# Instance: BMS Project Management & Engineering — Kingsford Hotel Bacolod

**WBS leaves served:** 1.1, 1.3, 1.4, 3.1
**Module ref:** `_playbook/modules/bms/project-management-engineering.md`

## Project-specific parameters

- Project duration: 16 weeks (A-003); PM 1 FTE × 16 wk = 640 hr
- Mobilization: week 1 (80 hr per B4)
- FAT: 2 days at Manila workshop (A-034) — week 5; engineer support 40 hr
- Submittal stages: 3 per A-035

## BOQ line items
Per BOQ generator outputs under WBS 1.1 / 1.3 / 1.4. See `06-boq.yaml`.

## Cross-references
A-003, A-034, A-035; Q-004; D1, D2.