# 1.4 — Factory Acceptance Test

Module: [bms/project-management-engineering](../../../_playbook/modules/bms/project-management-engineering.md)

| Field | Value | Source |
|-------|-------|--------|
| FAT location | BMS contractor's facility (Manila) | Standard |
| FAT scope | Power-up of representative panels (sample 4 of 13); functional simulation of 1 of each system (chiller, AHU, DOAS, exhaust, calorifier, boiler) | Standard |
| Customer attendance | Megaworld APD + TUEC (consultant) | A-014 |
| Duration | 5 days | D1 |
| Outputs | FAT report, deficiency log | Standard |