# A4 — Panel Schedule
# Generated from A1-io-list.yaml
#
metadata:
  project: "Kingsford Hotel Bacolod \u2014 BMS Rehabilitation (A/B run)"
  generated_from: A1-io-list.yaml
  generator: _playbook/tools/generate-a4-panel-schedule.py
  controller_sizing_rule: 1 DDC controller per 40 physical I/O, +1 network gateway if Network drops present. Refine after Q-008 confirms wiring topology.
  power_estimate_basis: ~25W per controller, ~5W per network device. Excludes UPS/transformer overhead.
summary:
  total_panels: 6
  total_physical_io: 629
  total_hli_subpoints: 110
  total_network_drops: 23
  total_io_points: 762
  total_controllers_estimated: 18
  total_power_watts_estimated: 565
  panel_summary_table:
  - panel: FCP-2F
    location: 2nd Floor / 2nd Floor (Casino)
    physical_io: 234
    network: 6
    controllers: 6
    power_w: 180
    equipment_count: 30
  - panel: FCP-3F
    location: 3rd Floor (Amenity) / 3rd Floor (Guestroom)
    physical_io: 81
    network: 0
    controllers: 3
    power_w: 75
    equipment_count: 27
  - panel: FCP-BSMT
    location: Basement / Basement (Genset) / Lower Ground
    physical_io: 72
    network: 1
    controllers: 2
    power_w: 55
    equipment_count: 15
  - panel: FCP-GF
    location: Ground Floor
    physical_io: 63
    network: 0
    controllers: 2
    power_w: 50
    equipment_count: 12
  - panel: FCP-RD
    location: Roofdeck
    physical_io: 113
    network: 4
    controllers: 3
    power_w: 95
    equipment_count: 19
  - panel: MCP-PLANT
    location: 2nd Floor (Plant Room)
    physical_io: 66
    network: 12
    controllers: 2
    power_w: 110
    equipment_count: 22
panels:
- id: FCP-2F
  location: 2nd Floor / 2nd Floor (Casino)
  system_scope:
  - AC
  - VENT
  equipment_served:
    instance_count: 30
    instances:
    - AHU-2M.1
    - AHU-2M.2
    - AHU-B.1
    - AHU-B.2
    - AHU-B.3
    - AHU-EL
    - AHU-FR2
    - AHU-FR3
    - AHU-PF
    - DOAS-2M
    - EF-2.1
    - EF-2.2
    - EF-2.3
    - EF-2.4
    - EF-2B.1
    - EF-2B.2
    - EF-CHR.1
    - EF-CHR.2
    - EF-GS.1
    - EF-GS.2
    - ION-2M.1
    - ION-2M.2
    - PAHU-B1
    - PAHU-B2
    - PAHU-B3
    - PAHU-FR
    - PAHU-PF
    - TEF-2.1
    - TEF-2.3
    - TEF-2B.3
    by_class:
      AHU (Chilled-Water-Served): 98
      Precooled Air Handling Unit: 70
      AHU (Modulating CHW-served): 34
      Exhaust Fan (General): 30
      DOAS Unit: 25
      Exhaust Fan (Toilet): 9
      Ozone Generator (UV-light or Corona): 6
  io_summary:
    physical_io: 234
    hli_subpoints: 32
    network_drops: 6
    total: 272
    by_type:
      AI: 81
      AO: 39
      DI: 114
      HLI: 32
      Network: 6
    by_co:
      BMS Contractor: 85
      Equipment Supplier: 146
      ME Contractor: 41
  controller_estimate:
    ddc_controllers: 6
    network_gateway: 1
    total_controllers: 6
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 180
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: FCP-3F
  location: 3rd Floor (Amenity) / 3rd Floor (Guestroom)
  system_scope:
  - VENT
  equipment_served:
    instance_count: 27
    instances:
    - EF-3GE.1
    - EF-3GE.2
    - TEF-3A.1
    - TEF-3A.2
    - TEF-3B.1
    - TEF-3C.1
    - TEF-3C.2
    - TEF-3D.1
    - TEF-3D.10
    - TEF-3D.11
    - TEF-3D.12
    - TEF-3D.13
    - TEF-3D.14
    - TEF-3D.15
    - TEF-3D.16
    - TEF-3D.17
    - TEF-3D.18
    - TEF-3D.19
    - TEF-3D.2
    - TEF-3D.20
    - TEF-3D.3
    - TEF-3D.4
    - TEF-3D.5
    - TEF-3D.6
    - TEF-3D.7
    - TEF-3D.8
    - TEF-3D.9
    by_class:
      Exhaust Fan (Toilet): 75
      Exhaust Fan (General): 6
  io_summary:
    physical_io: 81
    hli_subpoints: 0
    network_drops: 0
    total: 81
    by_type:
      DI: 81
    by_co:
      Equipment Supplier: 81
  controller_estimate:
    ddc_controllers: 3
    network_gateway: 0
    total_controllers: 3
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 75
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: FCP-BSMT
  location: Basement / Basement (Genset) / Lower Ground
  system_scope:
  - EE
  - HWL
  - VENT
  equipment_served:
    instance_count: 15
    instances:
    - ATS-1
    - BLR-1
    - BLR-2
    - GEN-1
    - HP-LZ.1
    - HP-LZ.2
    - HP-LZ.3
    - HW-HDR-LZ
    - HWT-LZ.1
    - HWT-LZ.2
    - HWT-LZ.3
    - PAHU-0.1
    - RP-LZ.1
    - RP-LZ.2
    - RP-LZ.3
    by_class:
      Steam Boiler: 32
      Precooled Air Handling Unit: 14
      Heat Pump: 9
      Recirculating Pump: 9
      Multifunction Power Meter (Main): 5
      Calorifier (Hot Water Storage Tank): 3
      Hot Water Header Set: 3
  io_summary:
    physical_io: 72
    hli_subpoints: 2
    network_drops: 1
    total: 75
    by_type:
      AI: 18
      AO: 4
      DI: 50
      HLI: 2
      Network: 1
    by_co:
      BMS Contractor: 23
      EE Contractor: 5
      Equipment Supplier: 45
      ME Contractor: 2
  controller_estimate:
    ddc_controllers: 2
    network_gateway: 1
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 55
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: FCP-GF
  location: Ground Floor
  system_scope:
  - AC
  - VENT
  equipment_served:
    instance_count: 12
    instances:
    - AHU-1.1
    - AHU-1.2
    - AHU-1.3
    - EF-1.2A
    - EF-1MR.1
    - EF-1ST0.1
    - EF-LPG.1
    - EF-MRF.1
    - TEF-1.1
    - TEF-1.2
    - TEF-1.3
    - TEF-1.4
    by_class:
      AHU (Chilled-Water-Served): 42
      Exhaust Fan (General): 15
      Exhaust Fan (Toilet): 12
  io_summary:
    physical_io: 63
    hli_subpoints: 6
    network_drops: 0
    total: 69
    by_type:
      AI: 15
      AO: 9
      DI: 39
      HLI: 6
    by_co:
      BMS Contractor: 15
      Equipment Supplier: 45
      ME Contractor: 9
  controller_estimate:
    ddc_controllers: 2
    network_gateway: 0
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 50
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: FCP-RD
  location: Roofdeck
  system_scope:
  - AC
  - HWL
  - VENT
  equipment_served:
    instance_count: 19
    instances:
    - COW-HDR
    - CT-1
    - CT-2
    - CT-3
    - CT-COMMON
    - DOAS-RD.1
    - DOAS-RD.2
    - HP-HZ.1
    - HP-HZ.2
    - HP-HZ.3
    - HW-HDR-HZ
    - HWT-HZ.1
    - HWT-HZ.2
    - HWT-HZ.3
    - PAHU-RD.1
    - PAHU-RD.2
    - RP-HZ.1
    - RP-HZ.2
    - RP-HZ.3
    by_class:
      DOAS Unit: 50
      Precooled Air Handling Unit: 28
      Cooling Tower: 21
      Heat Pump: 9
      Recirculating Pump: 9
      Cooling Tower (Common): 4
      Calorifier (Hot Water Storage Tank): 3
      Hot Water Header Set: 3
      Condenser Water Header: 2
  io_summary:
    physical_io: 113
    hli_subpoints: 12
    network_drops: 4
    total: 129
    by_type:
      AI: 39
      AO: 11
      DI: 63
      HLI: 12
      Network: 4
    by_co:
      BMS Contractor: 45
      Equipment Supplier: 66
      ME Contractor: 18
  controller_estimate:
    ddc_controllers: 3
    network_gateway: 1
    total_controllers: 3
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 95
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''
- id: MCP-PLANT
  location: 2nd Floor (Plant Room)
  system_scope:
  - AC
  - EE
  equipment_served:
    instance_count: 22
    instances:
    - CH-1
    - CH-2
    - CH-3
    - CHW-BYPASS
    - CHW-HDR-R
    - CHW-HDR-S
    - PCHW-1
    - PCHW-2
    - PCHW-3
    - PCHW-S
    - PCOW-1
    - PCOW-2
    - PCOW-3
    - PM-GEN
    - PM-MAIN
    - PM-MCC-BOILER
    - PM-MCC-CHILLER
    - PM-MCC-CT
    - PM-MCC-FIRE-PUMP
    - PM-MCC-MDP-1
    - PM-MCC-MDP-2
    - PM-MCC-MDP-3
    by_class:
      Chiller (Package Water-Cooled): 90
      Primary CHW Pump: 15
      Condenser Water Pump: 9
      Multifunction Power Meter (Feeder): 7
      Primary CHW Pump (Standby): 5
      CHW Bypass Header: 4
      CHW Supply Main Header: 2
      CHW Return Main Header: 2
      Multifunction Power Meter (Main): 2
  io_summary:
    physical_io: 66
    hli_subpoints: 58
    network_drops: 12
    total: 136
    by_type:
      AI: 31
      AO: 1
      DI: 34
      HLI: 58
      Network: 12
    by_co:
      BMS Contractor: 38
      Equipment Supplier: 86
      ME Contractor: 12
  controller_estimate:
    ddc_controllers: 2
    network_gateway: 1
    total_controllers: 2
    rule: 1 DDC per 40 physical I/O, plus 1 network gateway if BACnet/Modbus integration on panel
  power_estimate_w: 110
  enclosure_assumption: Wall-mount IP54 metal cabinet, sized per controller count + 30% spare
  notes: ''