# C1 — Contractor / Owner-Supplied Matrix

**Project:** Kingsford Hotel Bacolod — BMS (AB-Run-2)
**Generated from:** A1-io-list.yaml
**Generator:** `_playbook/tools/generate-c1-co-matrix.py`

This matrix shows, per equipment class, which **BMS-side field devices** are supplied by which party. It is the contractual-scope-boundary view derived from the points list `C/O` column.

Suppliers:
- **BMS Contractor** — we (the proposing party) supply
- **ME Contractor** — Mechanical contractor supplies (typically valves, dampers, motorized actuators)
- **EE Contractor** — Electrical contractor supplies (power metering related — varies by project)
- **Equipment Supplier** — Manufacturer / Equipment vendor supplies (auxiliary contacts on motors/pumps, native equipment data via BACnet/Modbus, VFDs)
- **Owner** — Customer / building owner supplies

---

## Overall Summary

| Supplier | Total BMS I/O Points | Share |
|----------|---------------------:|------:|
| Equipment Supplier | 253 | 53.4% |
| BMS Contractor | 165 | 34.8% |
| ME Contractor | 56 | 11.8% |
| **Total** | **474** | **100%** |

---

## Per-Equipment-Class Breakdown

### DOAS Unit  ·  3 units, 72 I/O points

**Instances:** DOAS-2F, DOAS-RD1, DOAS-RD2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 42 | Auxiliary Contact (24×), VFD (12×), Temperature Sensor (3×), Humidity Sensor (3×) |
| BMS Contractor | 18 | Temperature Sensor (9×), Humidity Sensor (6×), Flow Sensor (3×) |
| ME Contractor | 12 | Damper Controller (6×), Electric Valve Actuator (6×) |

### AHU (Chilled-Water-Served)  ·  5 units, 70 I/O points

**Instances:** AHU-2F-A, AHU-2F-B, AHU-3F-AM, AHU-GF-LOB, AHU-GF-REST

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 30 | Damper Controller (10×), Auxiliary Contact (10×), VFD (10×) |
| BMS Contractor | 20 | Temperature Sensor (15×), CO2 Sensor (5×) |
| ME Contractor | 20 | Damper Controller (10×), Electric Valve Actuator (10×) |

### Chiller (Package Water-Cooled)  ·  2 units, 56 I/O points

**Instances:** CH-1, CH-2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 38 | Chiller Native (36×), Chiller Native BACnet IP (2×) |
| BMS Contractor | 14 | Temperature Sensor (8×), Flow Sensor (6×) |
| ME Contractor | 4 | Electric Valve Actuator (4×) |

### AHU (Modulating CHW-served)  ·  3 units, 42 I/O points

**Instances:** AHU-CASINO-1, AHU-CASINO-2, AHU-GF-CASINO

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 18 | Damper Controller (6×), Auxiliary Contact (6×), VFD (6×) |
| BMS Contractor | 12 | Temperature Sensor (6×), CO/CO2 Sensor (3×), VOC Sensor (3×) |
| ME Contractor | 12 | Damper Controller (6×), Electric Valve Actuator (6×) |

### Multifunction Power Meter (Feeder)  ·  8 units, 40 I/O points

**Instances:** PM-AIR-2F, PM-AIR-GF, PM-BOILER, PM-CASINO, PM-CHILLER, PM-COOLING, PM-FIREPMP, PM-PLUMB

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 40 | Modbus Power Meter (40×) |

### Precooled Air Handling Unit  ·  3 units, 36 I/O points

**Instances:** PAHU-2F, PAHU-BSMT, PAHU-ROOF

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 21 | Auxiliary Contact (9×), Damper Controller (6×), VFD (6×) |
| BMS Contractor | 9 | Temperature Sensor (6×), Flow Sensor (3×) |
| ME Contractor | 6 | Electric Valve Actuator (6×) |

### Steam Boiler  ·  2 units, 32 I/O points

**Instances:** BLR-1, BLR-2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 20 | Auxiliary Contact (16×), Level Sensor (4×) |
| BMS Contractor | 12 | Temperature Sensor (4×), Electric Valve Actuator (4×), Pressure Sensor (2×), Oxygen Sensor (2×) |

### Exhaust Fan (General)  ·  5 units, 15 I/O points

**Instances:** EAS-GEN-2F, EAS-GEN-3F, EAS-GEN-BSMT, EAS-GEN-GF, EAS-GEN-ROOF

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 15 | Auxiliary Contact (15×) |

### Primary CHW Pump  ·  2 units, 14 I/O points

**Instances:** CHWP-1, CHWP-2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 14 | Auxiliary Contact (8×), VFD (4×), Pressure Sensor (2×) |

### Cooling Tower  ·  2 units, 14 I/O points

**Instances:** CT-1, CT-2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 8 | Level Sensor / Electrode (4×), Electric Valve Actuator (4×) |
| Equipment Supplier | 6 | Auxiliary Contact (6×) |

### Condenser Water Pump  ·  3 units, 12 I/O points

**Instances:** CWP-1, CWP-2, CWP-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 12 | Auxiliary Contact (12×) |

### Exhaust Fan (Toilet)  ·  4 units, 12 I/O points

**Instances:** EAS-TOILET-2F, EAS-TOILET-3F, EAS-TOILET-BSMT, EAS-TOILET-GF

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 12 | Auxiliary Contact (12×) |

### Recirculating Pump  ·  3 units, 9 I/O points

**Instances:** HW-PUMP-LG-1, HW-PUMP-LG-2, HW-PUMP-ROOF-1

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 9 | Auxiliary Contact (9×) |

### Multifunction Power Meter (Main)  ·  1 unit, 8 I/O points

**Instances:** PM-MAIN-LG

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 8 | Modbus Power Meter (8×) |

### Primary CHW Pump (Standby)  ·  1 unit, 7 I/O points

**Instances:** CHWP-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 7 | Auxiliary Contact (4×), VFD (2×), Pressure Sensor (1×) |

### Cooling Tower (Common)  ·  1 unit, 6 I/O points

**Instances:** CT-COMMON

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 4 | Temperature Sensor (3×), Humidity Sensor (1×) |
| ME Contractor | 2 | pH Sensor / Conductivity Sensor (1×), Electric Valve Actuator (1×) |

### Heat Pump  ·  2 units, 6 I/O points

**Instances:** HP-LG-1, HP-ROOF-1

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 6 | Auxiliary Contact (6×) |

### BTU Meter  ·  1 unit, 5 I/O points

**Instances:** BTU-CHW-MAIN

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 5 | Modbus BTU Meter (5×) |

### CHW Bypass Header  ·  1 unit, 4 I/O points

**Instances:** CHW-BYP

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 4 | Electric Valve Actuator (2×), Diff. Pressure Sensor (1×), Diff. Temp Sensor (1×) |

### Ozone Generator (UV-light or Corona)  ·  1 unit, 3 I/O points

**Instances:** OZ-CASINO-1

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 3 | Auxiliary Contact (3×) |

### Hot Water Header Set  ·  1 unit, 3 I/O points

**Instances:** HW-HEADERS-LG

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 3 | Temperature Sensor (3×) |

### CHW Supply Main Header  ·  1 unit, 2 I/O points

**Instances:** CHW-SUP-HDR

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (1×), Pressure Sensor (1×) |

### CHW Return Main Header  ·  1 unit, 2 I/O points

**Instances:** CHW-RET-HDR

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (1×), Pressure Sensor (1×) |

### Condenser Water Header  ·  1 unit, 2 I/O points

**Instances:** CW-HDR

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (2×) |

### Calorifier (Hot Water Storage Tank)  ·  2 units, 2 I/O points

**Instances:** CALOR-LG, CALOR-ROOF

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (2×) |

---

## Notes for Proposal Inclusions/Exclusions

- BMS scope = BMS Contractor row(s) above. We supply these field devices, plus the BMS panels, controllers, network, head-end, programming, and T&C.
- Items marked **ME Contractor** or **Equipment Supplier** are **NOT in BMS supply scope** — they're supplied under Mechanical or Equipment contracts. BMS scope includes the *terminations* and *signal cables* to these devices, but not the devices themselves.
- This matrix feeds C3 (Inclusions / Exclusions / Clarifications) — the customer-facing summary of scope boundaries.