# Instance: BMS Controller Panels for Kingsford Hotel Bacolod (A/B run)

**WBS leaves served:** 2.3.1–2.3.8, 3.4
**Module ref:** `_playbook/modules/bms/controller-panel.md`

## Project-specific parameter values

From `A4-panel-schedule.yaml`:
- 6 panels (1× MCP-PLANT + 5× FCPs)
- 18 controllers (per A4)
- I/O density: see A1 totals (≈762 rows; physical I/O ≈ 380, HLI ≈ 250, network ≈ 130)

## Per-panel summary

| Panel | Location | Equipment served | Controllers | Power |
|-------|----------|-----------------|-------------|-------|
| MCP-PLANT | 2F Plant Room | Chillers (×3), Primary CHW Pumps (×4), COW Pumps (×3), CHW Headers + Bypass, Power Meters | 6 | 250 W |
| FCP-RD | Roofdeck | Cooling Towers (×3 + common), DOAS-RD.1/RD.2, PAHU-RD.1/RD.2, Calorifier-HZ ×3, HW-HDR-HZ, HP-HZ ×3, RP-HZ ×3, COW-HDR | 4 | 110 W |
| FCP-2F | 2F BOH/Casino | AHU-B.1..3/PF/EL/FR2/FR3 (×7), PAHU-B.1..3/PF/FR (×5), AHU-2M.1/2.2 (×2), DOAS-2M, ION-2M.1/2 (×2), 2F exhaust (×13) | 4 | 95 W |
| FCP-GF | GF BOH | AHU-1.1/1.2/1.3 (×3), GF exhaust (×9) | 2 | 60 W |
| FCP-3F | 3F Amenity | 3F amenity AHU & general exhaust + 27× toilet/general exhaust | 1 | 65 W |
| FCP-BSMT | Basement / Lower Ground | BLR-1, BLR-2, HWT-LZ ×3, HW-HDR-LZ, HP-LZ ×3, RP-LZ ×3, GEN-1, ATS-1, PAHU-0.1 | 1 | 70 W |

## BOQ line items

Per the module's BOQ items table — multiplied by quantities above. Spare I/O ≥ 20% per A-012.

## Open assumptions

A-011 (panel layout), A-012 (spare 20%), A-004 (controller family).

## Cross-references

- Working docs: A1, A4, A5, A7, B4
- Assumptions: A-004, A-011, A-012
- Clarifications: Q-004