater system sequencing (heat pump + recirculating pump + tank temp)
- Boiler firing rate vs. steam pressure
- Cooling tower fan staging vs. condenser water temperature
- Energy savings algorithm verification (max-demand limiting + load shedding)
notes:
- 'P2P = point-to-point verification: every physical I/O calibrated, range-checked, polarity verified, scaled correctly.'
- 'Functional test: per-equipment sequence verification (e.g., does the AHU CHW valve modulate correctly to maintain supply air temp?).'
- 'Integrated test: cross-system sequence (e.g., chiller staging triggers correctly when load increases).'
- "Owner T&C / SAT: separate from this \u2014 handled in proposal as an item under 5.5 in WBS."