# B3 — Commissioning Point Inventory
#
metadata:
  project: "Kingsford Hotel Bacolod \u2014 BMS (AB-Run-2)"
  generated_from: A1-io-list.yaml + A2-equipment-takeoff.yaml
  generator: _playbook/tools/generate-b1-b3-programming-and-commissioning.py
  rates:
    hrs_per_p2p_point: 0.15
    hrs_per_functional_test: 1.5
    hrs_per_integrated_test: 4.0
summary:
  p2p_points: 383
  functional_tests: 59
  integrated_tests: 8
  total_test_items: 450
tc_hours:
  point_to_point: 57.4
  functional_per_equipment: 88.5
  integrated_sequences: 32.0
  total_tc_hours: 177.9
  person_days_at_8hr: 22.2
p2p_breakdown_by_panel:
  PNL-AIR-ROOF: 70
  PNL-AIR-2F: 70
  PNL-CH-PLANT-2F: 59
  PNL-CASINO-GF: 45
  PNL-AIR-GF: 34
  PNL-BLR-LG: 32
  PNL-CT-ROOF: 22
  PNL-AIR-3F: 20
  PNL-AIR-BSMT: 18
  PNL-PL-LG: 13
functional_test_inventory:
- equipment: AHU-2F-A
  equipment_class: AHU (Chilled-Water-Served)
  location: 2F Common Public
- equipment: AHU-2F-B
  equipment_class: AHU (Chilled-Water-Served)
  location: 2F Common Public
- equipment: AHU-3F-AM
  equipment_class: AHU (Chilled-Water-Served)
  location: 3F Amenity
- equipment: AHU-CASINO-1
  equipment_class: AHU (Modulating CHW-served)
  location: Ground Floor Casino
- equipment: AHU-CASINO-2
  equipment_class: AHU (Modulating CHW-served)
  location: Ground Floor Casino
- equipment: AHU-GF-CASINO
  equipment_class: AHU (Modulating CHW-served)
  location: Ground Floor Casino Lobby
- equipment: AHU-GF-LOB
  equipment_class: AHU (Chilled-Water-Served)
  location: Ground Floor Lobby
- equipment: AHU-GF-REST
  equipment_class: AHU (Chilled-Water-Served)
  location: Ground Floor Restaurant
- equipment: BLR-1
  equipment_class: Steam Boiler
  location: Lower Ground Boiler Room
- equipment: BLR-2
  equipment_class: Steam Boiler
  location: Lower Ground Boiler Room
- equipment: BTU-CHW-MAIN
  equipment_class: BTU Meter
  location: 2F Chiller Plant Room
- equipment: CALOR-LG
  equipment_class: Calorifier (Hot Water Storage Tank)
  location: Lower Ground Calorifier Room
- equipment: CALOR-ROOF
  equipment_class: Calorifier (Hot Water Storage Tank)
  location: Roofdeck DOAS
- equipment: CH-1
  equipment_class: Chiller (Package Water-Cooled)
  location: 2F Chiller Plant Room
- equipment: CH-2
  equipment_class: Chiller (Package Water-Cooled)
  location: 2F Chiller Plant Room
- equipment: CHW-BYP
  equipment_class: CHW Bypass Header
  location: 2F Chiller Plant Room
- equipment: CHW-RET-HDR
  equipment_class: CHW Return Main Header
  location: 2F Chiller Plant Room
- equipment: CHW-SUP-HDR
  equipment_class: CHW Supply Main Header
  location: 2F Chiller Plant Room
- equipment: CHWP-1
  equipment_class: Primary CHW Pump
  location: 2F Chiller Plant Room
- equipment: CHWP-2
  equipment_class: Primary CHW Pump
  location: 2F Chiller Plant Room
- equipment: CHWP-3
  equipment_class: Primary CHW Pump (Standby)
  location: 2F Chiller Plant Room
- equipment: CT-1
  equipment_class: Cooling Tower
  location: Roofdeck Cooling Tower
- equipment: CT-2
  equipment_class: Cooling Tower
  location: Roofdeck Cooling Tower
- equipment: CT-COMMON
  equipment_class: Cooling Tower (Common)
  location: Roofdeck Cooling Tower
- equipment: CW-HDR
  equipment_class: Condenser Water Header
  location: Roofdeck Cooling Tower
- equipment: CWP-1
  equipment_class: Condenser Water Pump
  location: 2F Chiller Plant Room
- equipment: CWP-2
  equipment_class: Condenser Water Pump
  location: 2F Chiller Plant Room
- equipment: CWP-3
  equipment_class: Condenser Water Pump
  location: 2F Chiller Plant Room
- equipment: DOAS-2F
  equipment_class: DOAS Unit
  location: 2F Common Public
- equipment: DOAS-RD1
  equipment_class: DOAS Unit
  location: Roofdeck DOAS
- equipment: DOAS-RD2
  equipment_class: DOAS Unit
  location: Roofdeck DOAS
- equipment: EAS-GEN-2F
  equipment_class: Exhaust Fan (General)
  location: 2F Common Public
- equipment: EAS-GEN-3F
  equipment_class: Exhaust Fan (General)
  location: 3F Amenity
- equipment: EAS-GEN-BSMT
  equipment_class: Exhaust Fan (General)
  location: Basement BOH
- equipment: EAS-GEN-GF
  equipment_class: Exhaust Fan (General)
  location: Ground Floor Lobby
- equipment: EAS-GEN-ROOF
  equipment_class: Exhaust Fan (General)
  location: Roofdeck DOAS
- equipment: EAS-TOILET-2F
  equipment_class: Exhaust Fan (Toilet)
  location: 2F Common Public
- equipment: EAS-TOILET-3F
  equipment_class: Exhaust Fan (Toilet)
  location: 3F Amenity
- equipment: EAS-TOILET-BSMT
  equipment_class: Exhaust Fan (Toilet)
  location: Basement BOH
- equipment: EAS-TOILET-GF
  equipment_class: Exhaust Fan (Toilet)
  location: Ground Floor Lobby
- equipment: HP-LG-1
  equipment_class: Heat Pump
  location: Lower Ground Calorifier Room
- equipment: HP-ROOF-1
  equipment_class: Heat Pump
  location: Roofdeck DOAS
- equipment: HW-HEADERS-LG
  equipment_class: Hot Water Header Set
  location: Lower Ground Calorifier Room
- equipment: HW-PUMP-LG-1
  equipment_class: Recirculating Pump
  location: Lower Ground Calorifier Room
- equipment: HW-PUMP-LG-2
  equipment_class: Recirculating Pump
  location: Lower Ground Calorifier Room
- equipment: HW-PUMP-ROOF-1
  equipment_class: Recirculating Pump
  location: Roofdeck DOAS
- equipment: OZ-CASINO-1
  equipment_class: Ozone Generator (UV-light or Corona)
  location: Ground Floor Casino
- equipment: PAHU-2F
  equipment_class: Precooled Air Handling Unit
  location: 2F Common Public
- equipment: PAHU-BSMT
  equipment_class: Precooled Air Handling Unit
  location: Basement BOH
- equipment: PAHU-ROOF
  equipment_class: Precooled Air Handling Unit
  location: Roofdeck DOAS
- equipment: PM-AIR-2F
  equipment_class: Multifunction Power Meter (Feeder)
  location: 2F Common Public
- equipment: PM-AIR-GF
  equipment_class: Multifunction Power Meter (Feeder)
  location: Ground Floor Lobby
- equipment: PM-BOILER
  equipment_class: Multifunction Power Meter (Feeder)
  location: Lower Ground Boiler Room
- equipment: PM-CASINO
  equipment_class: Multifunction Power Meter (Feeder)
  location: Ground Floor Casino
- equipment: PM-CHILLER
  equipment_class: Multifunction Power Meter (Feeder)
  location: 2F Chiller Plant Room
- equipment: PM-COOLING
  equipment_class: Multifunction Power Meter (Feeder)
  location: Roofdeck Cooling Tower
- equipment: PM-FIREPMP
  equipment_class: Multifunction Power Meter (Feeder)
  location: Lower Ground Boiler Room
- equipment: PM-MAIN-LG
  equipment_class: Multifunction Power Meter (Main)
  location: Lower Ground Main Switchgear
- equipment: PM-PLUMB
  equipment_class: Multifunction Power Meter (Feeder)
  location: Lower Ground Calorifier Room
integrated_test_inventory:
- Chiller plant sequencing (chiller staging + CHW pump + COW pump + cooling tower fan)
- CHW differential pressure control (PCHWP VFD speed via header dP)
- AHU supply-air temperature control (modulating CHW valve loop)
- DOAS demand-controlled ventilation (CO2-based fresh air modulation)
- Hotwater system sequencing (heat pump + recirculating pump + tank temp)
- Boiler firing rate vs. steam pressure
- Cooling tower fan staging vs. condenser water temperature
- Energy savings algorithm verification (max-demand limiting + load shedding)
notes:
- 'P2P = point-to-point verification: every physical I/O calibrated, range-checked, polarity verified, scaled correctly.'
- 'Functional test: per-equipment sequence verification (e.g., does the AHU CHW valve modulate correctly to maintain supply air temp?).'
- 'Integrated test: cross-system sequence (e.g., chiller staging triggers correctly when load increases).'
- "Owner T&C / SAT: separate from this \u2014 handled in proposal as an item under 5.5 in WBS."