# D1 — Project Schedule

**Project:** Kingsford Hotel Bacolod — BMS
**Date:** 2026-04-28
**Duration:** 16 weeks (PO → Handover)

```mermaid
gantt
title BMS — Kingsford Hotel Bacolod
dateFormat  YYYY-MM-DD
section PM & Engineering
PM mobilization               :a1, 2026-05-01, 5d
Engineering and design        :a2, after a1, 28d
Submittals and approvals      :a3, after a2, 14d
section Supply
Material PO and lead time     :b1, 2026-05-15, 35d
Factory Acceptance Test       :b2, after b1, 5d
section Installation
First-fix containment         :c1, 2026-06-15, 14d
Cable pulling                 :c2, after c1, 21d
Panel install                 :c3, after c2, 14d
Device install                :c4, after c3, 14d
Head-end install              :c5, 2026-07-01, 14d
section Programming and T&C
Programming                   :d1, after c3, 21d
Pre-comm and P2P              :d2, after c4, 10d
Functional and integrated     :d3, after d2, 14d
section Handover
Owner SAT                     :e1, after d3, 5d
Training and documentation    :e2, after e1, 5d
```

## Critical milestones

| Week | Milestone |
|------|-----------|
| 4 | Engineering submittals issued |
| 6 | Material PO closed; FAT prep |
| 9 | First-fix containment complete |
| 12 | Pre-commissioning starts |
| 15 | Owner SAT complete |
| 16 | Handover |