# 5.1 — Pre-commissioning (P2P)

Module: [bms/testing-commissioning](../../../_playbook/modules/bms/testing-commissioning.md)

| Field | Value | Source |
|-------|-------|--------|
| Test items | 601 (one per A1 point) | B3 |
| P2P scope | continuity from sensor/actuator → BMS panel → controller input | Standard |
| Crew | 2 T&C engineers, week 11 | D2 |
| Hours | ~152 / 19 person-days (B3 total) | B3 |