# 02 — Classification

**Project:** Kingsford Hotel Bacolod — BMS
**Customer:** Megaworld Corporation (slug: `megaworld`; customer-kb entry: yes — STUB)
**Date:** 2026-04-28

## Discipline

- **Primary:** BMS (building management / automation — HVAC, ventilation, plumbing, electrical metering, integration)
- **Secondary:** none

## Stage

- **Greenfield (new construction)** — classified per technical evidence, despite cover letter wording.
- Cited evidence:
  - Cover letter: *"...Rehabilitation of Building Management System for the Kingsford Hotel Bacolod project."* (`Requirement.rtf`) — **weak signal**.
  - EE Plan cover letter: *"We issue the following construction bulletin to provide information on the 'For Construction' documents reflecting the electrical revisions due to the adjusted mechanical layout and the added power provisions for the kitchen layouts from Basement to 3rd floor."* (`EE Plan (TUEC).pdf` p.1, dated November 5, 2025, Construction Bulletin No.8) — **strong greenfield signal**.
  - BMS Points list and EE Plan are stamped Construction Bulletin (revision-controlled new-construction issuance).
  - **No existing-system inventory** present in the input bundle — strong greenfield signal.
- Per Phase-2 triangulation rule: **technical-document evidence governs**. Classify as Greenfield. Promote the wording mismatch to clarification (`Q-001` in Phase 8).

## Scope type

- [x] Supply
- [x] Delivery
- [x] Installation
- [x] Testing & Commissioning (explicitly named)
- [x] Programming / engineering (implicit in "Complete ... Commissioning of BMS")
- [ ] Training (not stated — flag in Phase 8)
- [ ] Maintenance / O&M after handover (not stated — flag)

## Facility type

- Hotel / Hospitality. Casino lobby provisions referenced in EE Plan (`PPCAS-14` panel relocated inside casino lobby per APD note). Apply **`bms-hospitality-casino`** overlay on top of `bms-greenfield` base checklist.

## Estimated tier

- **Medium** (provisional) — basis: project-specific BMS points list is 3 A1 pages (typical hotel-tower point density of 600–1,200 BMS points across ~22 floors); EE Plan covers Basement 1 → 3rd floor + load schedules + power riser (Part 1 of 2 for fire-pump scheme). Refine in Phase 5a after points-list extraction. Likely cost bracket PHP 25M–50M.

## Implications for later phases

- Required-doc checklist column: **`bms-greenfield`** with **`bms-hospitality-casino`** additive rows applied (`_playbook/checklists/required-docs-by-project-type.md`).
- Module catalog: `_playbook/modules/bms/`
- Stage-specific assumption set: greenfield assumptions (no demolition, no hot cutover, no existing-cable reuse).
- Brand selection: Megaworld customer-kb entry exists but is STUB — fall back to internal preferred (Siemens for BMS / PLC / FDAS / SCADA; Dell for PCs) and surface picks as assumptions for customer review.
- Special considerations:
  - Casino-floor specifics (CO sensors, smoke-zone exhaust, gaming-zone HVAC, vault) per `bms-hospitality-casino` checklist additive rows.
  - Cover-letter wording mismatch (rehab vs. greenfield) — open clarification.
  - No architectural / mechanical / plumbing layout drawings provided — drawing-availability triage will confirm scope of measurable vs. fallback-assumed cable runs.