# Instance: BMS Testing & Commissioning — Kingsford Hotel Bacolod

**WBS leaves served:** 5.1, 5.2, 5.3, 5.4, 5.5, 5.6
**Module ref:** `_playbook/modules/bms/testing-commissioning.md`

## Project-specific parameters

Per B3 commissioning point inventory:
- 762 test items, 323 hr T&C labor (40.4 person-days)
- Pre-comm + P2P: continuity / IO tagging / range / polarity / scaling
- Functional: per-equipment sequences from BMS-01 Description of Operations
- Integrated: chiller-CT-AHU coordination; casino IAQ (CO + DCV); HW LZ/HZ load sharing
- Owner SAT: week 17, customer-witnessed
- As-built drawings + commissioning report

## BOQ line items
Per BOQ under 5.x; 60 hr as-built + 30 hr commissioning report.

## Cross-references
B3, A1 BMS-01 Desc. of Operations; A-033; D1 weeks 14-17.