# A4 — Panel Schedule
# Generated from A1-io-list.yaml
#
metadata:
  project: "Kingsford Hotel Bacolod \u2014 BMS (AB-Run-2)"
  generated_from: A1-io-list.yaml
  generator: _playbook/tools/generate-a4-panel-schedule.py
  controller_sizing_rule: 1 DDC controller per 40 physical I/O, +1 network gateway if Network drops present. Refine after Q-008 confirms wiring topology.
  power_estimate_basis: ~25W per controller, ~5W per network device. Excludes UPS/transformer overhead.
summary:
  total_panels: 11
  total_physical_io: 383
  total_hli_subpoints: 79
  total_network_drops: 12
  total_io_points: 474
  total_controllers_estimated: 20
  total_power_watts_estimated: 560
  panel_summary_table:
  - panel: PNL-AIR-2F
    location: 2F Common Public
    physical_io: 70
    network: 1
    controllers: 2
    power_w: 55
    equipment_count: 7
  - panel: PNL-AIR-3F
    location: 3F Amenity
    physical_io: 20
    network: 0
    controllers: 1
    power_w: 25
    equipment_count: 3
  - panel: PNL-AIR-BSMT
    location: Basement BOH
    physical_io: 18
    network: 0
    controllers: 1
    power_w: 25
    equipment_count: 3
  - panel: PNL-AIR-GF
    location: Ground Floor Lobby / Ground Floor Restaurant
    physical_io: 34
    network: 1
    controllers: 2
    power_w: 55
    equipment_count: 5
  - panel: PNL-AIR-ROOF
    location: Roofdeck DOAS
    physical_io: 70
    network: 0
    controllers: 2
    power_w: 50
    equipment_count: 7
  - panel: PNL-BLR-LG
    location: Lower Ground Boiler Room
    physical_io: 32
    network: 1
    controllers: 2
    power_w: 55
    equipment_count: 3
  - panel: PNL-CASINO-GF
    location: Ground Floor Casino / Ground Floor Casino Lobby
    physical_io: 45
    network: 1
    controllers: 2
    power_w: 55
    equipment_count: 5
  - panel: PNL-CH-PLANT-2F
    location: 2F Chiller Plant Room
    physical_io: 59
    network: 4
    controllers: 2
    power_w: 70
    equipment_count: 13
  - panel: PNL-CT-ROOF
    location: Roofdeck Cooling Tower
    physical_io: 22
    network: 1
    controllers: 2
    power_w: 55
    equipment_count: 5
  - panel: PNL-PL-LG
    location: Lower Ground Boiler Room / Lower Ground Calorifier Room
    physical_io: 13
    network: 2
    controllers: 2
    power_w: 60
    equipment_count: 7
  - panel: PNL-PM-LG
    location: Lower Ground Main Switchgear
    physical_io: 0
    network: 1
    controllers: 2
    power_w: 55
    equipment_count: 1
panels:
- id: PNL-AIR-2F
  location: 2F Common Public
  system_scope:
  - Air Conditioning
  - Exhaust
  - Power Monitoring
  - Ventilation
  equipment_served:
    instance_count: 7
    instances:
    - AHU-2F-A
    - AHU-2F-B
    - DOAS-2F
    - EAS-GEN-2F
    - EAS-TOILET-2F
    - PAHU-2F
    - PM-AIR-2F
    by_class:
      AHU (Chilled-Water-Served): 28
      DOAS Unit: 24
      Precooled Air Handling Unit: 12
      Multifunction Power Meter (Feeder): 5
      Exhaust Fan (Toilet): 3
      Exhaust Fan (General): 3
  io_summary:
    physical_io: 70
    hli_subpoints: 4
    network_drops: 1
    total: 75
    by_type:
      AI: 24
      AO: 15
      DI: 31
      HLI: 4
      Network: 1
    by_co:
      BMS Contractor: 22
      Equipment Supplier: 39
      ME Contractor: 14
  controller_estimate:
    ddc_controllers: 2
    network_gateway: 1
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 55
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: PNL-AIR-3F
  location: 3F Amenity
  system_scope:
  - Air Conditioning
  - Exhaust
  equipment_served:
    instance_count: 3
    instances:
    - AHU-3F-AM
    - EAS-GEN-3F
    - EAS-TOILET-3F
    by_class:
      AHU (Chilled-Water-Served): 14
      Exhaust Fan (Toilet): 3
      Exhaust Fan (General): 3
  io_summary:
    physical_io: 20
    hli_subpoints: 0
    network_drops: 0
    total: 20
    by_type:
      AI: 5
      AO: 4
      DI: 11
    by_co:
      BMS Contractor: 4
      Equipment Supplier: 12
      ME Contractor: 4
  controller_estimate:
    ddc_controllers: 1
    network_gateway: 0
    total_controllers: 1
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 25
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: PNL-AIR-BSMT
  location: Basement BOH
  system_scope:
  - Exhaust
  - Ventilation
  equipment_served:
    instance_count: 3
    instances:
    - EAS-GEN-BSMT
    - EAS-TOILET-BSMT
    - PAHU-BSMT
    by_class:
      Precooled Air Handling Unit: 12
      Exhaust Fan (Toilet): 3
      Exhaust Fan (General): 3
  io_summary:
    physical_io: 18
    hli_subpoints: 0
    network_drops: 0
    total: 18
    by_type:
      AI: 4
      AO: 3
      DI: 11
    by_co:
      BMS Contractor: 3
      Equipment Supplier: 13
      ME Contractor: 2
  controller_estimate:
    ddc_controllers: 1
    network_gateway: 0
    total_controllers: 1
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 25
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: PNL-AIR-GF
  location: Ground Floor Lobby / Ground Floor Restaurant
  system_scope:
  - Air Conditioning
  - Exhaust
  - Power Monitoring
  equipment_served:
    instance_count: 5
    instances:
    - AHU-GF-LOB
    - AHU-GF-REST
    - EAS-GEN-GF
    - EAS-TOILET-GF
    - PM-AIR-GF
    by_class:
      AHU (Chilled-Water-Served): 28
      Multifunction Power Meter (Feeder): 5
      Exhaust Fan (Toilet): 3
      Exhaust Fan (General): 3
  io_summary:
    physical_io: 34
    hli_subpoints: 4
    network_drops: 1
    total: 39
    by_type:
      AI: 10
      AO: 8
      DI: 16
      HLI: 4
      Network: 1
    by_co:
      BMS Contractor: 13
      Equipment Supplier: 18
      ME Contractor: 8
  controller_estimate:
    ddc_controllers: 1
    network_gateway: 1
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 55
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: PNL-AIR-ROOF
  location: Roofdeck DOAS
  system_scope:
  - Exhaust
  - Hot Water
  - Ventilation
  equipment_served:
    instance_count: 7
    instances:
    - CALOR-ROOF
    - DOAS-RD1
    - DOAS-RD2
    - EAS-GEN-ROOF
    - HP-ROOF-1
    - HW-PUMP-ROOF-1
    - PAHU-ROOF
    by_class:
      DOAS Unit: 48
      Precooled Air Handling Unit: 12
      Exhaust Fan (General): 3
      Heat Pump: 3
      Recirculating Pump: 3
      Calorifier (Hot Water Storage Tank): 1
  io_summary:
    physical_io: 70
    hli_subpoints: 0
    network_drops: 0
    total: 70
    by_type:
      AI: 25
      AO: 11
      DI: 34
    by_co:
      BMS Contractor: 16
      Equipment Supplier: 44
      ME Contractor: 10
  controller_estimate:
    ddc_controllers: 2
    network_gateway: 0
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 50
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: PNL-BLR-LG
  location: Lower Ground Boiler Room
  system_scope:
  - Boiler
  - Power Monitoring
  equipment_served:
    instance_count: 3
    instances:
    - BLR-1
    - BLR-2
    - PM-BOILER
    by_class:
      Steam Boiler: 32
      Multifunction Power Meter (Feeder): 5
  io_summary:
    physical_io: 32
    hli_subpoints: 4
    network_drops: 1
    total: 37
    by_type:
      AI: 8
      DI: 22
      DO: 2
      HLI: 4
      Network: 1
    by_co:
      BMS Contractor: 17
      Equipment Supplier: 20
  controller_estimate:
    ddc_controllers: 1
    network_gateway: 1
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 55
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: PNL-CASINO-GF
  location: Ground Floor Casino / Ground Floor Casino Lobby
  system_scope:
  - Air Conditioning
  - Casino Air Conditioning
  - Power Monitoring
  equipment_served:
    instance_count: 5
    instances:
    - AHU-CASINO-1
    - AHU-CASINO-2
    - AHU-GF-CASINO
    - OZ-CASINO-1
    - PM-CASINO
    by_class:
      AHU (Modulating CHW-served): 42
      Multifunction Power Meter (Feeder): 5
      Ozone Generator (UV-light or Corona): 3
  io_summary:
    physical_io: 45
    hli_subpoints: 4
    network_drops: 1
    total: 50
    by_type:
      AI: 24
      AO: 12
      DI: 8
      DO: 1
      HLI: 4
      Network: 1
    by_co:
      BMS Contractor: 17
      Equipment Supplier: 21
      ME Contractor: 12
  controller_estimate:
    ddc_controllers: 2
    network_gateway: 1
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 55
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: PNL-CH-PLANT-2F
  location: 2F Chiller Plant Room
  system_scope:
  - Chilled Water Plant
  - Condenser Water Loop
  - Power Monitoring
  equipment_served:
    instance_count: 13
    instances:
    - BTU-CHW-MAIN
    - CH-1
    - CH-2
    - CHW-BYP
    - CHW-RET-HDR
    - CHW-SUP-HDR
    - CHWP-1
    - CHWP-2
    - CHWP-3
    - CWP-1
    - CWP-2
    - CWP-3
    - PM-CHILLER
    by_class:
      Chiller (Package Water-Cooled): 56
      Primary CHW Pump: 14
      Condenser Water Pump: 12
      Primary CHW Pump (Standby): 7
      BTU Meter: 5
      Multifunction Power Meter (Feeder): 5
      CHW Bypass Header: 4
      CHW Supply Main Header: 2
      CHW Return Main Header: 2
  io_summary:
    physical_io: 59
    hli_subpoints: 44
    network_drops: 4
    total: 107
    by_type:
      AI: 26
      AO: 3
      DI: 23
      DO: 7
      HLI: 44
      Network: 4
    by_co:
      BMS Contractor: 32
      Equipment Supplier: 71
      ME Contractor: 4
  controller_estimate:
    ddc_controllers: 2
    network_gateway: 1
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 70
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: PNL-CT-ROOF
  location: Roofdeck Cooling Tower
  system_scope:
  - Condenser Water Loop
  - Power Monitoring
  equipment_served:
    instance_count: 5
    instances:
    - CT-1
    - CT-2
    - CT-COMMON
    - CW-HDR
    - PM-COOLING
    by_class:
      Cooling Tower: 14
      Cooling Tower (Common): 6
      Multifunction Power Meter (Feeder): 5
      Condenser Water Header: 2
  io_summary:
    physical_io: 22
    hli_subpoints: 4
    network_drops: 1
    total: 27
    by_type:
      AI: 7
      DI: 11
      DO: 4
      HLI: 4
      Network: 1
    by_co:
      BMS Contractor: 19
      Equipment Supplier: 6
      ME Contractor: 2
  controller_estimate:
    ddc_controllers: 1
    network_gateway: 1
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 55
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: PNL-PL-LG
  location: Lower Ground Boiler Room / Lower Ground Calorifier Room
  system_scope:
  - Hot Water
  - Power Monitoring
  equipment_served:
    instance_count: 7
    instances:
    - CALOR-LG
    - HP-LG-1
    - HW-HEADERS-LG
    - HW-PUMP-LG-1
    - HW-PUMP-LG-2
    - PM-FIREPMP
    - PM-PLUMB
    by_class:
      Multifunction Power Meter (Feeder): 10
      Recirculating Pump: 6
      Hot Water Header Set: 3
      Heat Pump: 3
      Calorifier (Hot Water Storage Tank): 1
  io_summary:
    physical_io: 13
    hli_subpoints: 8
    network_drops: 2
    total: 23
    by_type:
      AI: 4
      DI: 9
      HLI: 8
      Network: 2
    by_co:
      BMS Contractor: 14
      Equipment Supplier: 9
  controller_estimate:
    ddc_controllers: 1
    network_gateway: 1
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 60
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: PNL-PM-LG
  location: Lower Ground Main Switchgear
  system_scope:
  - Power Monitoring
  equipment_served:
    instance_count: 1
    instances:
    - PM-MAIN-LG
    by_class:
      Multifunction Power Meter (Main): 8
  io_summary:
    physical_io: 0
    hli_subpoints: 7
    network_drops: 1
    total: 8
    by_type:
      HLI: 7
      Network: 1
    by_co:
      BMS Contractor: 8
  controller_estimate:
    ddc_controllers: 1
    network_gateway: 1
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 55
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''