# 02 — Classification

**Project:** Kingsford Hotel Bacolod — BMS
**Customer:** Megaworld Corporation (slug: `megaworld`; customer-kb entry: yes — STUB, see D-003)
**Date:** 2026-04-28

## Discipline
- **Primary:** BMS
- **Secondary:** Power monitoring (energy submetering at major load centers per Megaworld MC Standards)

## Stage
- **Greenfield (new construction)** — see Decision D-002.
- Cited evidence:
  - Cover letter wording: *"...Rehabilitation of Building Management System..."* (weak evidence — single keyword)
  - Drawing evidence per pilot reads: TUEC-issued **Construction Bulletin** drawings (BMS Points list and EE Plan) — strong greenfield indicator (new-construction permits + design-revision pattern)
  - Absence of existing-system inventory in the input bundle — strong greenfield signal (a rehab would supply existing controller make / model / age and a site survey)
- Triangulation outcome: classify as Greenfield. Add Q-001 asking the customer to confirm the wording mismatch.

## Scope type
- [x] Supply
- [x] Installation
- [x] Programming
- [x] Testing & Commissioning
- [ ] Training (assumed in base scope unless customer indicates otherwise)
- [ ] Maintenance / O&M (not stated; assume separate post-handover engagement)

## Facility type
- Hotel + Casino (Kingsford brand under Megaworld portfolio)
- Bacolod City. **Casino MVAC scope confirmed** in BMS Points list page BMS-02: dedicated Casino DOAS at 2nd Level, Casino AHUs (AHU-2M.1 / AHU-2M.2), and casino-floor air ionizers. Classification key is therefore **`bms-hospitality-casino`** (not plain hotel).

## Estimated tier
- **Medium-Large** — Phase 3 extraction confirms approximately **600 physical + HLI points** plus **~70 network/BACnet/Modbus integrations** (chillers, VFDs, BTU meters). Hotel is a high-rise: Underground / B1 / GF / GFM / 2F + Mezzanine / 3F / 5F / 6-9F / 10-11F / 12F / Roof Deck. Project value range expected PHP 35–75M.

## Implications for later phases
- Required-doc checklist: **`bms-greenfield`** + **`bms-hospitality-casino`** add-on rows (CO sensors at return, casino-floor zoning, ionizer monitoring) per `_playbook/checklists/required-docs-by-project-type.md`
- Module catalog: `_playbook/modules/bms/` (controller-panel, head-end, network-infrastructure, field-devices-hvac, field-devices-power, field-devices-plumbing, cabling-and-containment, programming-engineering, testing-commissioning, training-handover, project-management-engineering)
- Greenfield-specific assumption set: standard MEP coordination sequencing; no demolition / cutover / cable-reuse rows
- Brand resolution: customer-kb Megaworld brand list is STUB → use internal preferred (Siemens BMS / Dell PCs) with brand confirmation as RFI Q-NNN. See D-003.
- Casino-specific rows (CO sensors at return ducts, gaming-floor zoning) do **not** apply unless Phase 3 surfaces casino content