# D1 — Project Schedule

**Project:** Kingsford Hotel Bacolod — BMS
**Date:** 2026-04-28
**Basis:** A-003 (16 weeks total). Pending Q-004 customer confirmation.

```mermaid
gantt
    title Kingsford Hotel Bacolod BMS — 16-week schedule
    dateFormat  YYYY-MM-DD
    axisFormat  W%V
    section Engineering
    Mobilization + kickoff      :m1, 2026-06-01, 1w
    Engineering & shop drawings :e1, after m1, 4w
    Submittals & approvals       :s1, after e1, 1w
    section Procurement
    Material RFQ + PO            :p1, after e1, 2w
    Material delivery            :p2, after p1, 4w
    section Installation
    Containment install          :i1, after s1, 4w
    Cable pulling + termination  :i2, after i1, 4w
    Panel install                :i3, after i2, 2w
    Device install               :i4, after i3, 3w
    Network + head-end install   :i5, after i4, 1w
    section Testing
    FAT @ Manila workshop        :f1, after p2, 2d
    Pre-comm + P2P               :t1, after i5, 2w
    Functional testing           :t2, after t1, 1w
    Integrated commissioning     :t3, after t2, 1w
    Owner SAT + handover         :h1, after t3, 1w
    section Training
    Operator training (5d)       :tr1, after t2, 1w
    Engineer training (3d)       :tr2, after tr1, 3d
    section Closeout
    As-built + commissioning report :ab1, after h1, 1w
    6-month refresher (later)    :rf1, 2026-12-15, 3d
```

| Phase | Weeks | Key deliverables |
|-------|-------|------------------|
| Engineering | 1–5 | Shop drawings, system architecture, sequences, programming spec, submittal package |
| Procurement | 5–10 | POs issued, materials delivered to site, FAT |
| Installation | 6–14 | Containment, cabling, panels, devices, network |
| Testing & Commissioning | 14–17 | P2P, functional, integrated, SAT |
| Training & Handover | 16–17 | Operator + engineer training, handover documentation |
| Refresher | Week 40 (post-handover) | 3-day refresher per A-033 |

**Total elapsed:** 16 weeks engagement + 6-month deferred refresher
**Critical path:** Engineering → Procurement → Installation → T&C — sequential per typical greenfield BMS project
**Float:** Engineering and procurement run partially in parallel; cable install can begin in week 6 once shop drawings approved