# A3 — Cable Schedule
# Generated from A1-io-list.yaml; lengths per A-001
#
metadata:
  project: "Kingsford Hotel Bacolod \u2014 BMS"
  generated_from: A1-io-list.yaml
  generator: _playbook/tools/generate-a3-cable-schedule.py
  assumptions:
  - 'A-001: 30 m average panel-to-device run; 80 m trunk per floor'
  - Cable conductor count = (points + 2 spare), rounded up to standard 4/6/8/12 sizes
  - Cat6 for all BACnet/IP network drops
  - BACnet MS/TP backbone interconnects all BMS panels (refine after Q-008)
  - 240V single-phase power feed to each BMS panel @ 30 m default length
summary:
  total_field_cable_runs: 29
  total_field_cable_length_m: 473
  total_trunk_cable_length_m: 400
  total_power_feed_length_m: 234
  grand_total_cable_length_m: 1107
  field_cable_by_type_m:
    "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)": 305
    "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)": 168
  field_cable_by_panel_m:
    BMS-PNL-BOHAHU-2F: 2
    BMS-PNL-AHU-RD: 4
    BMS-PNL-CHWPLANT-2F: 5
    BMS-PNL-CT-RD: 2
    BMS-PNL-CASINO-2F: 3
    BMS-PNL-VENT-RD: 1
    BMS-PNL-PLUMBING-LG: 3
    BMS-PNL-PLUMBING-RD: 2
    BMS-PNL-AHU-2F: 2
    BMS-PNL-BOILER-LG: 2
    BMS-PNL-VENT-GF: 1
    BMS-PNL-VENT-2F: 1
    BMS-PNL-VENT-3F: 1
field_cables:
- id: C0001
  from: BMS-PNL-BOHAHU-2F
  to: AHU-2/B.2/B.3/PP/CL/FRE/FRD (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: "Air Handling \u2014 Basement / Podium BOH"
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 70
    AO: 30
  conductor_count_required: 126
  conductor_count_specified: 126
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_same_room
  length_basis: "Plant-room equipment is typically within 5\u201315 m straight-line of its dedicated BMS field\npanel. Add ~2 m vertical for floor-mounted panel to ceiling tray, ~3 m horizontal to\nequipment,\
    \ ~2 m drop to terminations, ~3 m allowance for cornering and slack at termination.\n~12 m matches the median of Philippine hotel-BMS prior-project benchmarks for chiller-plant\nand boiler-room cabling\
    \ where the panel is sited at the room's wall and equipment is\narranged in two rows along the room's length.\n"
  carries_io_points: 100
  carries_point_ids:
  - P-00122
  - P-00123
  - P-00124
  - P-00125
  - P-00126
  - '...'
  notes: 100 I/O points carried, 126C cable; length 12 m (typical_range:plant_room_same_room)
- id: C0002
  from: BMS-PNL-BOHAHU-2F
  to: AHU-2/B.2/B.3/PP/CL/FRE/FRD (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: "Air Handling \u2014 Basement / Podium BOH"
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 20
  conductor_count_required: 23
  conductor_count_specified: 24
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_same_room
  length_basis: "Plant-room equipment is typically within 5\u201315 m straight-line of its dedicated BMS field\npanel. Add ~2 m vertical for floor-mounted panel to ceiling tray, ~3 m horizontal to\nequipment,\
    \ ~2 m drop to terminations, ~3 m allowance for cornering and slack at termination.\n~12 m matches the median of Philippine hotel-BMS prior-project benchmarks for chiller-plant\nand boiler-room cabling\
    \ where the panel is sited at the room's wall and equipment is\narranged in two rows along the room's length.\n"
  carries_io_points: 20
  carries_point_ids:
  - P-00222
  - P-00223
  - P-00224
  - P-00225
  - P-00226
  - '...'
  notes: 20 I/O points carried, 24C cable; length 12 m (typical_range:plant_room_same_room)
- id: C0003
  from: BMS-PNL-AHU-RD
  to: AHU-RD (with CHW mod valve) (BMS Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: "Air Handling \u2014 Roofdeck AHU"
  location: RD
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 16
    AO: 4
  conductor_count_required: 25
  conductor_count_specified: 25
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 16
  length_method: measured
  length_basis: ECE-16 (RD)
  carries_io_points: 20
  carries_point_ids:
  - P-00552
  - P-00553
  - P-00554
  - P-00555
  - P-00556
  - '...'
  notes: 20 I/O points carried, 25C cable; length 16 m (measured)
- id: C0004
  from: BMS-PNL-AHU-RD
  to: AHU-RD (with CHW mod valve) (ME Contractor)
  equipment_class: AHU (Chilled-Water-Served)
  system: "Air Handling \u2014 Roofdeck AHU"
  location: RD
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 8
    DO: 4
  conductor_count_required: 14
  conductor_count_specified: 16
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 14
  length_method: measured
  length_basis: ECE-16 (RD)
  carries_io_points: 12
  carries_point_ids:
  - P-00572
  - P-00573
  - P-00574
  - P-00575
  - P-00576
  - '...'
  notes: 12 I/O points carried, 16C cable; length 14 m (measured)
- id: C0005
  from: BMS-PNL-CHWPLANT-2F
  to: CDWP-1 to CDWP-3 (ME Contractor)
  equipment_class: Condenser Water Pump
  system: Chilled Water Plant
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 9
    DO: 3
  conductor_count_required: 13
  conductor_count_specified: 16
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_same_room
  length_basis: "Plant-room equipment is typically within 5\u201315 m straight-line of its dedicated BMS field\npanel. Add ~2 m vertical for floor-mounted panel to ceiling tray, ~3 m horizontal to\nequipment,\
    \ ~2 m drop to terminations, ~3 m allowance for cornering and slack at termination.\n~12 m matches the median of Philippine hotel-BMS prior-project benchmarks for chiller-plant\nand boiler-room cabling\
    \ where the panel is sited at the room's wall and equipment is\narranged in two rows along the room's length.\n"
  carries_io_points: 12
  carries_point_ids:
  - P-00110
  - P-00111
  - P-00112
  - P-00113
  - P-00114
  - '...'
  notes: 12 I/O points carried, 16C cable; length 12 m (typical_range:plant_room_same_room)
- id: C0006
  from: BMS-PNL-CHWPLANT-2F
  to: CH-1 to CH-3 (BMS Contractor)
  equipment_class: Chiller (Package Water-Cooled)
  system: Chilled Water Plant
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 27
  conductor_count_required: 34
  conductor_count_specified: 34
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 14
  length_method: measured
  length_basis: EE Plan EE-09 (2F Power System Layout) chiller bay; calibrated against 7.5 m structural grid
  carries_io_points: 27
  carries_point_ids:
  - P-00001
  - P-00002
  - P-00003
  - P-00004
  - P-00005
  - '...'
  notes: 27 I/O points carried, 34C cable; length 14 m (measured)
- id: C0007
  from: BMS-PNL-CHWPLANT-2F
  to: CH-1 to CH-3 (ME Contractor)
  equipment_class: Chiller (Package Water-Cooled)
  system: Chilled Water Plant
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 54
  conductor_count_required: 62
  conductor_count_specified: 62
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: measured
  length_basis: EE-09 (2F)
  carries_io_points: 54
  carries_point_ids:
  - P-00028
  - P-00029
  - P-00030
  - P-00031
  - P-00032
  - '...'
  notes: 54 I/O points carried, 62C cable; length 12 m (measured)
- id: C0008
  from: BMS-PNL-CHWPLANT-2F
  to: CHW Supply & Return Main Header (BMS Contractor)
  equipment_class: CHW Supply Main Header
  system: Chilled Water Plant
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 6
    AO: 1
  conductor_count_required: 9
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 8
  length_method: measured
  length_basis: EE-09 (2F)
  carries_io_points: 7
  carries_point_ids:
  - P-00103
  - P-00104
  - P-00105
  - P-00106
  - P-00107
  - '...'
  notes: 7 I/O points carried, 12C cable; length 8 m (measured)
- id: C0009
  from: BMS-PNL-CHWPLANT-2F
  to: CHWP-1 to CHWP-3 (ME Contractor)
  equipment_class: Primary CHW Pump
  system: Chilled Water Plant
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 18
    DO: 3
  conductor_count_required: 24
  conductor_count_specified: 24
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 10
  length_method: measured
  length_basis: EE-09 (2F)
  carries_io_points: 21
  carries_point_ids:
  - P-00082
  - P-00083
  - P-00084
  - P-00085
  - P-00086
  - '...'
  notes: 21 I/O points carried, 24C cable; length 10 m (measured)
- id: C0010
  from: BMS-PNL-CT-RD
  to: CT-1 to CT-3 (BMS Contractor)
  equipment_class: Cooling Tower
  system: "Heat Rejection \u2014 Cooling Tower"
  location: RD
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 24
  conductor_count_required: 30
  conductor_count_specified: 30
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 18
  length_method: measured
  length_basis: EE Plan ECE-16 (Roof Deck Layout) calibrated against guestroom grid 7.5 m
  carries_io_points: 24
  carries_point_ids:
  - P-00584
  - P-00585
  - P-00586
  - P-00587
  - P-00588
  - '...'
  notes: 24 I/O points carried, 30C cable; length 18 m (measured)
- id: C0011
  from: BMS-PNL-CT-RD
  to: CT-1 to CT-3 (ME Contractor)
  equipment_class: Cooling Tower
  system: "Heat Rejection \u2014 Cooling Tower"
  location: RD
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 8
    DO: 3
  conductor_count_required: 12
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 16
  length_method: measured
  length_basis: ECE-16 (RD)
  carries_io_points: 11
  carries_point_ids:
  - P-00608
  - P-00609
  - P-00610
  - P-00611
  - P-00612
  - '...'
  notes: 11 I/O points carried, 12C cable; length 16 m (measured)
- id: C0012
  from: BMS-PNL-CASINO-2F
  to: "DOAS (Casino) \u2014 2 units (BMS Contractor)"
  equipment_class: DOAS Unit
  system: "Casino MVAC \u2014 Dedicated Outdoor Air"
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 16
    AO: 6
  conductor_count_required: 28
  conductor_count_specified: 28
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 26
  length_method: measured
  length_basis: "EE-09 (2F Power Layout) \u2014 casino zone, panel PPCAS-14 area"
  carries_io_points: 22
  carries_point_ids:
  - P-00504
  - P-00505
  - P-00506
  - P-00507
  - P-00508
  - '...'
  notes: 22 I/O points carried, 28C cable; length 26 m (measured)
- id: C0013
  from: BMS-PNL-CASINO-2F
  to: "DOAS (Casino) \u2014 2 units (ME Contractor)"
  equipment_class: DOAS Unit
  system: "Casino MVAC \u2014 Dedicated Outdoor Air"
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 4
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 24
  length_method: measured
  length_basis: EE-09 (2F)
  carries_io_points: 4
  carries_point_ids:
  - P-00526
  - P-00527
  - P-00528
  - P-00529
  notes: 4 I/O points carried, 6C cable; length 24 m (measured)
- id: C0014
  from: BMS-PNL-VENT-RD
  to: EF-RD.1/RD.2, EF-1 (ME Contractor)
  equipment_class: Exhaust Fan (General)
  system: General Ventilation
  location: RD
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 9
  conductor_count_required: 10
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 14
  length_method: measured
  length_basis: ECE-16 (RD)
  carries_io_points: 9
  carries_point_ids:
  - P-00473
  - P-00474
  - P-00475
  - P-00476
  - P-00477
  - '...'
  notes: 9 I/O points carried, 12C cable; length 14 m (measured)
- id: C0015
  from: BMS-PNL-PLUMBING-LG
  to: HW Supply & Return Header (LG) (BMS Contractor)
  equipment_class: CHW Supply Main Header
  system: "Plumbing \u2014 Sanitary Hot Water"
  location: LG
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 6
  conductor_count_required: 8
  conductor_count_specified: 8
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 10
  length_method: measured
  length_basis: LG plumbing area
  carries_io_points: 6
  carries_point_ids:
  - P-00284
  - P-00285
  - P-00286
  - P-00287
  - P-00288
  - '...'
  notes: 6 I/O points carried, 8C cable; length 10 m (measured)
- id: C0016
  from: BMS-PNL-PLUMBING-RD
  to: "HWT-HZ (\xD73) (BMS Contractor)"
  equipment_class: Calorifier (Hot Water Storage Tank)
  system: "Plumbing \u2014 Sanitary Hot Water"
  location: RD
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: measured
  length_basis: ECE-16 (RD) plumbing zone
  carries_io_points: 3
  carries_point_ids:
  - P-00281
  - P-00282
  - P-00283
  notes: 3 I/O points carried, 4C cable; length 12 m (measured)
- id: C0017
  from: BMS-PNL-PLUMBING-LG
  to: "HWT-LZ (\xD73) (BMS Contractor)"
  equipment_class: Calorifier (Hot Water Storage Tank)
  system: "Plumbing \u2014 Sanitary Hot Water"
  location: LG
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 3
  conductor_count_required: 4
  conductor_count_specified: 4
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 14
  length_method: measured
  length_basis: LG plumbing area
  carries_io_points: 3
  carries_point_ids:
  - P-00278
  - P-00279
  - P-00280
  notes: 3 I/O points carried, 4C cable; length 14 m (measured)
- id: C0018
  from: BMS-PNL-AHU-2F
  to: PAHU-0.1 (BMS Contractor)
  equipment_class: Precooled Air Handling Unit
  system: "Air Handling \u2014 Pre-cooled"
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 6
    AO: 2
  conductor_count_required: 10
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_same_room
  length_basis: "Plant-room equipment is typically within 5\u201315 m straight-line of its dedicated BMS field\npanel. Add ~2 m vertical for floor-mounted panel to ceiling tray, ~3 m horizontal to\nequipment,\
    \ ~2 m drop to terminations, ~3 m allowance for cornering and slack at termination.\n~12 m matches the median of Philippine hotel-BMS prior-project benchmarks for chiller-plant\nand boiler-room cabling\
    \ where the panel is sited at the room's wall and equipment is\narranged in two rows along the room's length.\n"
  carries_io_points: 8
  carries_point_ids:
  - P-00262
  - P-00263
  - P-00264
  - P-00265
  - P-00266
  - '...'
  notes: 8 I/O points carried, 12C cable; length 12 m (typical_range:plant_room_same_room)
- id: C0019
  from: BMS-PNL-AHU-2F
  to: PAHU-0.1 (ME Contractor)
  equipment_class: Precooled Air Handling Unit
  system: "Air Handling \u2014 Pre-cooled"
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 4
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_same_room
  length_basis: "Plant-room equipment is typically within 5\u201315 m straight-line of its dedicated BMS field\npanel. Add ~2 m vertical for floor-mounted panel to ceiling tray, ~3 m horizontal to\nequipment,\
    \ ~2 m drop to terminations, ~3 m allowance for cornering and slack at termination.\n~12 m matches the median of Philippine hotel-BMS prior-project benchmarks for chiller-plant\nand boiler-room cabling\
    \ where the panel is sited at the room's wall and equipment is\narranged in two rows along the room's length.\n"
  carries_io_points: 4
  carries_point_ids:
  - P-00270
  - P-00271
  - P-00272
  - P-00273
  notes: 4 I/O points carried, 6C cable; length 12 m (typical_range:plant_room_same_room)
- id: C0020
  from: BMS-PNL-AHU-RD
  to: "PAHU-RD (\xD72) (BMS Contractor)"
  equipment_class: Precooled Air Handling Unit
  system: "Air Handling \u2014 Pre-cooled (Roofdeck)"
  location: RD
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 4
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 14
  length_method: measured
  length_basis: ECE-16 (RD)
  carries_io_points: 4
  carries_point_ids:
  - P-00538
  - P-00539
  - P-00540
  - P-00541
  notes: 4 I/O points carried, 6C cable; length 14 m (measured)
- id: C0021
  from: BMS-PNL-AHU-RD
  to: "PAHU-RD (\xD72) (ME Contractor)"
  equipment_class: Precooled Air Handling Unit
  system: "Air Handling \u2014 Pre-cooled (Roofdeck)"
  location: RD
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 6
    DO: 2
  conductor_count_required: 9
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: measured
  length_basis: ECE-16 (RD)
  carries_io_points: 8
  carries_point_ids:
  - P-00542
  - P-00543
  - P-00544
  - P-00545
  - P-00546
  - '...'
  notes: 8 I/O points carried, 12C cable; length 12 m (measured)
- id: C0022
  from: BMS-PNL-PLUMBING-RD
  to: "RP-HZ (\xD73) (ME Contractor)"
  equipment_class: Recirculating Pump
  system: "Plumbing \u2014 Sanitary Hot Water"
  location: RD
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 9
  conductor_count_required: 10
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_same_room
  length_basis: "Plant-room equipment is typically within 5\u201315 m straight-line of its dedicated BMS field\npanel. Add ~2 m vertical for floor-mounted panel to ceiling tray, ~3 m horizontal to\nequipment,\
    \ ~2 m drop to terminations, ~3 m allowance for cornering and slack at termination.\n~12 m matches the median of Philippine hotel-BMS prior-project benchmarks for chiller-plant\nand boiler-room cabling\
    \ where the panel is sited at the room's wall and equipment is\narranged in two rows along the room's length.\n"
  carries_io_points: 9
  carries_point_ids:
  - P-00317
  - P-00318
  - P-00319
  - P-00320
  - P-00321
  - '...'
  notes: 9 I/O points carried, 12C cable; length 12 m (typical_range:plant_room_same_room)
- id: C0023
  from: BMS-PNL-PLUMBING-LG
  to: "RP-LZ (\xD73) (ME Contractor)"
  equipment_class: Recirculating Pump
  system: "Plumbing \u2014 Sanitary Hot Water"
  location: LG
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 9
  conductor_count_required: 10
  conductor_count_specified: 12
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: typical_range:plant_room_same_room
  length_basis: "Plant-room equipment is typically within 5\u201315 m straight-line of its dedicated BMS field\npanel. Add ~2 m vertical for floor-mounted panel to ceiling tray, ~3 m horizontal to\nequipment,\
    \ ~2 m drop to terminations, ~3 m allowance for cornering and slack at termination.\n~12 m matches the median of Philippine hotel-BMS prior-project benchmarks for chiller-plant\nand boiler-room cabling\
    \ where the panel is sited at the room's wall and equipment is\narranged in two rows along the room's length.\n"
  carries_io_points: 9
  carries_point_ids:
  - P-00308
  - P-00309
  - P-00310
  - P-00311
  - P-00312
  - '...'
  notes: 9 I/O points carried, 12C cable; length 12 m (typical_range:plant_room_same_room)
- id: C0024
  from: BMS-PNL-BOILER-LG
  to: SB-1 & SB-2 (BMS Contractor)
  equipment_class: Steam Boiler
  system: Boiler / Laundry
  location: LG
  cable_type: "4C \xD7 1.5 mm\xB2 shielded FRLS (BMS sensor signal)"
  spec_source: rule:bms_signal_default
  spec_basis: "Philippines BFP IRR mandates FRLS in hospitality occupancies; sensor-grade BMS analog signals universally specified at 1.5 mm\xB2 for distances under 200 m; shielding mandatory adjacent to\
    \ lighting/power tray runs."
  by_class:
    AI: 6
  conductor_count_required: 8
  conductor_count_specified: 8
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 12
  length_method: measured
  length_basis: EE-22 LG laundry-room load schedule cross-reference
  carries_io_points: 6
  carries_point_ids:
  - P-00482
  - P-00483
  - P-00484
  - P-00485
  - P-00486
  - '...'
  notes: 6 I/O points carried, 8C cable; length 12 m (measured)
- id: C0025
  from: BMS-PNL-BOILER-LG
  to: SB-1 & SB-2 (ME Contractor)
  equipment_class: Steam Boiler
  system: Boiler / Laundry
  location: LG
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 14
    DO: 2
  conductor_count_required: 18
  conductor_count_specified: 20
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 10
  length_method: measured
  length_basis: LG mech area
  carries_io_points: 16
  carries_point_ids:
  - P-00488
  - P-00489
  - P-00490
  - P-00491
  - P-00492
  - '...'
  notes: 16 I/O points carried, 20C cable; length 10 m (measured)
- id: C0026
  from: BMS-PNL-CASINO-2F
  to: Sanitizer for AHU-2M.1/2M.2 (Equipment Supplier)
  equipment_class: Ozone Generator (UV-light or Corona)
  system: "Casino MVAC \u2014 Smoke Sanitizer"
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 4
  conductor_count_required: 5
  conductor_count_specified: 6
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 28
  length_method: typical_range:casino_floor_field
  length_basis: "Casino MVAC zone (PPCAS-14 panel area + casino DOAS) is a compact mechanical-room\nadjacent to the casino floor. BMS-PNL-CASINO-2F sees DOAS, smoke sanitizer, and\nAHU-2M.1/2M.2 within\
    \ ~15\u201325 m + ~3 m vertical + ~5 m allowance. 28 m is the central\nvalue applied where the precise device location is not measurable from the EE Plan.\n"
  carries_io_points: 4
  carries_point_ids:
  - P-00534
  - P-00535
  - P-00536
  - P-00537
  notes: 4 I/O points carried, 6C cable; length 28 m (typical_range:casino_floor_field)
- id: C0027
  from: BMS-PNL-VENT-GF
  to: TEF-1.1 to 1.4 + EF-1.2A/LPG.1/1MR.1/1STO.1/MRF.1 (ME Contractor)
  equipment_class: Exhaust Fan (General)
  system: General Ventilation
  location: GF
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 27
  conductor_count_required: 31
  conductor_count_specified: 31
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:guestroom_corridor
  length_basis: "A typical guestroom-floor corridor is 30\u201350 m long. A BMS panel located mid-corridor or\nat a service core sees ~10\u201325 m to the farthest field device on that floor + ~5 m\nvertical\
    \ (panel-to-tray-to-device drop) + ~5 m termination & cornering allowance.\n35 m is the median for the BOH ventilation-fan cabling pattern.\n"
  carries_io_points: 27
  carries_point_ids:
  - P-00326
  - P-00327
  - P-00328
  - P-00329
  - P-00330
  - '...'
  notes: 27 I/O points carried, 31C cable; length 35 m (typical_range:guestroom_corridor)
- id: C0028
  from: BMS-PNL-VENT-2F
  to: TEF-2.1/2.3/2B.3 + EF-2B.1/2B.2/GS.1&GS.2 + EF-2.1 to 2.4 + EF-CHRx2 (ME Contractor)
  equipment_class: Exhaust Fan (General)
  system: General Ventilation
  location: 2F
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 39
  conductor_count_required: 45
  conductor_count_specified: 45
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:guestroom_corridor
  length_basis: "A typical guestroom-floor corridor is 30\u201350 m long. A BMS panel located mid-corridor or\nat a service core sees ~10\u201325 m to the farthest field device on that floor + ~5 m\nvertical\
    \ (panel-to-tray-to-device drop) + ~5 m termination & cornering allowance.\n35 m is the median for the BOH ventilation-fan cabling pattern.\n"
  carries_io_points: 39
  carries_point_ids:
  - P-00353
  - P-00354
  - P-00355
  - P-00356
  - P-00357
  - '...'
  notes: 39 I/O points carried, 45C cable; length 35 m (typical_range:guestroom_corridor)
- id: C0029
  from: BMS-PNL-VENT-3F
  to: TEF-3Ax2/3B/3Cx2/3Dx20 + others (ME Contractor)
  equipment_class: Exhaust Fan (General)
  system: General Ventilation
  location: 3F
  cable_type: "4C \xD7 1.5 mm\xB2 FRLS (equipment aux contacts \u2014 status / H-O-A / trip)"
  spec_source: rule:equipment_aux_default
  spec_basis: Equipment-supplier-routed dry-contact signals (status / H-O-A / trip) sit on the same FRLS jacket rating; shielding not required for DI-only signals; ME Contractor routes from MCC dry-contact.
  by_class:
    DI: 81
  conductor_count_required: 93
  conductor_count_specified: 93
  spare_basis: per-class spare strategy (ai_pct=25%, ao_pct=25%, di_pct=15%, do_pct=15%, hli_pct=0%)
  length_m: 35
  length_method: typical_range:guestroom_corridor
  length_basis: "A typical guestroom-floor corridor is 30\u201350 m long. A BMS panel located mid-corridor or\nat a service core sees ~10\u201325 m to the farthest field device on that floor + ~5 m\nvertical\
    \ (panel-to-tray-to-device drop) + ~5 m termination & cornering allowance.\n35 m is the median for the BOH ventilation-fan cabling pattern.\n"
  carries_io_points: 81
  carries_point_ids:
  - P-00392
  - P-00393
  - P-00394
  - P-00395
  - P-00396
  - '...'
  notes: 81 I/O points carried, 93C cable; length 35 m (typical_range:guestroom_corridor)
trunk_cables:
- id: T0030
  from: BMS Server Room (head-end)
  to: All BMS panels at 2nd Floor
  cable_type: "Cat6 4P \xD7 23 AWG U/UTP, FRLS jacket (BACnet/IP) \u2014 riser fiber + Cat6 trunk"
  length_m: 80
  notes: "Network trunk for 2nd Floor \u2014 fiber to floor switch + Cat6 distribution to floor's BMS panels"
- id: T0031
  from: BMS Server Room (head-end)
  to: BMS panel controllers (per topology id mstp_main_backbone)
  cable_type: "BACnet MS/TP shielded twisted-pair trunk, 1pr \xD7 22 AWG low-cap"
  length_m: 320
  length_method: measured
  length_basis: "Daisy-chain across the 13 BMS field panels. Path: Boiler-LG \u2192 Plumbing-LG \u2192 CHWPlant-2F \u2192 BOH-AHU-2F \u2192 AHU-2F \u2192 Casino-2F \u2192 Vent-GF \u2192 Vent-2F \u2192 Vent-3F\
    \ \u2192 Vent-RD \u2192 AHU-RD \u2192 CT-RD \u2192 Plumbing-RD. Routed via riser shaft per EE-24 + horizontal corridor tray on each floor (per ECE auxiliary plans)."
  notes: "Daisy-chain across the 13 BMS field panels. Path: Boiler-LG \u2192 Plumbing-LG \u2192 CHWPlant-2F \u2192 BOH-AHU-2F \u2192 AHU-2F \u2192 Casino-2F \u2192 Vent-GF \u2192 Vent-2F \u2192 Vent-3F\
    \ \u2192 Vent-RD \u2192 AHU-RD \u2192 CT-RD \u2192 Plumbing-RD. Routed via riser shaft per EE-24 + horizontal corridor tray on each floor (per ECE auxiliary plans)."
panel_power_feeds:
- id: P0032
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-AHU-2F \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0033
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-AHU-RD \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0034
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-BOHAHU-2F \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0035
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-BOILER-LG \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0036
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-CASINO-2F \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0037
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-CHWPLANT-2F \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0038
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-CT-RD \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0039
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-PLUMBING-LG \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0040
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-PLUMBING-RD \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0041
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-VENT-2F \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0042
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-VENT-3F \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0043
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-VENT-GF \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)
- id: P0044
  from: Local panelboard / EE-supplied feeder
  to: "BMS-PNL-VENT-RD \u2014 BMS panel 240V power feed"
  cable_type: "3C \xD7 2.5 mm\xB2 FRLS (240V single-phase BMS panel power feed)"
  length_m: 18
  length_method: typical_range:bms_panel_power_feed
  length_basis: "BMS field panels typically draw <100 W; their 240V supply is taken from the nearest\npanelboard (often on the same floor, often in the same electrical room). Typical\nrun includes: ~3 m\
    \ horizontal at panelboard end \u2192 ~6 m horizontal to BMS panel\narea \u2192 ~3 m vertical drop \u2192 ~6 m cornering, slack, and termination allowance.\n18 m balances the boiler-room (closer, ~12\
    \ m) and casino/AHU-zone (further, ~22 m) cases.\n"
  notes: 240V single-phase 16A circuit to BMS panel; UPS-backed where in scope (A7); length 18 m (typical_range:bms_panel_power_feed)