# 5.3 — Integrated Testing

Module: [bms/testing-commissioning](../../../_playbook/modules/bms/testing-commissioning.md)

Covers WBS leaves 5.3.1 (CHW plant), 5.3.2 (Casino MVAC), 5.3.3 (Hotel/Roofdeck), 5.3.4 (Plumbing/Boiler).

| Field | Value | Source |
|-------|-------|--------|
| Test groups | 4 integrated systems | WBS 5.3 |
| Methodology | Run-up from cold start; verify cross-equipment interlocks (chiller → CHWP → CDWP → CT; DOAS → AHU → exhaust) | Standard |
| Cross-discipline coordination | with ME contractor for water + air balancing prerequisites | C2 |
| Casino-zone access procedures | per A-013 / +5% production-rate modifier | B4 |
| Crew | 2 T&C engineers + 1 sr engineer, week 13 | D2 |