# B1 — Programming Object Inventory
#
metadata:
  project: "Kingsford Hotel Bacolod \u2014 BMS"
  generated_from: A1-io-list.yaml + A2-equipment-takeoff.yaml
  generator: _playbook/tools/generate-b1-b3-programming-and-commissioning.py
  rates:
    hrs_per_point_object: 0.1
    hrs_per_control_loop: 2.0
    hrs_per_alarm: 0.15
    hrs_per_trend: 0.1
    hrs_per_schedule: 0.5
    hrs_per_report: 1.5
summary:
  point_database_objects: 724
  control_loops: 48
  alarm_definitions: 78
  trend_logs: 519
  schedules: 8
  scheduled_reports: 10
  total_objects: 1387
programming_hours:
  point_database_setup: 72.4
  control_logic_per_equipment: 96.0
  alarms: 11.7
  schedules: 4.0
  reports: 15.0
  trends: 51.9
  total_programming_hours: 251.0
  person_days_at_8hr: 31.4
control_loop_inventory:
- equipment: AHU-2F-1
  equipment_class: AHU (Chilled-Water-Served)
  location: 2nd Floor BOH
- equipment: AHU-2M.1
  equipment_class: AHU (Modulating CHW-served)
  location: 2nd Floor Casino MVAC Room
- equipment: AHU-2M.2
  equipment_class: AHU (Modulating CHW-served)
  location: 2nd Floor Casino MVAC Room
- equipment: AHU-B1-1
  equipment_class: AHU (Chilled-Water-Served)
  location: Basement 1 BOH
- equipment: AHU-GF-1
  equipment_class: AHU (Chilled-Water-Served)
  location: Ground Floor BOH
- equipment: AHU-GFM-1
  equipment_class: AHU (Chilled-Water-Served)
  location: Ground Floor Mezzanine BOH
- equipment: BTU-1
  equipment_class: BTU Meter
  location: 2nd Level Mechanical Room
- equipment: BTU-2
  equipment_class: BTU Meter
  location: 2nd Level Mechanical Room
- equipment: BTU-3
  equipment_class: BTU Meter
  location: 2nd Level Mechanical Room
- equipment: BTU-4
  equipment_class: BTU Meter
  location: 2nd Level Mechanical Room
- equipment: BTU-5
  equipment_class: BTU Meter
  location: 2nd Level Mechanical Room
- equipment: CH-1
  equipment_class: Chiller (Package Water-Cooled)
  location: 2nd Level Mechanical Room
- equipment: CH-2
  equipment_class: Chiller (Package Water-Cooled)
  location: 2nd Level Mechanical Room
- equipment: CH-3
  equipment_class: Chiller (Package Water-Cooled)
  location: 2nd Level Mechanical Room
- equipment: CHW-BYPASS
  equipment_class: CHW Bypass Header
  location: 2nd Level Mechanical Room
- equipment: CT-1
  equipment_class: Cooling Tower
  location: Roof Deck Mechanical
- equipment: CT-2
  equipment_class: Cooling Tower
  location: Roof Deck Mechanical
- equipment: CT-3
  equipment_class: Cooling Tower
  location: Roof Deck Mechanical
- equipment: CWP-1
  equipment_class: Condenser Water Pump
  location: 2nd Level Mechanical Room
- equipment: CWP-2
  equipment_class: Condenser Water Pump
  location: 2nd Level Mechanical Room
- equipment: CWP-3
  equipment_class: Condenser Water Pump
  location: 2nd Level Mechanical Room
- equipment: DOAS-2F-CASINO
  equipment_class: DOAS Unit
  location: 2nd Floor Casino MVAC Room
- equipment: DOAS-RD1
  equipment_class: DOAS Unit
  location: Roof Deck Mechanical
- equipment: DOAS-RD2
  equipment_class: DOAS Unit
  location: Roof Deck Mechanical
- equipment: HP-HZ-1
  equipment_class: Heat Pump
  location: Roof Deck HW Plant
- equipment: HP-HZ-2
  equipment_class: Heat Pump
  location: Roof Deck HW Plant
- equipment: HP-HZ-3
  equipment_class: Heat Pump
  location: Roof Deck HW Plant
- equipment: HP-LZ-1
  equipment_class: Heat Pump
  location: Lower Ground HW Plant
- equipment: HP-LZ-2
  equipment_class: Heat Pump
  location: Lower Ground HW Plant
- equipment: HP-LZ-3
  equipment_class: Heat Pump
  location: Lower Ground HW Plant
- equipment: PAHU-01
  equipment_class: Precooled Air Handling Unit
  location: Roof Deck Mechanical
- equipment: PAHU-02
  equipment_class: Precooled Air Handling Unit
  location: Roof Deck Mechanical
- equipment: PAHU-03
  equipment_class: Precooled Air Handling Unit
  location: Roof Deck Mechanical
- equipment: PAHU-04
  equipment_class: Precooled Air Handling Unit
  location: Roof Deck Mechanical
- equipment: PAHU-05
  equipment_class: Precooled Air Handling Unit
  location: Roof Deck Mechanical
- equipment: PAHU-06
  equipment_class: Precooled Air Handling Unit
  location: Roof Deck Mechanical
- equipment: PAHU-07
  equipment_class: Precooled Air Handling Unit
  location: Roof Deck Mechanical
- equipment: PCHWP-1
  equipment_class: Primary CHW Pump
  location: 2nd Level Mechanical Room
- equipment: PCHWP-2
  equipment_class: Primary CHW Pump
  location: 2nd Level Mechanical Room
- equipment: PCHWP-3
  equipment_class: Primary CHW Pump
  location: 2nd Level Mechanical Room
- equipment: RP-HZ-1
  equipment_class: Recirculating Pump
  location: Roof Deck HW Plant
- equipment: RP-HZ-2
  equipment_class: Recirculating Pump
  location: Roof Deck HW Plant
- equipment: RP-HZ-3
  equipment_class: Recirculating Pump
  location: Roof Deck HW Plant
- equipment: RP-LZ-1
  equipment_class: Recirculating Pump
  location: Lower Ground HW Plant
- equipment: RP-LZ-2
  equipment_class: Recirculating Pump
  location: Lower Ground HW Plant
- equipment: RP-LZ-3
  equipment_class: Recirculating Pump
  location: Lower Ground HW Plant
- equipment: SB-1
  equipment_class: Steam Boiler
  location: Lower Ground Laundry
- equipment: SB-2
  equipment_class: Steam Boiler
  location: Lower Ground Laundry
notes:
- 'Point database objects: every AI/AO/DI/DO/HLI in A1 becomes one programmable point. 724 total.'
- 'Control loops: one per equipment with active control. 48 loops covering chillers, pumps, fans, AHU/DOAS, boilers.'
- 'Alarms: 1 per critical equipment + system-wide alarms (network down, server fail, UPS, etc.).'
- 'Trends: subset of points logged for historical analysis. Defaults: 100% AO/DO, 100% AI, 40% DI, 70% HLI.'
- 'Schedules: occupancy weekday/weekend/holiday + plant on/off + lighting + setbacks.'
- 'Reports: daily/weekly/monthly energy + runtime + alarm summary.'