metadata:
  project: Kingsford Hotel Bacolod — BMS
  date: 2026-04-28
  source: A-028, A-029
  status: draft

# Per-project conduit + production modifiers (Op#11 — reasoned per project).

conduit_fraction_of_total_cable: 0.35
conduit_fraction_basis: |
  Greenfield hospitality + casino. Mechanical contractor provides cable
  tray in main runs (chiller plant, electrical risers, BOH corridors);
  BMS contractor installs conduit for last-leg drops to field devices,
  guestroom-corridor sensors, casino-floor MVAC sensors, and panel-room
  containment. Industry range 10-50%; greenfield+tray-supplied middle of
  range. Higher than helper's legacy 30% to reflect casino-floor
  separated conduit (regulatory) and per-room runs.
sources: ["RtRx prior Megaworld hospitality projects; BFP IRR + Megaworld MEP coordination practice"]

production_rate_modifier: 1.0
production_rate_modifier_basis: |
  Greenfield, daytime single shift, no occupied-building constraints.
  Standard production rates apply with no modifier.
sources: ["A-004 — daytime; A-001 greenfield"]

# Per-class device install rates (hours per device — overrides RATES default)
# Optional. Empty here; helper uses default 1.0 hr/device.
per_class_device_install_rates: {}