# C1 — Contractor / Owner-Supplied Matrix

**Project:** Kingsford Hotel Bacolod — BMS
**Generated from:** A1-io-list.yaml
**Generator:** `_playbook/tools/generate-c1-co-matrix.py`

This matrix shows, per equipment class, which **BMS-side field devices** are supplied by which party. It is the contractual-scope-boundary view derived from the points list `C/O` column.

Suppliers:
- **BMS Contractor** — we (the proposing party) supply
- **ME Contractor** — Mechanical contractor supplies (typically valves, dampers, motorized actuators)
- **EE Contractor** — Electrical contractor supplies (power metering related — varies by project)
- **Equipment Supplier** — Manufacturer / Equipment vendor supplies (auxiliary contacts on motors/pumps, native equipment data via BACnet/Modbus, VFDs)
- **Owner** — Customer / building owner supplies

---

## Overall Summary

| Supplier | Total BMS I/O Points | Share |
|----------|---------------------:|------:|
| Equipment Supplier | 328 | 59.2% |
| ME Contractor | 128 | 23.1% |
| BMS Contractor | 98 | 17.7% |
| **Total** | **554** | **100%** |

---

## Per-Equipment-Class Breakdown

### FCU (guestroom/zone, hardwired)  ·  90 units, 270 I/O points

**Instances:** FCU-2F.01, FCU-2F.02, FCU-2F.03, FCU-2F.04, FCU-2F.05, FCU-2F.06, FCU-2F.07, FCU-2F.08, FCU-2F.09, FCU-2F.10, FCU-2F.11, FCU-2F.12, FCU-2F.13, FCU-2F.14, FCU-2F.15, FCU-2F.16, FCU-2F.17, FCU-2F.18, FCU-2F.19, FCU-2F.20, FCU-2F.21, FCU-2F.22, FCU-2F.23, FCU-2F.24, FCU-2F.25, FCU-2F.26, FCU-2F.27, FCU-2F.28, FCU-2F.29, FCU-2F.30, FCU-3F.01, FCU-3F.02, FCU-3F.03, FCU-3F.04, FCU-3F.05, FCU-3F.06, FCU-3F.07, FCU-3F.08, FCU-3F.09, FCU-3F.10, FCU-3F.11, FCU-3F.12, FCU-3F.13, FCU-3F.14, FCU-3F.15, FCU-3F.16, FCU-3F.17, FCU-3F.18, FCU-3F.19, FCU-3F.20, FCU-3F.21, FCU-3F.22, FCU-3F.23, FCU-3F.24, FCU-3F.25, FCU-3F.26, FCU-3F.27, FCU-3F.28, FCU-3F.29, FCU-3F.30, FCU-GF.01, FCU-GF.02, FCU-GF.03, FCU-GF.04, FCU-GF.05, FCU-GF.06, FCU-GF.07, FCU-GF.08, FCU-GF.09, FCU-GF.10, FCU-GF.11, FCU-GF.12, FCU-GF.13, FCU-GF.14, FCU-GF.15, FCU-GF.16, FCU-GF.17, FCU-GF.18, FCU-GF.19, FCU-GF.20, FCU-GF.21, FCU-GF.22, FCU-GF.23, FCU-GF.24, FCU-GF.25, FCU-GF.26, FCU-GF.27, FCU-GF.28, FCU-GF.29, FCU-GF.30

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 180 | Auxiliary Contact (90×), Relay Output (90×) |
| ME Contractor | 90 | Valve Actuator (90×) |

### AHU (Chilled-Water-Served)  ·  6 units, 72 I/O points

**Instances:** AHU-AMEN-3F, AHU-BALL-2F, AHU-BOH-2F, AHU-BOH-BSMT, AHU-LOBBY-GF, AHU-REST-2F

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 24 | Temperature Sensor (12×), Humidity Sensor (6×), CO2 Sensor (6×) |
| Equipment Supplier | 24 | Auxiliary Contact (12×), VFD analog input (6×), VFD analog output (6×) |
| ME Contractor | 24 | Damper Actuator (12×), Electric Valve Actuator (6×), Position Feedback (6×) |

### DOAS Unit  ·  3 units, 63 I/O points

**Instances:** DOAS-2F, DOAS-GF, DOAS-RD

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 36 | Auxiliary Contact (18×), VFD analog input (6×), VFD analog output (6×), Temperature Sensor (3×), Humidity Sensor (3×) |
| BMS Contractor | 15 | Temperature Sensor (9×), Humidity Sensor (3×), Flow Sensor (3×) |
| ME Contractor | 12 | Damper Position Switch (3×), Damper Actuator (3×), Position Feedback (3×), Electric Valve Actuator (3×) |

### Cooling Tower  ·  3 units, 18 I/O points

**Instances:** CT-1, CT-2, CT-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 15 | Auxiliary Contact (9×), VFD analog input (3×), VFD analog output (3×) |
| BMS Contractor | 3 | Float Switch (3×) |

### Primary CHW Pump  ·  3 units, 15 I/O points

**Instances:** CHWP-1.1, CHWP-1.2, CHWP-1.3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 15 | Auxiliary Contact (9×), VFD BACnet card (6×) |

### Condenser Water Pump  ·  3 units, 12 I/O points

**Instances:** COWP-1, COWP-2, COWP-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 12 | Auxiliary Contact (9×), Relay Output (3×) |

### Exhaust Fan (General)  ·  4 units, 12 I/O points

**Instances:** EAS-2F, EAS-3F, EAS-BSMT, EAS-GF

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 12 | Auxiliary Contact (12×) |

### Recirculating Pump  ·  6 units, 12 I/O points

**Instances:** RP-1, RP-2, RP-3, RP-4, RP-5, RP-6

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 12 | Auxiliary Contact (12×) |

### Precooled Air Handling Unit  ·  1 unit, 10 I/O points

**Instances:** PAHU-RD

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 5 | Auxiliary Contact (2×), VFD analog input (1×), VFD analog output (1×), Damper Actuator (1×) |
| BMS Contractor | 3 | Temperature Sensor (2×), Flow Sensor (1×) |
| ME Contractor | 2 | Electric Valve Actuator (1×), Position Feedback (1×) |

### Multifunction Power Meter (Feeder)  ·  10 units, 10 I/O points

**Instances:** MTR-FDR-01, MTR-FDR-02, MTR-FDR-03, MTR-FDR-04, MTR-FDR-05, MTR-FDR-06, MTR-FDR-07, MTR-FDR-08, MTR-FDR-09, MTR-FDR-10

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 10 | Modbus Power Meter (10×) |

### Heat Pump  ·  3 units, 9 I/O points

**Instances:** HP-1, HP-2, HP-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 9 | Auxiliary Contact (9×) |

### Steam Boiler  ·  1 unit, 8 I/O points

**Instances:** SB-1

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 5 | Steam Pressure Sensor (high-T) (1×), Temperature Sensor (1×), High-Temperature Sensor (1×), Zirconia O2 Sensor (1×), Motorized Blowdown Valve (1×) |
| Equipment Supplier | 3 | Auxiliary Contact (3×) |

### BMS Network Drop  ·  8 units, 8 I/O points

**Instances:** NET-PNL-2F, NET-PNL-3F, NET-PNL-BOH-2F, NET-PNL-BSMT, NET-PNL-CHPLANT-GND, NET-PNL-GF, NET-PNL-HE-GF, NET-PNL-RD

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 8 | RJ45 + Cat6 to edge switch (8×) |

### Calorifier (Hot Water Storage Tank)  ·  6 units, 6 I/O points

**Instances:** CAL-1, CAL-2, CAL-3, CAL-4, CAL-5, CAL-6

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 6 | Temperature Sensor (6×) |

### Hot Water Header Set  ·  1 unit, 6 I/O points

**Instances:** HDR-HW

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 6 | Temperature Sensor (4×), Sensor (2×) |

### Chiller (Package Water-Cooled)  ·  3 units, 3 I/O points

**Instances:** CH-1, CH-2, CH-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 3 | BACnet IP card (3×) |

### CHW Supply Main Header  ·  1 unit, 3 I/O points

**Instances:** HDR-CHWS

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 3 | Temperature Sensor (3×) |

### CHW Return Main Header  ·  1 unit, 3 I/O points

**Instances:** HDR-CHWR

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 3 | Temperature Sensor (3×) |

### Condenser Water Header  ·  1 unit, 3 I/O points

**Instances:** HDR-COW

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 3 | Temperature Sensor (3×) |

### CHW Bypass Header  ·  1 unit, 3 I/O points

**Instances:** HDR-CHW-BP

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 3 | Differential Pressure Sensor (1×), Electric Valve Actuator (1×), Position Feedback (1×) |

### Multifunction Power Meter (Main)  ·  3 units, 3 I/O points

**Instances:** MTR-MAIN-1, MTR-MAIN-2, MTR-MAIN-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 3 | Modbus Power Meter (3×) |

### Primary CHW Pump (Standby)  ·  1 unit, 2 I/O points

**Instances:** CHWP-1.STBY

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 2 | Auxiliary Contact (2×) |

### Cooling Tower (Common)  ·  1 unit, 2 I/O points

**Instances:** CT-COMMON

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Outdoor Temperature Sensor (1×), Humidity Sensor (1×) |

### BTU Meter  ·  1 unit, 1 I/O points

**Instances:** BTU-CHWS-MAIN

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 1 | Ultrasonic BTU Meter (1×) |

---

## Notes for Proposal Inclusions/Exclusions

- BMS scope = BMS Contractor row(s) above. We supply these field devices, plus the BMS panels, controllers, network, head-end, programming, and T&C.
- Items marked **ME Contractor** or **Equipment Supplier** are **NOT in BMS supply scope** — they're supplied under Mechanical or Equipment contracts. BMS scope includes the *terminations* and *signal cables* to these devices, but not the devices themselves.
- This matrix feeds C3 (Inclusions / Exclusions / Clarifications) — the customer-facing summary of scope boundaries.