# B1 — Programming Object Inventory
#
metadata:
  project: "Kingsford Hotel Bacolod \u2014 BMS"
  generated_from: A1-io-list.yaml + A2-equipment-takeoff.yaml
  generator: _playbook/tools/generate-b1-b3-programming-and-commissioning.py
  rates:
    hrs_per_point_object: 0.1
    hrs_per_control_loop: 2.0
    hrs_per_alarm: 0.15
    hrs_per_trend: 0.1
    hrs_per_schedule: 0.5
    hrs_per_report: 1.5
summary:
  point_database_objects: 546
  control_loops: 35
  alarm_definitions: 65
  trend_logs: 397
  schedules: 8
  scheduled_reports: 10
  total_objects: 1061
programming_hours:
  point_database_setup: 54.6
  control_logic_per_equipment: 70.0
  alarms: 9.8
  schedules: 4.0
  reports: 15.0
  trends: 39.7
  total_programming_hours: 193.1
  person_days_at_8hr: 24.1
control_loop_inventory:
- equipment: AHU-AMEN-3F
  equipment_class: AHU (Chilled-Water-Served)
  location: 3F
- equipment: AHU-BALL-2F
  equipment_class: AHU (Chilled-Water-Served)
  location: 2F
- equipment: AHU-BOH-2F
  equipment_class: AHU (Chilled-Water-Served)
  location: 2F
- equipment: AHU-BOH-BSMT
  equipment_class: AHU (Chilled-Water-Served)
  location: Basement
- equipment: AHU-LOBBY-GF
  equipment_class: AHU (Chilled-Water-Served)
  location: GF
- equipment: AHU-REST-2F
  equipment_class: AHU (Chilled-Water-Served)
  location: 2F
- equipment: BTU-CHWS-MAIN
  equipment_class: BTU Meter
  location: Plant Room
- equipment: CH-1
  equipment_class: Chiller (Package Water-Cooled)
  location: Plant Room (Basement)
- equipment: CH-2
  equipment_class: Chiller (Package Water-Cooled)
  location: Plant Room (Basement)
- equipment: CH-3
  equipment_class: Chiller (Package Water-Cooled)
  location: Plant Room (Basement)
- equipment: CHWP-1.1
  equipment_class: Primary CHW Pump
  location: Plant Room
- equipment: CHWP-1.2
  equipment_class: Primary CHW Pump
  location: Plant Room
- equipment: CHWP-1.3
  equipment_class: Primary CHW Pump
  location: Plant Room
- equipment: CHWP-1.STBY
  equipment_class: Primary CHW Pump (Standby)
  location: Plant Room
- equipment: COWP-1
  equipment_class: Condenser Water Pump
  location: Plant Room
- equipment: COWP-2
  equipment_class: Condenser Water Pump
  location: Plant Room
- equipment: COWP-3
  equipment_class: Condenser Water Pump
  location: Plant Room
- equipment: CT-1
  equipment_class: Cooling Tower
  location: Roofdeck
- equipment: CT-2
  equipment_class: Cooling Tower
  location: Roofdeck
- equipment: CT-3
  equipment_class: Cooling Tower
  location: Roofdeck
- equipment: DOAS-2F
  equipment_class: DOAS Unit
  location: 2F
- equipment: DOAS-GF
  equipment_class: DOAS Unit
  location: GF
- equipment: DOAS-RD
  equipment_class: DOAS Unit
  location: Roofdeck
- equipment: HDR-CHW-BP
  equipment_class: CHW Bypass Header
  location: Plant Room
- equipment: HP-1
  equipment_class: Heat Pump
  location: Plant Room
- equipment: HP-2
  equipment_class: Heat Pump
  location: Plant Room
- equipment: HP-3
  equipment_class: Heat Pump
  location: Plant Room
- equipment: PAHU-RD
  equipment_class: Precooled Air Handling Unit
  location: Roofdeck
- equipment: RP-1
  equipment_class: Recirculating Pump
  location: Plant Room
- equipment: RP-2
  equipment_class: Recirculating Pump
  location: Plant Room
- equipment: RP-3
  equipment_class: Recirculating Pump
  location: Plant Room
- equipment: RP-4
  equipment_class: Recirculating Pump
  location: Plant Room
- equipment: RP-5
  equipment_class: Recirculating Pump
  location: Plant Room
- equipment: RP-6
  equipment_class: Recirculating Pump
  location: Plant Room
- equipment: SB-1
  equipment_class: Steam Boiler
  location: Basement
notes:
- 'Point database objects: every AI/AO/DI/DO/HLI in A1 becomes one programmable point. 546 total.'
- 'Control loops: one per equipment with active control. 35 loops covering chillers, pumps, fans, AHU/DOAS, boilers.'
- 'Alarms: 1 per critical equipment + system-wide alarms (network down, server fail, UPS, etc.).'
- 'Trends: subset of points logged for historical analysis. Defaults: 100% AO/DO, 100% AI, 40% DI, 70% HLI.'
- 'Schedules: occupancy weekday/weekend/holiday + plant on/off + lighting + setbacks.'
- 'Reports: daily/weekly/monthly energy + runtime + alarm summary.'