# 06 — Bill of Quantities (BOQ)

**Project:** Kingsford Hotel Bacolod — BMS (AB-Run-2)
**Currency:** PHP
**Total line items:** 86  ·  **RFQ-required:** 63 (73.3%)
**Generated:** by `_playbook/tools/generate-06-boq.py` from working docs A1–B4 + pricing defaults

## Pricing structure

- Base subtotal:        **PHP 13,609,435**
- Overhead & margin (20%): PHP 2,721,887
- Cost + overhead:      PHP 16,331,322
- Contingency (7.5%):    PHP 1,224,849
- Cost + contingency:   PHP 17,556,171
- VAT (12%):              PHP 2,106,741
- **Grand total:**      **PHP 19,662,912**

- *Optional items (7.x), priced separately:* PHP 0 (most TBD per Q-012/Q-015/Q-016)

## Section subtotals

| Section | Subtotal | % of base |
|---------|---------:|----------:|
| 1.0 | PHP 1,688,000 | 12.4% |
| 2.0 | PHP 10,204,670 | 75.0% |
| 3.0 | PHP 749,875 | 5.5% |
| 4.0 | PHP 490,160 | 3.6% |
| 5.0 | PHP 385,530 | 2.8% |
| 6.0 | PHP 91,200 | 0.7% |
| **Base total** | **PHP 13,609,435** | **100.0%** |

## Cost pool breakdown (base, excl. optional)

| Pool | Subtotal | % of base |
|------|---------:|----------:|
| Material | PHP 9,258,670 | 68.0% |
| Labor | PHP 3,184,765 | 23.4% |
| Service/Lot | PHP 1,166,000 | 8.6% |

## 1.0  Project Management & Engineering

| WBS | Description | Qty | Unit | Unit Price | Extended | Source | RFQ? |
|-----|-------------|----:|------|-----------:|---------:|--------|:----:|
| 1.1 | Project management (off-site, full duration, 16 weeks) | 640 | hr | PHP 1,500 | PHP 960,000 | D2 PM 1 FTE × 16 wk |  |
| 1.1 | Site mobilization (week 1) | 80 | hr | PHP 1,500 | PHP 120,000 | D1 + B4 mobilization |  |
| 1.2 | Engineering & design (system architecture, panel layouts, IO list, sequences, network) | 320 | hr | PHP 1,200 | PHP 384,000 | D2 engineering allocation |  |
| 1.3 | Submittals & approvals administration | 80 | hr | PHP 1,200 | PHP 96,000 | within engineering budget |  |
| 1.4 | Factory Acceptance Test (FAT) delivery | 1 | lot | PHP 80,000 | PHP 80,000 | D1 week 5 |  |
| 1.4 | FAT support hours (BMS engineer) | 40 | hr | PHP 1,200 | PHP 48,000 | D2 week 5 |  |
| | **Section 1.0 subtotal** | | | | **PHP 1,688,000** | | |

## 2.0  Material Supply

| WBS | Description | Qty | Unit | Unit Price | Extended | Source | RFQ? |
|-----|-------------|----:|------|-----------:|---------:|--------|:----:|
| 2.1.1 | BMS Server (Primary) — dual-CPU, 16+ GB RAM, redundant PSU | 1 | each | PHP 350,000 | PHP 350,000 | A6 HE-SVR-01 | ✓ |
| 2.1.1 | BMS Server (Standby, redundancy) | 1 | each | PHP 350,000 | PHP 350,000 | A6 HE-SVR-02 | ✓ |
| 2.1.2 | Operator Workstation | 2 | each | PHP 80,000 | PHP 160,000 | A6 HE-WS-01, HE-WS-02 | ✓ |
| 2.1.3 | Graphics PC + 55-inch Display | 1 | set | PHP 150,000 | PHP 150,000 | A6 HE-GFX-01 | ✓ |
| 2.1.4 | Head-End UPS (3 kVA, 30-min runtime) | 1 | each | PHP 90,000 | PHP 90,000 | A6 HE-UPS-01 | ✓ |
| 2.1.5 | Software licenses (server + 3 client + energy module + graphics editor) | 1 | lot | PHP 600,000 | PHP 600,000 | A6 HE-SW-* | ✓ |
| 2.1.6 | Server-room peripherals (KVM, console monitor, color laser printer, 19-inch rack) | 1 | lot | PHP 80,000 | PHP 80,000 | A6 HE-PRINTER, HE-RACK, HE-KVM, HE-MON | ✓ |
| 2.2.1 | Core managed L2/L3 switch (24-port + 4 SFP) | 1 | each | PHP 120,000 | PHP 120,000 | A5 SW-CORE | ✓ |
| 2.2.2 | Edge managed L2 switch (16-port + 2 SFP) | 3 | each | PHP 35,000 | PHP 105,000 | A5 SW-GND/2F/RD | ✓ |
| 2.2.2 | Edge managed L2 switch (8-port + 2 SFP) | 3 | each | PHP 18,000 | PHP 54,000 | A5 SW-LZ/3F/BSMT | ✓ |
| 2.2.3 | Riser fiber, OM3 multimode 6-strand armored | 300 | m | PHP 280 | PHP 84,000 | A5 | ✓ |
| 2.2.3 | Fiber transceivers (1G SX/LX, paired) | 14 | each | PHP 8,000 | PHP 112,000 | A5 | ✓ |
| 2.2.4 | IDF wall-mount enclosures (9U) | 6 | each | PHP 18,000 | PHP 108,000 | A5 | ✓ |
| 2.3.1+2.3.2+2.3.3+2.3.4 | BMS field cabinet (small, IP54 wall-mount) | 10 | each | PHP 40,000 | PHP 400,000 | A4 panels (small I/O) | ✓ |
| 2.3.1+2.3.2+2.3.3+2.3.4 | BMS field cabinet (medium, IP54 wall-mount) | 6 | each | PHP 80,000 | PHP 480,000 | A4 panels (medium I/O) | ✓ |
| 2.3.1+2.3.2+2.3.3+2.3.4 | BMS field cabinet (large, IP54 wall-mount) | 2 | each | PHP 150,000 | PHP 300,000 | A4 panels (large I/O) | ✓ |
| 2.3.5 | DDC controllers (incl. network gateway controllers) | 30 | each | PHP 90,000 | PHP 2,700,000 | A4 total_controllers | ✓ |
| 2.3.5 | AI input modules (16-channel) | 11 | each | PHP 40,000 | PHP 440,000 | 137 AI + 25% spare ÷ 16 | ✓ |
| 2.3.5 | AO output modules (16-channel) | 5 | each | PHP 45,000 | PHP 225,000 | 56 AO + 25% spare ÷ 16 | ✓ |
| 2.3.5 | DI input modules (32-channel) | 7 | each | PHP 30,000 | PHP 210,000 | 176 DI + 25% spare ÷ 32 | ✓ |
| 2.3.5 | DO output modules (16-channel) | 2 | each | PHP 35,000 | PHP 70,000 | 14 DO + 25% spare ÷ 16 | ✓ |
| 2.3.5 | 24VDC switching power supplies (5A, redundant for 6 critical panels) | 24 | each | PHP 8,000 | PHP 192,000 | 18 panels + 6 redundant | ✓ |
| 2.3.5 | Terminal blocks (push-in 2.5 mm²) | 900 | each | PHP 80 | PHP 72,000 | (716 I/O × 1.25) | ✓ |
| 2.3.5 | Surge protection (signal-level SPD) | 36 | each | PHP 5,000 | PHP 180,000 | 2 per panel × 18 | ✓ |
| 2.3.5 | Cable management hardware (DIN rail, ducts, ferrules) per panel | 18 | lot | PHP 8,000 | PHP 144,000 | per A4 panel | ✓ |
| 2.4.1 | Temperature sensor — immersion/thermowell (water-side) | 12 | each | PHP 4,500 | PHP 54,000 | A1 BMS-supplied immersion temps | ✓ |
| 2.4.1 | Temperature sensor — duct insertion | 50 | each | PHP 3,000 | PHP 150,000 | A1 BMS-supplied duct temps | ✓ |
| 2.4.1 | Temperature sensor — outdoor (weatherproof) | 1 | each | PHP 6,000 | PHP 6,000 | A1 ct-common.outside-air-temp | ✓ |
| 2.4.2 | Humidity sensor (duct/outdoor) | 24 | each | PHP 6,500 | PHP 156,000 | A1 BMS-supplied RH sensors | ✓ |
| 2.4.3 | Pressure sensor — water-side | 6 | each | PHP 8,000 | PHP 48,000 | A1 BMS-supplied pressure | ✓ |
| 2.4.3 | Differential pressure sensor (CHW header) | 1 | each | PHP 12,000 | PHP 12,000 | A1 hdr-chw-bp.diff-press | ✓ |
| 2.4.3 | Pressure sensor — duct static | 4 | each | PHP 8,000 | PHP 32,000 | A1 EAF static pressure | ✓ |
| 2.4.4 | Flow sensor — water (insertion) | 9 | each | PHP 25,000 | PHP 225,000 | A1 chiller branch flows | ✓ |
| 2.4.4 | BTU meter (ultrasonic, Modbus) | 1 | each | PHP 80,000 | PHP 80,000 | A1 BTU-CHWS-MAIN | ✓ |
| 2.4.5 | Modulating valve actuator (BMS-supplied for CHW bypass) | 1 | each | PHP 12,000 | PHP 12,000 | A1 hdr-chw-bp.iso-vlv-cmd | ✓ |
| 2.4.8 | CO2 sensor (duct return) | 5 | each | PHP 8,000 | PHP 40,000 | A1 return-air-co2 | ✓ |
| 2.4.8 | CO sensor (duct return, casino) | 2 | each | PHP 10,000 | PHP 20,000 | A1 return-air-co | ✓ |
| 2.4.8 | VOC sensor (ozonizer return) | 2 | each | PHP 12,000 | PHP 24,000 | A1 ozonizer voc | ✓ |
| 2.4 | Mounting brackets, thermowells, valve fittings | 1 | lot | PHP 2,000 | PHP 2,000 | per device count + 5% spare | ✓ |
| 2.5.1 | Tank temperature sensor (calorifiers) | 6 | each | PHP 3,500 | PHP 21,000 | A1 calorifier tank temps | ✓ |
| 2.5.2 | HW header temperature sensors (supply/return/MUCW) | 6 | each | PHP 4,500 | PHP 27,000 | A1 hdr-hw-* temps | ✓ |
| 2.5.3 | Pump aux-contact wiring kits (heat pumps + recirc pumps) | 12 | each | PHP 1,500 | PHP 18,000 | A1 HP + RP rows | ✓ |
| 2.5.4 | Boiler steam pressure sensor | 2 | each | PHP 12,000 | PHP 24,000 | A1 sb-*.steam-pressure | ✓ |
| 2.5.4 | Boiler feedwater temperature sensor | 2 | each | PHP 4,500 | PHP 9,000 | A1 sb-*.feedwater-temp | ✓ |
| 2.5.4 | Boiler fluegas temperature sensor (high-temp) | 2 | each | PHP 8,000 | PHP 16,000 | A1 sb-*.fluegas-temp | ✓ |
| 2.5.4 | Boiler fluegas O2 sensor (zirconia) | 2 | each | PHP 30,000 | PHP 60,000 | A1 sb-*.fluegas-o2 | ✓ |
| 2.5.4 | Boiler motorized blowdown valve (BMS-supplied actuator) | 2 | each | PHP 18,000 | PHP 36,000 | A1 sb-*.blowdown-vlv-cmd | ✓ |
| 2.6.1 | Multifunction power meter (Main switchgear class) | 3 | each | PHP 90,000 | PHP 270,000 | A1 MTR-MAIN-* | ✓ |
| 2.6.1 | Multifunction power meter (Sub-feeder class) | 10 | each | PHP 35,000 | PHP 350,000 | A1 MTR-FDR-* | ✓ |
| 2.6.2 | Current transformers (split-core, sized per ampacity) | 39 | each | PHP 4,000 | PHP 156,000 | 13 meters × 3 phases | ✓ |
| 2.6.4 | Modbus serial-to-IP gateway | 2 | each | PHP 25,000 | PHP 50,000 | 1 per switchgear group | ✓ |
| 2.6 | Modbus shielded TP cable | 300 | m | PHP 80 | PHP 24,000 | A3 ee_metering trunks | ✓ |
| 2.7.1 | 4C × 1.5 mm² shielded FRLS control/signal cable | 1720 | m | PHP 95 | PHP 163,400 | A3 field cables (BMS/ME/EQ-supplier) | ✓ |
| 2.7.1 | 6C × 1.5 mm² shielded FRLS (where conductor count > 4) | 149 | m | PHP 130 | PHP 19,370 | A3 field cables (wider runs) | ✓ |
| 2.7.2 | BACnet MS/TP shielded TP cable (low-cap) | 150 | m | PHP 90 | PHP 13,500 | A3 trunk | ✓ |
| 2.7.3 | Cat6 4P × 23 AWG U/UTP FRLS cable | 700 | m | PHP 90 | PHP 63,000 | A3 network drops + trunk | ✓ |
| 2.7.5 | Conduit (PVC HW 25 mm) | 849 | m | PHP 120 | PHP 101,880 | 30% of total cable length | ✓ |
| 2.7 | 3C × 2.5 mm² FRLS panel power feed cable | 232 | m | PHP 110 | PHP 25,520 | A3 panel power feeds | ✓ |
| 2.7.6 | Cable identification (labels, ferrules, marker tags) — full project lot | 1 | lot | PHP 30,000 | PHP 30,000 | per cable count | ✓ |
| 2.7.5 | Cable management (junction boxes, cable ties) per panel field | 18 | lot | PHP 5,000 | PHP 90,000 | per panel | ✓ |
| | **Section 2.0 subtotal** | | | | **PHP 10,204,670** | | |

## 3.0  Installation

| WBS | Description | Qty | Unit | Unit Price | Extended | Source | RFQ? |
|-----|-------------|----:|------|-----------:|---------:|--------|:----:|
| 3.0 | Installation labor — Wireman / Electrician (cable pulling, conduit, panel install, terminations) | 932.9 | hr | PHP 350 | PHP 326,515 | B4 total 1435.2 hr × 65% trade split |  |
| 3.0 | Installation labor — BMS Technician (testing, pre-comm) | 358.8 | hr | PHP 700 | PHP 251,160 | B4 total 1435.2 hr × 25% |  |
| 3.0 | Installation labor — Engineer / Supervisor (oversight, fault resolution) | 143.5 | hr | PHP 1,200 | PHP 172,200 | B4 total 1435.2 hr × 10% |  |
| | **Section 3.0 subtotal** | | | | **PHP 749,875** | | |

## 4.0  Programming & Configuration

| WBS | Description | Qty | Unit | Unit Price | Extended | Source | RFQ? |
|-----|-------------|----:|------|-----------:|---------:|--------|:----:|
| 4.1 | Controller programming (point database, control loops, schedules, alarms, reports, trends) | 173.8 | hr | PHP 1,200 | PHP 208,560 | B1 programming hours |  |
| 4.2 | Graphics development (35 pages: navigation, floor, system, popups, alarm, trend, reports) | 256 | hr | PHP 1,100 | PHP 281,600 | B2 graphics hours |  |
| | **Section 4.0 subtotal** | | | | **PHP 490,160** | | |

## 5.0  Testing & Commissioning

| WBS | Description | Qty | Unit | Unit Price | Extended | Source | RFQ? |
|-----|-------------|----:|------|-----------:|---------:|--------|:----:|
| 5.1 | Pre-commissioning (cable continuity, megger, panel power-up smoke test) — covered in B4 | 0 | lot | PHP 0 | PHP 0 | B4 covered |  |
| 5.2 | Point-to-point (P2P) testing | 57.4 | hr | PHP 700 | PHP 40,180 | B3 h_p2p |  |
| 5.3 | Functional testing per equipment | 88.5 | hr | PHP 700 | PHP 61,950 | B3 h_functional |  |
| 5.4 | Integrated commissioning (cross-system sequences, energy savings) | 32 | hr | PHP 1,200 | PHP 38,400 | B3 h_integrated |  |
| 5.5 | Owner T&C / SAT support (1 week) | 40 | hr | PHP 1,200 | PHP 48,000 | D2 SAT week |  |
| 5.6 | Snagging / punch-list resolution | 30 | hr | PHP 700 | PHP 21,000 | typical for medium project |  |
| 5.7 | As-built documentation package (drawings, O&M, point database, programming archive) | 1 | lot | PHP 80,000 | PHP 80,000 | D2 docs allocation |  |
| 5.7 | As-built documentation engineer hours | 80 | hr | PHP 1,200 | PHP 96,000 | D2 docs allocation |  |
| | **Section 5.0 subtotal** | | | | **PHP 385,530** | | |

## 6.0  Training & Handover

| WBS | Description | Qty | Unit | Unit Price | Extended | Source | RFQ? |
|-----|-------------|----:|------|-----------:|---------:|--------|:----:|
| 6.1 | Operator training — on-site, 16 hours over 2 days, up to 6 operators | 1 | lot | PHP 60,000 | PHP 60,000 | A-013 (default) |  |
| 6.1 | Training delivery hours (1 trainer × 16 hr) | 16 | hr | PHP 1,200 | PHP 19,200 | trainer time |  |
| 6.3 | Documentation handover (formal, with sign-off) | 8 | hr | PHP 1,500 | PHP 12,000 | week 16 |  |
| | **Section 6.0 subtotal** | | | | **PHP 91,200** | | |

## 7.0  Optional / Out-of-scope

| WBS | Description | Qty | Unit | Unit Price | Extended | Source | RFQ? |
|-----|-------------|----:|------|-----------:|---------:|--------|:----:|
| 7.1 | [OPTION] 1-year preventive maintenance contract (post-warranty) | 1 | yr | PHP 0 | PHP 0 | Q-016 dependent — quote separately | ✓ |
| 7.2 | [OPTION] Additional administrator training (8 hr session) | 0 | lot | PHP 30,000 | PHP 0 | Q-015 dependent |  |
| 7.3 | [OPTION] FDAS integration (BACnet/Modbus from fire panel + smoke control sequences) | 0 | lot | PHP 0 | PHP 0 | Q-012 dependent — TBD | ✓ |
| 7.4 | [OPTION] PMS integration (guestroom occupancy → BMS for FCU control) | 0 | lot | PHP 0 | PHP 0 | Q-012 dependent — TBD | ✓ |
| | **Section 7.0 subtotal** | | | | **PHP 0** | | |

## Open items requiring Phase 9 RFQ resolution

63 of 86 line items currently use placeholder rates and require supplier quotes:

| WBS | Description | Qty | Unit | Placeholder Rate |
|-----|-------------|----:|------|-----------------:|
| 2.1.1 | BMS Server (Primary) — dual-CPU, 16+ GB RAM, redundant PSU | 1 | each | PHP 350,000 |
| 2.1.1 | BMS Server (Standby, redundancy) | 1 | each | PHP 350,000 |
| 2.1.2 | Operator Workstation | 2 | each | PHP 80,000 |
| 2.1.3 | Graphics PC + 55-inch Display | 1 | set | PHP 150,000 |
| 2.1.4 | Head-End UPS (3 kVA, 30-min runtime) | 1 | each | PHP 90,000 |
| 2.1.5 | Software licenses (server + 3 client + energy module + graphics editor) | 1 | lot | PHP 600,000 |
| 2.1.6 | Server-room peripherals (KVM, console monitor, color laser printer, 19-inch rack) | 1 | lot | PHP 80,000 |
| 2.2.1 | Core managed L2/L3 switch (24-port + 4 SFP) | 1 | each | PHP 120,000 |
| 2.2.2 | Edge managed L2 switch (16-port + 2 SFP) | 3 | each | PHP 35,000 |
| 2.2.2 | Edge managed L2 switch (8-port + 2 SFP) | 3 | each | PHP 18,000 |
| 2.2.3 | Riser fiber, OM3 multimode 6-strand armored | 300 | m | PHP 280 |
| 2.2.3 | Fiber transceivers (1G SX/LX, paired) | 14 | each | PHP 8,000 |
| 2.2.4 | IDF wall-mount enclosures (9U) | 6 | each | PHP 18,000 |
| 2.3.1+2.3.2+2.3.3+2.3.4 | BMS field cabinet (small, IP54 wall-mount) | 10 | each | PHP 40,000 |
| 2.3.1+2.3.2+2.3.3+2.3.4 | BMS field cabinet (medium, IP54 wall-mount) | 6 | each | PHP 80,000 |
| 2.3.1+2.3.2+2.3.3+2.3.4 | BMS field cabinet (large, IP54 wall-mount) | 2 | each | PHP 150,000 |
| 2.3.5 | DDC controllers (incl. network gateway controllers) | 30 | each | PHP 90,000 |
| 2.3.5 | AI input modules (16-channel) | 11 | each | PHP 40,000 |
| 2.3.5 | AO output modules (16-channel) | 5 | each | PHP 45,000 |
| 2.3.5 | DI input modules (32-channel) | 7 | each | PHP 30,000 |
| 2.3.5 | DO output modules (16-channel) | 2 | each | PHP 35,000 |
| 2.3.5 | 24VDC switching power supplies (5A, redundant for 6 critical panels) | 24 | each | PHP 8,000 |
| 2.3.5 | Terminal blocks (push-in 2.5 mm²) | 900 | each | PHP 80 |
| 2.3.5 | Surge protection (signal-level SPD) | 36 | each | PHP 5,000 |
| 2.3.5 | Cable management hardware (DIN rail, ducts, ferrules) per panel | 18 | lot | PHP 8,000 |
| 2.4.1 | Temperature sensor — immersion/thermowell (water-side) | 12 | each | PHP 4,500 |
| 2.4.1 | Temperature sensor — duct insertion | 50 | each | PHP 3,000 |
| 2.4.1 | Temperature sensor — outdoor (weatherproof) | 1 | each | PHP 6,000 |
| 2.4.2 | Humidity sensor (duct/outdoor) | 24 | each | PHP 6,500 |
| 2.4.3 | Pressure sensor — water-side | 6 | each | PHP 8,000 |
| 2.4.3 | Differential pressure sensor (CHW header) | 1 | each | PHP 12,000 |
| 2.4.3 | Pressure sensor — duct static | 4 | each | PHP 8,000 |
| 2.4.4 | Flow sensor — water (insertion) | 9 | each | PHP 25,000 |
| 2.4.4 | BTU meter (ultrasonic, Modbus) | 1 | each | PHP 80,000 |
| 2.4.5 | Modulating valve actuator (BMS-supplied for CHW bypass) | 1 | each | PHP 12,000 |
| 2.4.8 | CO2 sensor (duct return) | 5 | each | PHP 8,000 |
| 2.4.8 | CO sensor (duct return, casino) | 2 | each | PHP 10,000 |
| 2.4.8 | VOC sensor (ozonizer return) | 2 | each | PHP 12,000 |
| 2.4 | Mounting brackets, thermowells, valve fittings | 1 | lot | PHP 2,000 |
| 2.5.1 | Tank temperature sensor (calorifiers) | 6 | each | PHP 3,500 |
| 2.5.2 | HW header temperature sensors (supply/return/MUCW) | 6 | each | PHP 4,500 |
| 2.5.3 | Pump aux-contact wiring kits (heat pumps + recirc pumps) | 12 | each | PHP 1,500 |
| 2.5.4 | Boiler steam pressure sensor | 2 | each | PHP 12,000 |
| 2.5.4 | Boiler feedwater temperature sensor | 2 | each | PHP 4,500 |
| 2.5.4 | Boiler fluegas temperature sensor (high-temp) | 2 | each | PHP 8,000 |
| 2.5.4 | Boiler fluegas O2 sensor (zirconia) | 2 | each | PHP 30,000 |
| 2.5.4 | Boiler motorized blowdown valve (BMS-supplied actuator) | 2 | each | PHP 18,000 |
| 2.6.1 | Multifunction power meter (Main switchgear class) | 3 | each | PHP 90,000 |
| 2.6.1 | Multifunction power meter (Sub-feeder class) | 10 | each | PHP 35,000 |
| 2.6.2 | Current transformers (split-core, sized per ampacity) | 39 | each | PHP 4,000 |
| 2.6.4 | Modbus serial-to-IP gateway | 2 | each | PHP 25,000 |
| 2.6 | Modbus shielded TP cable | 300 | m | PHP 80 |
| 2.7.1 | 4C × 1.5 mm² shielded FRLS control/signal cable | 1720 | m | PHP 95 |
| 2.7.1 | 6C × 1.5 mm² shielded FRLS (where conductor count > 4) | 149 | m | PHP 130 |
| 2.7.2 | BACnet MS/TP shielded TP cable (low-cap) | 150 | m | PHP 90 |
| 2.7.3 | Cat6 4P × 23 AWG U/UTP FRLS cable | 700 | m | PHP 90 |
| 2.7.5 | Conduit (PVC HW 25 mm) | 849 | m | PHP 120 |
| 2.7 | 3C × 2.5 mm² FRLS panel power feed cable | 232 | m | PHP 110 |
| 2.7.6 | Cable identification (labels, ferrules, marker tags) — full project lot | 1 | lot | PHP 30,000 |
| 2.7.5 | Cable management (junction boxes, cable ties) per panel field | 18 | lot | PHP 5,000 |
| 7.1 | [OPTION] 1-year preventive maintenance contract (post-warranty) | 1 | yr | PHP 0 |
| 7.3 | [OPTION] FDAS integration (BACnet/Modbus from fire panel + smoke control sequences) | 0 | lot | PHP 0 |
| 7.4 | [OPTION] PMS integration (guestroom occupancy → BMS for FCU control) | 0 | lot | PHP 0 |

These items will be re-priced after Phase 9 supplier RFQ responses.