# C1 — Contractor / Owner-Supplied Matrix

**Project:** Kingsford Hotel Bacolod — BMS Rehabilitation (A/B run)
**Generated from:** A1-io-list.yaml
**Generator:** `_playbook/tools/generate-c1-co-matrix.py`

This matrix shows, per equipment class, which **BMS-side field devices** are supplied by which party. It is the contractual-scope-boundary view derived from the points list `C/O` column.

Suppliers:
- **BMS Contractor** — we (the proposing party) supply
- **ME Contractor** — Mechanical contractor supplies (typically valves, dampers, motorized actuators)
- **EE Contractor** — Electrical contractor supplies (power metering related — varies by project)
- **Equipment Supplier** — Manufacturer / Equipment vendor supplies (auxiliary contacts on motors/pumps, native equipment data via BACnet/Modbus, VFDs)
- **Owner** — Customer / building owner supplies

---

## Overall Summary

| Supplier | Total BMS I/O Points | Share |
|----------|---------------------:|------:|
| Equipment Supplier | 469 | 61.5% |
| BMS Contractor | 206 | 27.0% |
| ME Contractor | 82 | 10.8% |
| EE Contractor | 5 | 0.7% |
| **Total** | **762** | **100%** |

---

## Per-Equipment-Class Breakdown

### AHU (Chilled-Water-Served)  ·  10 units, 140 I/O points

**Instances:** AHU-1.1, AHU-1.2, AHU-1.3, AHU-B.1, AHU-B.2, AHU-B.3, AHU-EL, AHU-FR2, AHU-FR3, AHU-PF

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 60 | Auxiliary Contact (20×), VFD (20×), Damper Controller (20×) |
| BMS Contractor | 50 | Temperature Sensor (40×), CO2 Sensor (10×) |
| ME Contractor | 30 | Damper Controller (20×), Electric Valve Actuator (10×) |

### Precooled Air Handling Unit  ·  8 units, 112 I/O points

**Instances:** PAHU-0.1, PAHU-B1, PAHU-B2, PAHU-B3, PAHU-FR, PAHU-PF, PAHU-RD.1, PAHU-RD.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 56 | Auxiliary Contact (24×), Damper Controller (16×), VFD (16×) |
| BMS Contractor | 40 | Temperature Sensor (16×), Flow Sensor (8×), Humidity Sensor (8×), RJ45 to edge switch (8×) |
| ME Contractor | 16 | Electric Valve Actuator (16×) |

### Exhaust Fan (Toilet)  ·  32 units, 96 I/O points

**Instances:** TEF-1.1, TEF-1.2, TEF-1.3, TEF-1.4, TEF-2.1, TEF-2.3, TEF-2B.3, TEF-3A.1, TEF-3A.2, TEF-3B.1, TEF-3C.1, TEF-3C.2, TEF-3D.1, TEF-3D.10, TEF-3D.11, TEF-3D.12, TEF-3D.13, TEF-3D.14, TEF-3D.15, TEF-3D.16, TEF-3D.17, TEF-3D.18, TEF-3D.19, TEF-3D.2, TEF-3D.20, TEF-3D.3, TEF-3D.4, TEF-3D.5, TEF-3D.6, TEF-3D.7, TEF-3D.8, TEF-3D.9

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 96 | Auxiliary Contact (96×) |

### Chiller (Package Water-Cooled)  ·  3 units, 90 I/O points

**Instances:** CH-1, CH-2, CH-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 57 | Chiller Native (54×), Chiller native BACnet (3×) |
| BMS Contractor | 21 | Temperature Sensor (12×), Flow Sensor (9×) |
| ME Contractor | 12 | Electric Valve Actuator (12×) |

### DOAS Unit  ·  3 units, 75 I/O points

**Instances:** DOAS-2M, DOAS-RD.1, DOAS-RD.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 42 | Auxiliary Contact (24×), VFD (12×), Temperature Sensor (3×), Humidity Sensor (3×) |
| BMS Contractor | 21 | Temperature Sensor (9×), Humidity Sensor (6×), Flow Sensor (3×), RJ45 to edge switch (3×) |
| ME Contractor | 12 | Damper Controller (6×), Electric Valve Actuator (6×) |

### Exhaust Fan (General)  ·  17 units, 51 I/O points

**Instances:** EF-1.2A, EF-1MR.1, EF-1ST0.1, EF-2.1, EF-2.2, EF-2.3, EF-2.4, EF-2B.1, EF-2B.2, EF-3GE.1, EF-3GE.2, EF-CHR.1, EF-CHR.2, EF-GS.1, EF-GS.2, EF-LPG.1, EF-MRF.1

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 51 | Auxiliary Contact (51×) |

### AHU (Modulating CHW-served)  ·  2 units, 34 I/O points

**Instances:** AHU-2M.1, AHU-2M.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 16 | Temperature Sensor (8×), Humidity Sensor (4×), CO2 Sensor (2×), CO Sensor (2×) |
| Equipment Supplier | 12 | Auxiliary Contact (4×), VFD (4×), Damper Controller (4×) |
| ME Contractor | 6 | Damper Controller (4×), Electric Valve Actuator (2×) |

### Steam Boiler  ·  2 units, 32 I/O points

**Instances:** BLR-1, BLR-2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 20 | Auxiliary Contact (16×), Level Sensor (4×) |
| BMS Contractor | 12 | Electric Valve Actuator (4×), Temperature Sensor (4×), Pressure Sensor (2×), Oxygen Sensor (2×) |

### Cooling Tower  ·  3 units, 21 I/O points

**Instances:** CT-1, CT-2, CT-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 9 | Level Sensor (6×), Electric Valve Actuator (3×) |
| Equipment Supplier | 6 | Auxiliary Contact (6×) |
| ME Contractor | 6 | Electric Valve Actuator (3×), pH/Cond Sensor (3×) |

### Heat Pump  ·  6 units, 18 I/O points

**Instances:** HP-HZ.1, HP-HZ.2, HP-HZ.3, HP-LZ.1, HP-LZ.2, HP-LZ.3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 18 | Auxiliary Contact (18×) |

### Recirculating Pump  ·  6 units, 18 I/O points

**Instances:** RP-HZ.1, RP-HZ.2, RP-HZ.3, RP-LZ.1, RP-LZ.2, RP-LZ.3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 18 | Auxiliary Contact (18×) |

### Primary CHW Pump  ·  3 units, 15 I/O points

**Instances:** PCHW-1, PCHW-2, PCHW-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 15 | Auxiliary Contact (9×), Pressure Sensor (3×), VFD (3×) |

### Condenser Water Pump  ·  3 units, 9 I/O points

**Instances:** PCOW-1, PCOW-2, PCOW-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 9 | Auxiliary Contact (9×) |

### Multifunction Power Meter (Main)  ·  4 units, 7 I/O points

**Instances:** ATS-1, GEN-1, PM-GEN, PM-MAIN

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| EE Contractor | 5 | Auxiliary Contact (5×) |
| BMS Contractor | 2 | Modbus RTU meter (2×) |

### Multifunction Power Meter (Feeder)  ·  7 units, 7 I/O points

**Instances:** PM-MCC-BOILER, PM-MCC-CHILLER, PM-MCC-CT, PM-MCC-FIRE-PUMP, PM-MCC-MDP-1, PM-MCC-MDP-2, PM-MCC-MDP-3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 7 | Modbus RTU meter (7×) |

### Ozone Generator (UV-light or Corona)  ·  2 units, 6 I/O points

**Instances:** ION-2M.1, ION-2M.2

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 4 | Auxiliary Contact (4×) |
| BMS Contractor | 2 | VOC Sensor (2×) |

### Calorifier (Hot Water Storage Tank)  ·  6 units, 6 I/O points

**Instances:** HWT-HZ.1, HWT-HZ.2, HWT-HZ.3, HWT-LZ.1, HWT-LZ.2, HWT-LZ.3

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 6 | Temperature Sensor (6×) |

### Hot Water Header Set  ·  2 units, 6 I/O points

**Instances:** HW-HDR-HZ, HW-HDR-LZ

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 6 | Temperature Sensor (6×) |

### Primary CHW Pump (Standby)  ·  1 unit, 5 I/O points

**Instances:** PCHW-S

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| Equipment Supplier | 5 | Auxiliary Contact (3×), Pressure Sensor (1×), VFD (1×) |

### Cooling Tower (Common)  ·  1 unit, 4 I/O points

**Instances:** CT-COMMON

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 4 | Temperature Sensor (3×), Humidity Sensor (1×) |

### CHW Bypass Header  ·  1 unit, 4 I/O points

**Instances:** CHW-BYPASS

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 4 | Electric Valve Actuator (2×), Diff. Pressure Sensor (1×), Diff. Temp Sensor (1×) |

### CHW Supply Main Header  ·  1 unit, 2 I/O points

**Instances:** CHW-HDR-S

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (1×), Pressure Sensor (1×) |

### CHW Return Main Header  ·  1 unit, 2 I/O points

**Instances:** CHW-HDR-R

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (1×), Pressure Sensor (1×) |

### Condenser Water Header  ·  1 unit, 2 I/O points

**Instances:** COW-HDR

| Supplier | I/O Count | Provides |
|----------|----------:|----------|
| BMS Contractor | 2 | Temperature Sensor (2×) |

---

## Notes for Proposal Inclusions/Exclusions

- BMS scope = BMS Contractor row(s) above. We supply these field devices, plus the BMS panels, controllers, network, head-end, programming, and T&C.
- Items marked **ME Contractor** or **Equipment Supplier** are **NOT in BMS supply scope** — they're supplied under Mechanical or Equipment contracts. BMS scope includes the *terminations* and *signal cables* to these devices, but not the devices themselves.
- This matrix feeds C3 (Inclusions / Exclusions / Clarifications) — the customer-facing summary of scope boundaries.